Investor-owned utilityNorthWestern Energy (South Dakota) interconnection application
NorthWestern Energy (South Dakota) is an investor-owned utility serving 51,787 residential customers in South Dakota (EIA-861, 2025). Applications: PowerClerk (NorthWestern Energy PowerClerk – Level 1 Small Generator Interconnection Request). Gridpol files NorthWestern Energy (South Dakota) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Partly researched from official sources. Not verified: NWE net-metering page and Level 1 request form are Montana-specific (MT Rules 16-17, $200 fee, MT PSC disconnect rule). SD process falls under SD Small Generator Interconnection rules (ARSD 20:10:36); NWE SD reported only one interconnection in 2025 ($50 fee). Verify on first project with NWE SD (Huron) which channel (PowerClerk or paper) and which SD credit/buyback terms apply.
NorthWestern Energy (South Dakota) at a glance
NorthWestern Energy (NorthWestern Energy Group)
TypeInvestor-owned utility
EIA utility ID13809
Residential customers51,787 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory27 counties in South Dakota
How to applyPowerClerk – NorthWestern Energy PowerClerk – Level 1 Small Generator Interconnection Request · official link
Who submitsApplicant registers in PowerClerk (applicant training guide available); system installed by qualified installer.
Export compensationNEM – Net metering (page content is Montana Rule 16)
Excess kWh credited to future bills; unused credits granted to utility at annual settle-up (Jan/Apr/Jul/Oct) – Montana rules; SD terms unconfirmed
Net meter exchange (non-AMI) up to 20 business days after inspections.
Documents NorthWestern Energy (South Dakota) asks for
- Interconnection application formLevel 1 Small Generator Interconnection Request in PowerClerk with required documentation uploads; Exhibit A Required Net Meter Application Information (annual settle-up month) Gridpol prepares this.
- Final inspection sign-offSystem must pass inspections before net meter request
How the NorthWestern Energy (South Dakota) process runs
- Submit Level 1 request in PowerClerk
- Authorization for interconnected operation per Interconnection Agreement
- Installation by qualified installer; inspections
- NWE reprograms AMI meter or exchanges meter
- Welcome letter – system may be activated
Fees
| Fee | Applies to | Note |
|---|---|---|
| $50 | SD application fee (as reported for a 4 kW interconnection, 2025) | From NWE 2025 South Dakota Annual Interconnection Report to SD PUC (ARSD 20:10:36:63); NWE's Montana Level 1 form shows $200 – not applicable to SD |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | PowerClerk; Levels 2-4 via separate PDF request form |
Sources
- NorthWestern Energy – Net Metering and Private Generation: https://www.northwesternenergy.com/clean-energy/our-environmental-projects/net-metering-private-generation (retrieved 2026-11-13)
- NorthWestern Energy SD Small Generator Facility Interconnection Report 2025 (SD PUC): https://puc.sd.gov/commission/commissionaction/interconnectionreports/2025NWEReport.pdf (retrieved 2026-11-13)
South Dakota interconnection rule
South Dakota Public Utilities Commission
Interconnection ruleARSD 20:10:36 (Small Generator Interconnection) – Small Generator Facility Interconnection · source
Applies toPublic utilities (PUC rate-regulated IOUs: Xcel/NSP, Black Hills, NorthWestern, MDU, Otter Tail) for facilities <=10 MW not under FERC/RTO jurisdiction
Application formCommission tier application forms (application forms available from the commission, 20:10:36:33); certificate of completion; interconnection agreement
TimelinesTier 1: acknowledgment within 3 business days, completeness within 10 BD, applicant 20 BD to cure, review within 15 BD after complete (20:10:36:33). Completion requires passed screens, code inspector approval, witness test if done, certificate of completion, executed agreement (20:10:36:34).
FeesTier 1 $50; Tier 2 $50 + $1/kW up to $500; Tier 3 and 4 $100 + $2/kW up to $1,000 (20:10:36:06).
InsuranceTier 1: proof of adequate homeowners/general/commercial liability; Tier 2 up to $500,000; Tiers 3-4 up to $1,000,000 at utility request (20:10:36:26). Endorsements (utility additional insured etc.) not required for residential <=10 kW (20:10:36:27).
External disconnectOnly if required by the utility: primary-line lockable visible-break device; secondary-line lockable device with clearly indicated status; lockbox alternative (20:10:36:15).
Export compensationNone statewide
No statewide net metering rule; compensation per utility tariff (e.g. avoided-cost/PURPA).
Electric cooperatives and municipal utilities are not rate-regulated by the PUC and set their own interconnection and buyback policies.
- ARSD 20:10:36 chapter index: https://sdlegislature.gov/api/Rules/20:10:36.html (retrieved 2026-11-13)
- ARSD 20:10:36:06 Application fees: https://sdlegislature.gov/api/Rules/20:10:36:06.html (retrieved 2026-11-13)
- ARSD 20:10:36:26 Insurance amounts: https://sdlegislature.gov/api/Rules/20:10:36:26.html (retrieved 2026-11-13)
- ARSD 20:10:36:33 Tier 1 review procedures: https://sdlegislature.gov/api/Rules/20:10:36:33.html (retrieved 2026-11-13)
Other utilities in South Dakota
- Xcel Energy (Minnesota)94,137
- Black Hills Energy (Black Hills Power)67,608
- Sioux Valley SW Electric Cooperative22,989
- Southeastern Electric Cooperative Inc.20,959
- West River Electric Association Inc.18,975
- Watertown Municipal Utilities11,775
- City of Brookings10,769
- Black Hills Electric Cooperative, Inc.9,415
- Otter Tail Power9,094
- Central Electric Cooperative, Inc.6,515
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.