Lynches River Electric Cooperative, Inc. is an electric cooperative serving 21,730 residential customers in South Carolina (EIA-861, 2025). Gridpol files Lynches River Electric Cooperative, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
South Carolina’s commission rule (South Carolina Generator Interconnection Procedures, Forms and Agreements (SCGIP), adopted by Order No. 2016-191, Docket No. 2015-362-E, under S.C. Code Ann. 58-27-460; revised in Docket No. 2019-326-E) does not bind electric cooperatives; Lynches River Electric Cooperative, Inc. sets its own interconnection policy. We confirm its form on the first project. Electric cooperatives and municipal utilities are not covered by the SCGIP or Solar Choice statute; distribution co-ops adopt their own net metering policies (2014 Act 236 s.7, uncodified); Santee Cooper has its own Generator Interconnection Procedures.
Lynches River Electric Cooperative, Inc. at a glance
Lynches River Elec Coop, Inc
TypeElectric cooperative
EIA utility ID11355
Residential customers21,730 (EIA-861, 2025)
Net-metered residential customers184 (EIA-861, 2025)
Service territory3 counties in South Carolina
Wholesale supplier / associationCentral Electric Power Cooperative, Inc. (SC)
Documents Lynches River Electric Cooperative, Inc. asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Lynches River Electric Cooperative, Inc.. We confirm Lynches River Electric Cooperative, Inc.’s exact list on the first project.
South Carolina interconnection rule
Details from 2016 SCGIP; revised SCGIP from Docket 2019-326-E (Dominion redline 2022) may have changed fees/insurance/timelines - verify current version on utility site. ORS site geo-blocks server, archive copy used.
Public Service Commission of South Carolina
Interconnection ruleSouth Carolina Generator Interconnection Procedures, Forms and Agreements (SCGIP), adopted by Order No. 2016-191, Docket No. 2015-362-E, under S.C. Code Ann. 58-27-460; revised in Docket No. 2019-326-E – South Carolina Generator Interconnection Procedures (SCGIP) · source
Applies toCommission-jurisdictional electrical utilities: Duke Energy Carolinas, Duke Energy Progress and Dominion Energy South Carolina (formerly SCE&G). Santee Cooper (state authority) and electric cooperatives are not bound; Santee Cooper publishes its own Generator Interconnection Procedures.
Application formStatewide standard Interconnection Request Application Form (Attachment 3; Attachment 7 combined request/Certificate of Completion/terms for certified inverters <=20 kW) and standard Interconnection Agreement (Attachment 10)
TimelinesReceipt confirmation within 3 business days; completeness determination within 10 business days (customer has 10 business days to cure); 20 kW process: screens and approval within 15 business days; utility gets >=10 business days notice of commissioning tests; pre-application report 20 business days ($500).
Fees20 kW Inverter Process: $100 processing fee. Study Process: deposit $10,000 + $1/kW AC. Pre-application report $500.
InsuranceResidential <=250 kW: homeowner's policy with liability >=$100,000 per occurrence; non-residential <=250 kW: CGL >=$300,000; non-residential >250 kW: CGL >=$1,000,000; self-insurance possible for creditworthy customers.
External disconnectRequired: manual load-break disconnect or safety switch with visible position indication, padlockable open, accessible to utility personnel, installed immediately adjacent to the utility meter unless otherwise approved (SCGIP 1.6 and 20 kW terms).
Export compensationNet billing – S.C. Code Ann. 58-40-10 and 58-40-20 (Act 62 of 2019, Solar Choice Metering)
Residential customer-generators <=20 kW AC; non-residential <= lesser of 1,000 kW AC or 100% of contract demand (up to 5,000 kW AC on TOU after 2025-06-01). Solar choice tariffs for applications after 2021-05-31 at Commission-determined value; pre-June 2021 customers keep Order 2015-194 net metering until 2029-05-31. Applies to electrical utilities with >=100,000 customer accounts.
Electric cooperatives and municipal utilities are not covered by the SCGIP or Solar Choice statute; distribution co-ops adopt their own net metering policies (2014 Act 236 s.7, uncodified); Santee Cooper has its own Generator Interconnection Procedures.
- SC ORS - SC Generator Interconnection Procedures, Order No. 2016-191 (archive.org copy): https://web.archive.org/web/20250605050625/https://solar.sc.gov/sites/orssolar/files/Documents/installing-and-maintaining-a-system/documents/sc-generator-interconnection-procedures.pdf (retrieved 2026-11-13)
- S.C. Code Title 58 Chapter 40 - Net Energy Metering / Solar Choice: https://www.scstatehouse.gov/code/t58c040.php (retrieved 2026-11-13)
- PSC SC - Docket No. 2019-326-E notice: https://www.psc.sc.gov/node/172 (retrieved 2026-11-13)
- Santee Cooper Generator Interconnection Standard: https://www.santeecooper.com/policies-reference-materials/generator-interconnection-standard/ (retrieved 2026-11-13)
Other utilities in South Carolina
- Dominion Energy South Carolina (DESC)712,679
- Duke Energy Carolinas (DEC)582,062
- Santee Cooper188,962
- Duke Energy Progress (DEP)143,884
- Berkeley Electric Cooperative (BEC)119,545
- Horry Electric Cooperative Inc.91,545
- Palmetto Electric Cooperative Inc.69,848
- Blue Ridge Electric Cooperative Inc.68,647
- York Electric Cooperative Inc.66,369
- Laurens Electric Cooperative, Inc.59,786
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks