Investor-owned utilityCentral Maine Power (CMP) interconnection application
Central Maine Power (CMP) is an investor-owned utility serving 584,462 residential customers in Maine (EIA-861, 2025). Applications: Own online portal (CMP Interconnection Application Request Portal). Gridpol files Central Maine Power (CMP) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Partly researched from official sources. verify on first project: cmpco.com (Avangrid) timed out/blocked from our network - confirm portal URL, Level 1 document list, Level 1 email, steps to PTO and storage rules; Chapter 324 framework same as Versant.
Central Maine Power (CMP) at a glance
Central Maine Power Co (Avangrid (Iberdrola))
TypeInvestor-owned utility
EIA utility ID3266
Residential customers584,462 (EIA-861, 2025)
Net-metered residential customers16,367 (EIA-861, 2025)
Service territory14 counties in Maine
How to applyOwn online portal – CMP Interconnection Application Request Portal
Who submitsApplicant fills out CMP New Service Request online form before submitting portal application(s) (per CMP page snippet).
Export compensationNet billing – Net Energy Billing (MPUC Chapter 313)
Documents Central Maine Power (CMP) asks for
- Interconnection application formLevel 1 application for certified inverter-based facilities <=25 kW (Chapter 324) Gridpol prepares this.
- Interconnection agreementLevel 1 Interconnection Agreement (Forms and Agreements 3)
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Level 1 application (Chapter 324) | MPUC cost summary also lists $150 cost-sharing and $40 ombudsman fee for Level 1 |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 25 kW | Inverter-based, Chapter 324 |
Levels 2-4 per Chapter 324 (see Versant entry)
Sources
- CMP - Interconnection (search snippet; site unreachable): https://www.cmpco.com/w/interconnection (retrieved 2026-11-13)
- MPUC - Average Interconnection Costs (search snippet): https://www.maine.gov/mpuc/regulated-utilities/electricity/average-interconnection-costs (retrieved 2026-11-13)
Maine interconnection rule
Maine Public Utilities Commission
Interconnection rule65-407 C.M.R. Chapter 324 – Small Generator Interconnection Procedures · source
Applies toTransmission and distribution utilities (T&D Utilities: CMP, Versant Power and other entities owning T&D plant for compensation in Maine) for generators subject to Commission jurisdiction (not FERC-jurisdictional). Rule text does not separately address consumer-owned utilities.
Application formStatewide standard forms adopted by Commission order must be used for all interconnection applications, interconnection agreements and study agreements (Ch. 324 s.4); deviations need Commission approval
TimelinesCompleteness notice within 5 business days (10 business days to cure); Level 1 screens 10 business days, deemed approval after 20 business days; Level 2 screens 15 business days; executable agreement within 10 business days of passing screens; applicant returns executed agreement within 30 business days; utility site visit before Level 1 agreement. Agreement may be terminated if not energized within 12 months of approval.
FeesLevel 1: $100. Level 2: $100 + $2/kW of generator capacity. Higher levels: study costs per Ch. 324 s.3 cost responsibility.
InsuranceUtility may require insurance only above thresholds: inverter-based none <=1 MW, $1M >2-5 MW, $2M >5 MW; non-inverter none <=50 kW, $500k 50-500 kW, $1M 0.5-2 MW, $2M 2-5 MW, $3M >5 MW. No additional liability insurance for s.5-compliant facilities unless applicant agrees.
External disconnectUtility shall not require additional controls, expressly including a utility-accessible disconnect switch, for facilities certified under Ch. 324 s.5 (IEEE 1547/UL 1741).
Export compensationNet billing – 35-A M.R.S. s.3209-A (kWh credit) and s.3209-B (tariff rate); 65-407 C.M.R. Chapter 313 (Net Energy Billing)
Net energy billing for DG resources <5 MW (kWh-credit and tariff-rate programs). Unused kWh credits expire per Commission rule; value remitted to low-income programs. Heavily amended 2023-2025 (PL 2025 c.430 ends new agreements for utility-side-of-meter resources after 2025-12-31); check current Ch. 313 for new projects.
Not addressed in Ch. 324 text; Maine's consumer-owned T&D utilities are generally Commission-regulated T&D utilities - confirm applicability with the specific utility.
- 65-407 C.M.R. ch. 324 (LII): https://www.law.cornell.edu/regulations/maine/department-65/division-407/chapter-324 (retrieved 2026-11-13)
- Ch. 324 s.11 Level 1: https://www.law.cornell.edu/regulations/maine/65-407-C-M-R-ch-324-SS-11 (retrieved 2026-11-13)
- Ch. 324 s.12 Level 2: https://www.law.cornell.edu/regulations/maine/65-407-C-M-R-ch-324-SS-12 (retrieved 2026-11-13)
- Ch. 324 s.15 General provisions (insurance, disconnect): https://www.law.cornell.edu/regulations/maine/65-407-C-M-R-ch-324-SS-15 (retrieved 2026-11-13)
- 35-A M.R.S. s.3209-A Net energy billing: https://www.mainelegislature.org/legis/statutes/35-A/title35-Asec3209-A.html (retrieved 2026-11-13)
- MPUC Order Adopting Rule, Docket 2023-00103: https://www.maine.gov/mpuc/sites/maine.gov.mpuc/files/inline-files/PUC%20Order%20Ch.%20324%2011-3-23.docx (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.