Investor-owned utilityOtter Tail Power interconnection application
Otter Tail Power is an investor-owned utility serving 104,750 residential customers in Minnesota, North Dakota, South Dakota (EIA-861, 2025). Applications: Own online portal (Otter Tail Simplified Application (Smartsheet form)). Gridpol files Otter Tail Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Otter Tail Power’s official sources (see below). Base application fee and timelines: see MN DIP; ND/SD processes not researched.
Otter Tail Power at a glance
Otter Tail Power Co (Otter Tail Corp)
TypeInvestor-owned utility
EIA utility ID14232
Residential customers104,750 (EIA-861, 2025)
Net-metered residential customers89 (EIA-861, 2025)
Service territory30 counties in Minnesota, 34 counties in North Dakota, 11 counties in South Dakota
How to applyOwn online portal – Otter Tail Simplified Application (Smartsheet form) · official link
Who submitsInstaller or customer; online form or mail paper application with fee to Otter Tail Power, Attn: Interconnection Coordinator, 215 S. Cascade St., Fergus Falls MN 56538-0496. Fees payable online (Paymentus).
Export compensationNEM – Small Power Producer Rider – Net Energy Billing Rate (MN 12.01)
Review time (official)Per MN DIP (not stated on page).
Documents Otter Tail Power asks for
- Interconnection application formMN DIP Attachment 2 Simplified Application (≤20 kW certified inverter); Attachment 3 Fast Track Gridpol prepares this.
- Single-line diagram (one-line)Single line diagram Gridpol prepares this.
- Site plan / site layoutSite diagram Gridpol prepares this.
- Inverter spec sheetUL 1741 SB (3rd Ed.) certified, Utility Required Profile (URP) since 1/1/2024
- Battery spec sheet (when applicable)Exhibit B 'For Energy Storage'
- Other utility-specific documentURP-AS 'Applied Settings' file returned after witness test/site inspection
- Other utility-specific documentCertificate of Completion (Exhibit C)
- Interconnection agreementMN DIA / Uniform Statewide Contract
How the Otter Tail Power process runs
- Submit Simplified Application online (or mail) + fee
- Review per MN DIP Section 2
- Sign MN DIA
- Install; inspection
- Witness test and site inspection; return URP-AS applied settings file
- Certificate of Completion (Exhibit C)
- Permission to operate
Fees
| Fee | Applies to | Note |
|---|---|---|
| per Attachment 3 + $30 | All MN applications | $30 state surcharge remitted to MN PUC; base fee not stated on page (MN DIP max $100 simplified) |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Simplified | 20 kW | certified inverter-based |
| Fast Track | MN DIP | |
| Study | 10000 kW | |
| Net metering cap | 40 kW |
ND/SD use separate state processes (ND DG application process docs)
Storage, EV and stamps
Battery storage
Exhibit B energy storage details required for storage; UL 1741 SB with URP.
Common issues the utility lists
- Inverter not UL 1741 SB certified or URP settings not applied
Gridpol’s pre-submission check covers these before we file.
Sources
- Otter Tail Power Minnesota Interconnection: https://www.otpco.com/customer-resources/how-to-connect-to-our-power-grid/minnesota-interconnection/ (retrieved 2026-11-13)
- Otter Tail Technical Specifications Manual for MN DER 2025: https://www.otpco.com/media/iwvlskbg/otps-technical-specification-manual_2025.pdf (retrieved 2026-11-13)
- Otter Tail MN 12.01 Small Power Producer Rider: https://www.otpco.com/media/uvplwynh/mn_1201.pdf (retrieved 2026-11-13)
Other utilities in Minnesota
- Xcel Energy (Minnesota)1,243,236
- Connexus Energy136,082
- Minnesota Power126,520
- Dakota Electric Association109,148
- East Central Energy55,839
- Rochester Public Utilities55,728
- Wright-Hennepin Cooperative Electric Association54,582
- Lake Country Power47,386
- Crow Wing Cooperative Power & Light Comp45,155
- Minnesota Valley Electric Cooperative43,682
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.