Home › Utilities › Tennessee › Middle Tennessee Electric (MTE)

Electric cooperative

Middle Tennessee Electric (MTE) interconnection application

Middle Tennessee Electric (MTE) is an electric cooperative serving 311,520 residential customers in Tennessee (EIA-861, 2025). Applications: PDF + mail (MTE Application for Interconnection of Distributed Generation + Interconnection Agreement (PDF) to MTE DER Coordinator (EnergyServices@mte.com)). Gridpol files Middle Tennessee Electric (MTE) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Middle Tennessee Electric (MTE)’s official sources (see below). Documents and steps confirmed. Verify on first project: submission channel (email vs. mail to DER coordinator), any application fee (see MTE Fee Descriptions), review time.

Middle Tennessee Electric (MTE) at a glance

Utility

Middle Tennessee E M C (TVA local power company (cooperative))

Type

Electric cooperative

EIA utility ID

12470

Residential customers

311,520 (EIA-861, 2025)

Net-metered residential customers

none reported

Service territory

8 counties in Tennessee

How to apply

PDF + mail – MTE Application for Interconnection of Distributed Generation + Interconnection Agreement (PDF) to MTE DER Coordinator (EnergyServices@mte.com) · official link

Who submits

Cooperative member signs as Interconnection Customer; system owner (if different) and NABCEP installer (company, contractor license #, NABCEP certification #) listed on application.

Export compensation

Avoided cost – Behind-the-meter self-consumption, or TVA Dispersed Power Production (excess sale)
No net metering. TVA (wholesale supplier) role: Tennessee has no state net metering mandate and the TN PUC does not regulate TVA local power companies (LPCs); the LPC sets its own interconnection rules under its TVA wholesale contract. For export compensation from TVA, the customer first establishes an interconnection agreement with the LPC and can then register in TVA's Dispersed Power Production (DPP) program to sell all or excess generation to TVA at avoided cost (time-of-day rates); metering at customer expense to TVA specs. Some LPCs (under TVA Long-Term Partnership flexibility) instead buy excess generation in their own programs.

Documents Middle Tennessee Electric (MTE) asks for

  • Interconnection application formMTE Application for Interconnection of Distributed Generation; indicate behind-the-meter or sell excess to TVA via DPP Gridpol prepares this.
  • Interconnection agreementMTE Interconnection, Metering, and Parallel Operation Agreement for Renewable Generation Systems - filled out, signed and approved before construction
  • Customer signatureThe account holder signs the application or authorization. We send the signature link.
  • Single-line diagram (one-line)Detailed one-line diagram Gridpol prepares this.
  • Inverter spec sheetInverter specs + NRTL testing/listing documentation
  • PV module spec sheetSolar panel specifications
  • Site plan / site layoutPhoto or sketch of proposed layout relative to existing electric service Gridpol prepares this.
  • Battery spec sheet (when applicable)Batteries listed as major equipment if included
  • Final inspection sign-offLocal building code official inspection/certification provided to MTE; MTE onsite inspection and commissioning witness or waiver
  • Proof of insurance (optional)Agreement only encourages equipment and liability insurance

How the Middle Tennessee Electric (MTE) process runs

  1. Download and complete Interconnection Application and Agreement (sign) before construction.
  2. MTE engineering reviews application, agreement, specs and drawings; identifies service upgrades (member pays).
  3. Executed agreement allows procurement and installation.
  4. Install with fused, lockable manual disconnect adjacent to meter socket and weatherproof single-line placard.
  5. Provide local code official inspection certification; MTE onsite inspection and commissioning test (or waiver); MTE installs metering at participant's expense.
  6. Written authorization for parallel operation; optional TVA DPP registration for excess sales.

Size levels and limits

LevelUp toNote
Residential documents process50 kW>50 kW or commercial: contact MTE EnergyPros for additional steps

Storage, EV and stamps

Battery storage

MTE publishes a Battery Energy Storage Systems page; batteries must be shown on the one-line diagram. No separate storage interconnection rules found.

Common issues the utility lists

  • Application considered complete only when all applicable and correct information is provided

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited