Municipal utilityCity of Tyndall interconnection application
City of Tyndall is a municipal utility serving 647 customers in South Dakota (EIA-861, 2025). Gridpol files City of Tyndall interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
South Dakota’s commission rule (ARSD 20:10:36 (Small Generator Interconnection)) does not bind municipal utilitys; City of Tyndall sets its own interconnection policy. We confirm its form on the first project. Electric cooperatives and municipal utilities are not rate-regulated by the PUC and set their own interconnection and buyback policies.
City of Tyndall at a glance
City of Tyndall
TypeMunicipal utility
EIA utility ID19333
Customers647 (EIA-861, 2025, short form: all customer classes)
Net-metered residential customersnone reported
Service territory1 county in South Dakota
Documents City of Tyndall asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for City of Tyndall. We confirm City of Tyndall’s exact list on the first project.
South Dakota interconnection rule
South Dakota Public Utilities Commission
Interconnection ruleARSD 20:10:36 (Small Generator Interconnection) – Small Generator Facility Interconnection · source
Applies toPublic utilities (PUC rate-regulated IOUs: Xcel/NSP, Black Hills, NorthWestern, MDU, Otter Tail) for facilities <=10 MW not under FERC/RTO jurisdiction
Application formCommission tier application forms (application forms available from the commission, 20:10:36:33); certificate of completion; interconnection agreement
TimelinesTier 1: acknowledgment within 3 business days, completeness within 10 BD, applicant 20 BD to cure, review within 15 BD after complete (20:10:36:33). Completion requires passed screens, code inspector approval, witness test if done, certificate of completion, executed agreement (20:10:36:34).
FeesTier 1 $50; Tier 2 $50 + $1/kW up to $500; Tier 3 and 4 $100 + $2/kW up to $1,000 (20:10:36:06).
InsuranceTier 1: proof of adequate homeowners/general/commercial liability; Tier 2 up to $500,000; Tiers 3-4 up to $1,000,000 at utility request (20:10:36:26). Endorsements (utility additional insured etc.) not required for residential <=10 kW (20:10:36:27).
External disconnectOnly if required by the utility: primary-line lockable visible-break device; secondary-line lockable device with clearly indicated status; lockbox alternative (20:10:36:15).
Export compensationNone statewide
No statewide net metering rule; compensation per utility tariff (e.g. avoided-cost/PURPA).
Electric cooperatives and municipal utilities are not rate-regulated by the PUC and set their own interconnection and buyback policies.
- ARSD 20:10:36 chapter index: https://sdlegislature.gov/api/Rules/20:10:36.html (retrieved 2026-11-13)
- ARSD 20:10:36:06 Application fees: https://sdlegislature.gov/api/Rules/20:10:36:06.html (retrieved 2026-11-13)
- ARSD 20:10:36:26 Insurance amounts: https://sdlegislature.gov/api/Rules/20:10:36:26.html (retrieved 2026-11-13)
- ARSD 20:10:36:33 Tier 1 review procedures: https://sdlegislature.gov/api/Rules/20:10:36:33.html (retrieved 2026-11-13)
Other utilities in South Dakota
- Xcel Energy (Minnesota)94,137
- Black Hills Energy (Black Hills Power)67,608
- NorthWestern Energy (South Dakota)51,787
- Sioux Valley SW Electric Cooperative22,989
- Southeastern Electric Cooperative Inc.20,959
- West River Electric Association Inc.18,975
- Watertown Municipal Utilities11,775
- City of Brookings10,769
- Black Hills Electric Cooperative, Inc.9,415
- Otter Tail Power9,094
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.