Municipal utilityNashville Electric Service (NES) interconnection application
Nashville Electric Service (NES) is a municipal utility serving 424,808 residential customers in Tennessee (EIA-861, 2025). Applications: PDF + email (NES Application for Interconnection (NESolar Savings & NESolar Connect) emailed to Renewables@NESPower.com; contracts signed via DocuSign). Gridpol files Nashville Electric Service (NES) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Nashville Electric Service (NES)’s official sources (see below). Application, documents, programs confirmed on NES PDFs. Verify on first project: current fee in NES Schedule of Fees and Charges, typical review time.
Nashville Electric Service (NES) at a glance
Nashville Electric Service (TVA local power company (municipal))
TypeMunicipal utility
EIA utility ID13216
Residential customers424,808 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory7 counties in Tennessee
How to applyPDF + email – NES Application for Interconnection (NESolar Savings & NESolar Connect) emailed to Renewables@NESPower.com; contracts signed via DocuSign · official link
Who submitsAccount holder (name must match NES account; authorized contact must be primary/secondary account holder or authorized corporate representative and signs via DocuSign). Project designer and solar contractor/installer listed on application (NABCEP level recommended).
Export compensationNet billing – NESolar Savings (excess purchase) / NESolar Connect (buy-all)
No net metering. NESolar Savings pays for exports at seasonal rate + TVA Total Monthly Fuel Cost (2024: summer $0.02916, winter $0.03083, transition $0.03147 per kWh + TMFC). NESolar Connect: $0.07031/$0.04267/$0.05433 + TMFC. TVA (wholesale supplier) role: Tennessee has no state net metering mandate and the TN PUC does not regulate TVA local power companies (LPCs); the LPC sets its own interconnection rules under its TVA wholesale contract. For export compensation from TVA, the customer first establishes an interconnection agreement with the LPC and can then register in TVA's Dispersed Power Production (DPP) program to sell all or excess generation to TVA at avoided cost (time-of-day rates); metering at customer expense to TVA specs. Some LPCs (under TVA Long-Term Partnership flexibility) instead buy excess generation in their own programs.
Application due no later than 60 days before production; formal engineering study may be required. No official review clock stated.
Wholesale supplier / associationTennessee Valley Authority (TVA) - local power company (distributor) network · TVA Dispersed Power Production (DPP) Guidelines + Dispersed Power Price Schedule CSPP (Attachment A)
Documents Nashville Electric Service (NES) asks for
- Interconnection application formNES Application for Interconnection of Renewable Generation - required in early planning, no later than 60 days before power production; total system cost required Gridpol prepares this.
- Customer signatureAuthorized customer signature (primary/secondary account holder)
- Single-line diagram (one-line)Detailed one-line diagram incl. wire/fuse sizes, inverters, breakers, relays, PV panel number/location; >50 kW show interlocks/anti-islanding operation Gridpol prepares this.
- Site plan / site layoutSite plan with address, billing and generation meter locations, inverter and panel locations; >50 kW AutoCAD in state plane coordinates Gridpol prepares this.
- Other utility-specific documentSite placard documentation: sunlight/weatherproof placard (no stickers) with system one-line, screwed/riveted at or in sight of utility solar disconnect, listing contractor and customer contacts
- Inverter spec sheetManufacturer cut sheets; UL 1741 and IEEE 1547 compliant
- PV module spec sheetPV panel cut sheets
- Battery spec sheet (when applicable)Battery manufacturer/model/chemistry/kW/kWh/cycle life, DC or AC coupled
- Interconnection agreementNES Interconnection and Operating Agreement (IOA) for each solar installation
- Net metering / net billing agreement (when applicable)NESolar Savings or NESolar Connect Power Purchase Agreement (if selling excess/all)
- Final inspection sign-offLocal building code official inspection/certification of solar and metering installation submitted to NES (Metro Codes electrical PV permit); NES Distributed Generation Checklist (commissioning)
- Other utility-specific document (when applicable)Operational Notice Form (to TVA) before production; Initiation Notice Form submitted by NES
How the Nashville Electric Service (NES) process runs
- Early planning: email NES Application for Interconnection with one-line, site plan, placard, cut sheets (no later than 60 days before operation); do not buy/install before written approval.
- NES review (engineering study if required); NES submits Initiation Notice to TVA; TVA approval if size requires.
- Sign IOA and NESolar Power Purchase Agreement via DocuSign.
- Install; Metro Codes electrical/PV permit inspection; submit inspection certification to NES.
- Operational Notice Form to TVA; NES commissioning per Distributed Generation Checklist; NES installs metering.
- Written authorization for parallel operation from NES.
Fees
| Fee | Applies to | Note |
|---|---|---|
| Per NES Schedule of Fees and Charges | Non-refundable application and engineering review charge (as applicable) | Charged to the NES account; amount not stated on application |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| NESolar Savings (behind-the-meter, excess sale) | 250 kW | <=250 kW DC; min 50 kWh avg monthly excess; sales <=100% of annual usage; program cap 10 MW |
| NESolar Connect (line-side, buy-all) | Min 200 kW solar (80 kW other); program cap 35 MW | |
| Facilities Study | 500 kW | Formal scoping for systems above 500 kW |
Systems may require TVA approval based on size; TVA transmission study/modeling for 5-25 MVA.
Storage, EV and stamps
Battery storage
Solar PV with battery storage is eligible under NESolar Savings; battery data required on application. NES may require equipment to prevent generation flowing to the grid per IOA.
Common issues the utility lists
- Placard showing only equipment layout (without one-line) or using stickers is not acceptable
- Customer name not matching NES account / signer not account holder
- NES may reject any energy resource posing safety risk or adverse system impact
Gridpol’s pre-submission check covers these before we file.
Sources
- NES Application for Interconnection for NESolar (8/19/24): https://www.nespower.com/-/media/project/nes/common/pdfs/nesolar-savings/application-for-interconnection-for-nesolar-8-19-24.pdf (retrieved 2026-11-13)
- NESolar Connect and NESolar Savings Guidelines (Aug 2024): https://www.nespower.com/-/media/project/nes/common/pdfs/nesolar-savings/nesolar-guidelines-082024.pdf (retrieved 2026-11-13)
- NES - Renewable Energy: https://www.nespower.com/clean-energy/renewable-energy/ (retrieved 2026-11-13)
- TVA Dispersed Power Production (DPP) Online Registration Process: https://www.tva.com/docs/default-source/1-float/dpp_customer_process_flow_finala99b8478-07f0-4731-89ce-f65bb2799261.pdf (retrieved 2026-11-13)
- TVA DPP program guidelines/pricing (Feb 28, 2022): https://www.tva.com/docs/default-source/1-float/march_2022_dpp_documents_for_publishinga32159c4-5499-417b-9b01-71e57b29f6df.pdf (retrieved 2026-11-13)
Other utilities in Tennessee
- Memphis Light, Gas and Water (MLGW)385,015
- Middle Tennessee Electric (MTE)311,520
- Knoxville Utilities Board (KUB)196,674
- EPB (Electric Power Board of Chattanooga)164,914
- Volunteer Electric Cooperative105,248
- Cumberland Electric Member Corporation101,734
- City of Clarksville77,509
- Johnson City72,729
- Duck River Electric Member Corporation71,969
- City of Lenoir63,379
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.