Home › Utilities › Maine

Maine

Maine interconnection applications

9 electric utilities serve Maine (EIA-861, 2025): 2 investor-owned utilitys, 2 electric cooperatives, 5 municipal utilitys. Together they serve 746,186 residential customers; 18,997 residential customers were on net metering at year-end 2025.

Largest utilities in Maine

Central Maine Power (CMP)Partly researched

Investor-owned utility · 584,462 residential customers · Maine

Applications: Own online portal – CMP Interconnection Application Request Portal

Interconnection process and documents →
Versant PowerProcess verified

Investor-owned utility · 137,839 residential customers · Maine

Applications: Own online portal – Adobe Sign e-sign application (Level 1 / Levels 2-4)

Interconnection process and documents →
Eastern Maine Electric CooperativeState guidance

Electric cooperative · 10,808 residential customers · Maine

Interconnection process and documents →
Kennebunk Light & Power DistrictState guidance

Municipal utility · 6,723 residential customers · Maine

Interconnection process and documents →
Houlton Water CompanyState guidance

Municipal utility · 3,907 residential customers · Maine

Interconnection process and documents →
Town of MadisonState guidance

Municipal utility · 2,447 residential customers · Maine

Interconnection process and documents →
Fox Islands Electric Cooperative, Inc.State guidance

Electric cooperative · 2,151 customers · Maine

Interconnection process and documents →
Van Buren Light & Power DistrictState guidance

Municipal utility · 1,369 customers · Maine

Interconnection process and documents →
Matinicus Plantation Electric CompanyState guidance

Municipal utility · 132 customers · Maine

Interconnection process and documents →

Export compensation among the researched Maine utilities: Net billing. Rules differ by utility – see each utility page.

Maine interconnection rule

Commission

Maine Public Utilities Commission

Interconnection rule

65-407 C.M.R. Chapter 324 – Small Generator Interconnection Procedures · source

Applies to

Transmission and distribution utilities (T&D Utilities: CMP, Versant Power and other entities owning T&D plant for compensation in Maine) for generators subject to Commission jurisdiction (not FERC-jurisdictional). Rule text does not separately address consumer-owned utilities.

Application form

Statewide standard forms adopted by Commission order must be used for all interconnection applications, interconnection agreements and study agreements (Ch. 324 s.4); deviations need Commission approval

Timelines

Completeness notice within 5 business days (10 business days to cure); Level 1 screens 10 business days, deemed approval after 20 business days; Level 2 screens 15 business days; executable agreement within 10 business days of passing screens; applicant returns executed agreement within 30 business days; utility site visit before Level 1 agreement. Agreement may be terminated if not energized within 12 months of approval.

Fees

Level 1: $100. Level 2: $100 + $2/kW of generator capacity. Higher levels: study costs per Ch. 324 s.3 cost responsibility.

Insurance

Utility may require insurance only above thresholds: inverter-based none <=1 MW, $1M >2-5 MW, $2M >5 MW; non-inverter none <=50 kW, $500k 50-500 kW, $1M 0.5-2 MW, $2M 2-5 MW, $3M >5 MW. No additional liability insurance for s.5-compliant facilities unless applicant agrees.

External disconnect

Utility shall not require additional controls, expressly including a utility-accessible disconnect switch, for facilities certified under Ch. 324 s.5 (IEEE 1547/UL 1741).

Export compensation

Net billing – 35-A M.R.S. s.3209-A (kWh credit) and s.3209-B (tariff rate); 65-407 C.M.R. Chapter 313 (Net Energy Billing)
Net energy billing for DG resources <5 MW (kWh-credit and tariff-rate programs). Unused kWh credits expire per Commission rule; value remitted to low-income programs. Heavily amended 2023-2025 (PL 2025 c.430 ends new agreements for utility-side-of-meter resources after 2025-12-31); check current Ch. 313 for new projects.

Not bound by the rule

Not addressed in Ch. 324 text; Maine's consumer-owned T&D utilities are generally Commission-regulated T&D utilities - confirm applicability with the specific utility.

LevelUp toCriteria / review / fee
Level 125 kWinverter-based generators not greater than 25 kW; screens s.7(A),(E),(I) (+ s.9(A) for networks) · completeness 5 business days; screens 10 business days after complete; agreement 10 business days; deemed approved if no decision in 20 business days · $100
Level 22000 kWgenerators not greater than 2 MW passing screens s.7(A)-(J) · completeness 5 business days; screens 15 business days after complete; agreement 10 business days · $100 + $2/kW
Level 310000 kWnon-exporting generators not greater than 10 MW · $100 + $3/kW (per CMP summary; not confirmed in current rule text)
Level 4all generators not subject to FERC jurisdiction not qualifying for Levels 1-3; feasibility/impact/facilities studies; site control documentation required

All 9 utilities in Maine

Residential customers in Maine per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited