Home › Utilities › Tennessee › Kingsport Power Company d/b/a AEP Appalachian Power

Investor-owned utility

Kingsport Power Company d/b/a AEP Appalachian Power interconnection application

Kingsport Power Company d/b/a AEP Appalachian Power is an investor-owned utility serving 43,364 residential customers in Tennessee (EIA-861, 2025). Applications: PowerClerk (AEP PowerClerk). Gridpol files Kingsport Power Company d/b/a AEP Appalachian Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Kingsport Power Company d/b/a AEP Appalachian Power’s official sources (see below). Confirmed from AEP Tennessee package. Not verified: process for >10 kW / non-inverter (contact apcodgcoordinator@aep.com), storage rules.

Kingsport Power Company d/b/a AEP Appalachian Power at a glance

Utility

Kingsport Power Co (American Electric Power (AEP))

Type

Investor-owned utility

EIA utility ID

10331

Residential customers

43,364 (EIA-861, 2025)

Net-metered residential customers

97 (EIA-861, 2025)

Service territory

3 counties in Tennessee

How to apply

PowerClerk – AEP PowerClerk · official link

Who submits

Customer submits Form NMIN-T (directly, by email/mail or AEP PowerClerk); licensed electrician and inverter vendor must sign the form. Not a TVA distributor (AEP-supplied, TPUC-regulated IOU).

Export compensation

NEM – Tariff N.M.S. (Net Metering Service Rider), T.P.U.C. Tariff No. 3 (Docket 21-00107, eff. Aug 8, 2022)
Monthly excess carried forward as kWh credit; no compensation for excess; end-of-period carryover limited to billed consumption.

Review time (official)

Notification at least 30 days (<=25 kW) / 60 days (>25 kW) before intended interconnection; Company returns valid form or incomplete form within 30 / 60 days (Tariff N.M.S. A.1-2).

Documents Kingsport Power Company d/b/a AEP Appalachian Power asks for

  • Interconnection application formForm NMIN-T Net Metering Interconnection Notification (2 pages); all sections and signatures required for valid notification Gridpol prepares this.
  • Final inspection sign-offLicensed electrician signature certifying installation per manufacturer specs and NEC
  • UL 1741 / IEEE 1547 certificationInverter vendor signs certifying UL1741; inverters must be UL1741 SB and IEEE 1547-2018 compliant (AEP TIIR)
  • Proof of insuranceCopy of policy with notification: >= $100,000 liability for <=10 kW; >= $300,000 for >10 kW
  • Single-line diagram (one-line)One-line diagram Gridpol prepares this.
  • Site plan / site layoutSketch layout Gridpol prepares this.
  • Other utility-specific document (when applicable)Proof of licensed electric vehicle (owned/leased) for residential limit increase to 15 kW

How the Kingsport Power Company d/b/a AEP Appalachian Power process runs

  1. Have all equipment needed for interconnection before notifying.
  2. Submit Form NMIN-T with $50 fee, insurance, one-line diagram and sketch by email/mail or aep.powerclerk.com (>=30 days before interconnection for <=25 kW).
  3. Company returns valid form or incomplete form within 30 days; resubmit if incomplete.
  4. Install with labeled lockable load-break disconnect near meter; electrician and vendor certifications.
  5. Leave generator OFF until APCo final review and meter exchange.

Fees

FeeApplies toNote
$50Inspection fee, required with all applicationsTN Net Metering Customer Package (Jan 2024)

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Residential (Tariff R.S.)10 kW10 kW AC; 15 kW AC with proof of owned/leased licensed EV
<=25 kW notification25 kW30-day notice
>25 kW60-day notice; contact Company before financial commitments; distribution impact conditions apply
Net metering cap10 kW

Annual output limited to historical annual consumption; program cap 1% of TN peak load forecast; eligible tariffs RS, SGS, MGS-Secondary, PS (no time-of-day).

Storage, EV and stamps

EV chargers

Net metering residential size limit rises from 10 kW to 15 kW AC with proof of a licensed EV owned or leased by the customer (Tariff N.M.S.). No EV load letter process found.

Common issues the utility lists

  • Incomplete NMIN-T (any missing section or signature) is returned; customer must resubmit after fixing deficiencies

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited