Colorado Springs Utilities interconnection application

Colorado Springs Utilities is a municipal utility serving 220,059 residential customers in Colorado (EIA-861, 2025). Applications: Own online portal (Connecting Solar portal (eTRACK+)). Gridpol files Colorado Springs Utilities interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Colorado Springs Utilities’s official sources (see below). Size limits (15 kW res / 100 kW business, 120% of usage) from V2.2024 application terms; confirm against current tariff.

Colorado Springs Utilities at a glance

Utility

City of Colorado Springs

Type

Municipal utility

EIA utility ID

3989

Residential customers

220,059 (EIA-861, 2025)

Net-metered residential customers

9,965 (EIA-861, 2025)

Service territory

2 counties in Colorado

How to apply

Own online portal – Connecting Solar portal (eTRACK+) · official link

Who submits

Installer (registered in eTRACK+ as Installer/Installer Master) creates the application for the customer; customer then gets an eTRACK+ invitation to track it. Self-installers can register. Installer acts with customer's consent to represent the customer; customer must own the premise and hold the CSU account; both initial/sign the application.

Export compensation

NEM – Renewable Energy Net Metering (Solar Energy Program)
Monthly net; credits banked; year-end positive balance paid on January bill at cogeneration rate (about $0.02/kWh) unless customer opts in to rollover.

Review time (official)

No official timeline published; approval or denial email sent to customer, installer and PPRBD. System must be completed within 12 months of application.

Documents Colorado Springs Utilities asks for

  • Interconnection application formSolar Energy Interconnection Application (completed in portal), CEC-listed equipment and PTC ratings Gridpol prepares this.
  • Net metering / net billing agreementSolar Energy Program Net Metering Agreement, signed
  • Site plan / site layoutShow all solar and meter equipment locations and production meter socket model Gridpol prepares this.
  • Single-line diagram (one-line)Electrical one-line diagram Gridpol prepares this.
  • PV module spec sheetEquipment specification sheets
  • Inverter spec sheetInverters must be on CEC list and meet PPRBD arc-fault requirements
  • Battery spec sheet (when applicable)Storage-only installs: provide ESS specification sheet
  • Photos (meter, main panel, equipment)Two revenue-meter photos: measured height of meter face from grade, and wide-angle photo with 3-ft minimum radius
  • Other utility-specific documentBuilding/solar shade analysis report; optional EV registration to raise usage basis
  • Customer signatureCustomer and installer initials/signature on application
  • Final inspection sign-offPPRBD 'ES' final electrical inspection; permit number entered in application

How the Colorado Springs Utilities process runs

  1. Installer registers/logs in to Connecting Solar portal (eTRACK+)
  2. Complete interconnection application and net metering agreement, upload documents; $100 fee billed
  3. CSU review; approval letter emailed to customer, installer and PPRBD (used for permitting) or denial with required updates
  4. Pull PPRBD permit and enter permit number in application; install (do not install before approval)
  5. PPRBD 'ES' final electrical inspection; PPRBD notifies CSU
  6. CSU installs net meter and production (REC) meter
  7. CSU issues Permission to Operate

Fees

FeeApplies toNote
$100Residential and small commercialBilled on customer's utility bill at submission
$1,000Large commercial >= 150 kW AC

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Residential15 kWMin 0.5 kW
Business100 kW

System must not exceed 120% of previous 12 months kWh at the premise meter (V2.2024 application terms).

Storage, EV and stamps

Battery storage

Energy-storage-only installation allowed on the application form (skip PV fields, attach ESS spec sheet). No further storage rules found on CSU pages.

EV chargers

Optional: newly registered EV (within 11 months) can be documented on the solar application to increase the annual consumption basis for sizing.

Common issues the utility lists

  • Incomplete application or missing required documentation (shade report, site plan, line diagram, meter photos, signed NMA, spec sheets) is denied
  • System would require modification of CSU facilities (right to deny)
  • Equipment not on CEC list

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.