Home › Utilities › Kentucky › Kentucky Power
Investor-owned utilityKentucky Power interconnection application
Kentucky Power is an investor-owned utility serving 130,322 residential customers in Kentucky (EIA-861, 2025). Applications: PowerClerk (AEP PowerClerk). Gridpol files Kentucky Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Kentucky Power’s official sources (see below). Fee amounts not stated; verify on first project.
Kentucky Power at a glance
Kentucky Power Co (American Electric Power)
TypeInvestor-owned utility
EIA utility ID22053
Residential customers130,322 (EIA-861, 2025)
Net-metered residential customers339 (EIA-861, 2025)
Service territory20 counties in Kentucky
How to applyPowerClerk – AEP PowerClerk · official link
Who submitsAccount owner applies via PowerClerk (installer may be listed as alternate contact on form); PowerClerk registration required.
Export compensationNet billing – Net Metering Service II (NMS II)
Excess energy credited at generation rate set by PSC.
Interconnection Service Agreement approval within 35 days of fully completed application for most homeowners (90-95% approved on first review).
Documents Kentucky Power asks for
- Interconnection application formLevel 1 (<=45 kW, UL 1741 inverter) or Level 2 Interconnection and Net Metering Application Gridpol prepares this.
- Inverter spec sheetUL 1741 certification documentation
- Site plan / site layoutShows meter, energy source, disconnect, inverter Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Proof of insuranceLiability insurance (checklist)
- Final inspection sign-offPermits / proof of local inspection
- Interconnection agreementInterconnection Service Agreement
How the Kentucky Power process runs
- Register in PowerClerk and submit application with fees and signature.
- Technical review.
- Sign Interconnection Service Agreement, pay any equipment costs.
- Install with AC disconnect adjacent to meter; local permits/inspection.
- Notify for post-installation field verification.
- Bi-directional meter installed; Permission to Operate letter.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 45 kW | inverter-based, UL 1741 |
| Net metering cap | 45 kW |
NMS II eligibility up to 45 kW.
Storage, EV and stamps
Battery storage
Battery storage requires a valid tariff option and the DER interconnection process; application asks battery power rating.
Sources
- Kentucky Power Generating Equipment: https://www.kentuckypower.com/builders/GeneratingEquipment.aspx (retrieved 2026-11-13)
- Kentucky Power Quick-Start Guide: https://www.kentuckypower.com/lib/docs/cleanenergy/renewable/solar/QuickStartGuide-KentuckyPower.pdf (retrieved 2026-11-13)
- KP Net Metering Customer Package 2021: https://www.kentuckypower.com/lib/docs/business/builders/KPNetMeteringCustomerPackage2021.pdf (retrieved 2026-11-13)
Other utilities in Kentucky
- KU454,021
- LG&E388,146
- Duke Energy140,950
- South Kentucky Rural E C C65,346
- Owen Electric Cooperative Inc.65,069
- Blue Grass Energy Cooperative Corporation61,870
- Warren Rural Electric Cooperative Corporation61,500
- Salt River Electric Cooperative Corporation54,002
- Jackson Energy Cooperative Corporation49,590
- Kenergy Corporation47,514
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.