Xcel Energy (Colorado) is an investor-owned utility serving 1,379,910 residential customers in Colorado (EIA-861, 2025). Applications: Own online portal (Xcel Energy Colorado DER Interconnection Application Portal (Salesforce-based, co.my.xcelenergy.com)). Gridpol files Xcel Energy (Colorado) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Xcel Energy (Colorado)’s official sources (see below). Process guide dated 2022 and RBC guide 2024; confirm current fee schedule, portal URL and RBC product availability on first project.

Xcel Energy (Colorado) at a glance

Utility

Public Service Co of Colorado (Xcel Energy)

Type

Investor-owned utility

EIA utility ID

15466

Residential customers

1,379,910 (EIA-861, 2025)

Net-metered residential customers

121,127 (EIA-861, 2025)

Service territory

56 counties in Colorado

How to apply

Own online portal – Xcel Energy Colorado DER Interconnection Application Portal (Salesforce-based, co.my.xcelenergy.com)

Who submits

Installer/developer normally initiates the application in the portal on the customer's behalf (application owner/agent); customer may also apply. Customer name on application must match the name on the Xcel Energy bill; account and premise numbers required. Interconnection/Solar agreements are e-signed by both the interconnection customer and the installer.

Export compensation

NEM – Net Energy Metering (with optional Solar*Rewards REC incentive)
Excess generation banked to the customer's virtual bank for future bills; Solar Bank Election form sets year-end treatment.

Review time (official)

Per Xcel portal guide: program review 2-3 business days; completeness review 10 business days (re-reviews 10 BD); Level 1 screens within 10 BD after deemed complete; Level 2 fast-track 15 BD; engineering review 10 BD (<10 kW DC) / 15 BD (>=10 kW DC); supplemental review 30 BD; agreements countersigned within 2 BD; final document review 3 BD; meter install/review within 20 BD of meter request. Application auto-withdrawn after 18 months.

Documents Xcel Energy (Colorado) asks for

  • Interconnection application formOnline application in DER portal (contact info, system details, application details) Gridpol prepares this.
  • Single-line diagram (one-line)One-line diagram; DC system size must match application; show battery configuration, PV production meter notes and 'Utility AC Disconnect' label + placard Gridpol prepares this.
  • Site plan / site layoutSite plan; Solar Team high-level review of site plan + line diagram Gridpol prepares this.
  • UL 1741 / IEEE 1547 certificationInverters must be UL 1741 certified and on the CEC Solar Equipment List
  • Battery spec sheet (when applicable)Storage: manufacturer, model, max continuous charge rate (kW), Storage Guidance Configuration (e.g. AC Net Metered Non-Export 2C, DC Net Metered 100% Renewable Export 3B/3BM), operating modes
  • Customer signatureE-signatures on Solar Agreements by customer and installer
  • Interconnection agreement (when applicable)SGIA required for systems >25 kW AC
  • Final inspection sign-offFinal electrical inspection uploaded to portal after construction
  • Other utility-specific document (when applicable)200% Rule support documentation if automatic 200% check fails; Solar Bank Election Form (Solar*Rewards/DG); Meter Collar Waiver if used; NABCEP form for Solar*Rewards; insurance only >= 1 MW AC

How the Xcel Energy (Colorado) process runs

  1. Initiate application in DER portal (installer), pay engineering/application fee; 200% Rule check
  2. Program review of site plan and line diagram
  3. Completeness review by engineering
  4. Engineering review / Level 1-2 screens (supplemental or study if needed)
  5. Study process if required
  6. Interconnection/Solar agreements e-signed by customer and installer; Xcel countersigns
  7. Design and construction; upload final electrical inspection (and NABCEP form for Solar*Rewards)
  8. Metering and testing: meter request, technician installs/reviews meter
  9. Permission to operate: door hanger plus automated PTO email from portal

Fees

FeeApplies toNote
$100<= 10 kW (application/initial study fee)2022 portal guide
$1,000>10 kW - 250 kW2022 portal guide
$2,000>250 kW - 2 MW2022 portal guide
$100 engineering feeBattery-only applications (Renewable Battery Connect)Solar+battery engineering fee based on solar kW AC; RBC application deposit $50/kW of max continuous charge rate (none for IQ/DIC), refunded if PTO within 18 months

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Small25 kW0.5-25 kW program tier
Medium500 kW25.01-500 kW
Large>500 kW up to 200% of annual load

Expected generation (PVWatts) plus other DG must not exceed 200% of prior-12-month consumption (200% Rule, checked automatically). Level 1 simplified / Level 2 fast-track / Level 3 study per CO PUC rules.

Storage, EV and stamps

Battery storage

Storage applied for in same portal (fuel type Energy Storage). Must declare Storage Guidance Configuration (e.g. AC Net Metered Non-Export 2C, DC Net Metered 100% Renewable Export 3B/3BM), operating modes, whether storage exports, whether 100% charged by NEM-eligible source. Renewable Battery Connect program (residential/small business, battery charged by on-site solar, internet connection, up to 60 utility-dispatched events/yr) has its own application products.

Common issues the utility lists

  • DC system size on site plan/line diagram does not match application
  • Battery details not entered exactly as on approved equipment list (manufacturer, model, charge rate, configuration)
  • Existing equipment (PV production meter, Utility AC Disconnect label/placard) not documented on one-line
  • kW AC of existing inverters not documented when adding battery to existing solar
  • Customer name not matching Xcel bill

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.