Home › Utilities › South Carolina › Berkeley Electric Cooperative (BEC)

Electric cooperative

Berkeley Electric Cooperative (BEC) interconnection application

Berkeley Electric Cooperative (BEC) is an electric cooperative serving 119,545 residential customers in South Carolina (EIA-861, 2025). Applications: Own online portal (BEC online interconnection form (FormAssembly via SmartHub, linked from BEC Solar Energy page)). Gridpol files Berkeley Electric Cooperative (BEC) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Berkeley Electric Cooperative (BEC)’s official sources (see below). Process, fees and documents from BEC Solar Energy page. Not verified: battery/storage rules, BEC 500 kVA interconnection standard details.

Berkeley Electric Cooperative (BEC) at a glance

Utility

Berkeley Electric Coop Inc

Type

Electric cooperative

EIA utility ID

1613

Residential customers

119,545 (EIA-861, 2025)

Net-metered residential customers

1,983 (EIA-861, 2025)

Service territory

3 counties in South Carolina

How to apply

Own online portal – BEC online interconnection form (FormAssembly via SmartHub, linked from BEC Solar Energy page) · official link

Who submits

Member signs the Interconnection Application; BEC notifies the solar company of application status. Contacts: Tameka Palmer tamekap@bec.coop (843) 899-8433.

Export compensation

Net billing – Renewable Generation Surplus Rider
All new installations: surplus kWh credited at $0.0603/kWh; available only on non-demand, non-time-of-day rates (Residential RS, GS <100 kVA). Legacy Net Metering rider: bank reset to zero each June 1.

Review time (official)

BEC reviews for completeness and notifies solar company; typically about two weeks after the building codes release for bi-directional meter installation.

Wholesale supplier / association

Central Electric Power Cooperative, Inc. (SC)

Documents Berkeley Electric Cooperative (BEC) asks for

  • Interconnection application formInterconnection Application, fully completed, signed and dated (same info also to local Building Inspector's office) Gridpol prepares this.
  • Customer signatureMember signature
  • Proof of insuranceHomeowners insurance declaration/policy
  • Other utility-specific documentSales contract with total price and monthly kWh production estimate
  • Single-line diagram (one-line)One-line electrical drawing Gridpol prepares this.
  • Final inspection sign-offCity/county Building & Codes inspection; inspector notifies BEC of release

How the Berkeley Electric Cooperative (BEC) process runs

  1. Optional: BEC evaluation of projected solar value.
  2. Submit online interconnection form (signed application, homeowner insurance, sales contract with production estimate, one-line drawing) and pay $150 fee.
  3. BEC reviews for completeness and notifies solar company of status.
  4. Install - connect in member's breaker panel, never in BEC meter base.
  5. City/county Building & Codes inspection; inspector notifies BEC of release. Leave PV breaker ON and outdoor disconnect OPEN.
  6. BEC metering inspection and bi-directional meter installation (typically ~2 weeks after release); solar company or member notified; energize only after meter is installed.

Fees

FeeApplies toNote
$150All solar interconnection applications (one-time)Must be paid before application is processed
$50Field inspection, per inspection
up to $1,000Unauthorized meter tampering (contractor entering BEC meter base)Penalty

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Residential (Renewable Surplus Rider)20 kWUp to max monthly kW use, <=20 kW AC
Small Commercial (<100 kVA transformer, non-demand)100 kW
Net metering cap20 kW

Size limited (wholesale power agreement) to annual kWh / 1,800 for kW AC, or average monthly kWh / 150. Large accounts >100 kVA may self-consume larger systems with no surplus value.

Common issues the utility lists

  • Application processed only after $150 fee is paid and form is fully completed, signed and dated
  • Connection inside BEC meter base (up to $1,000 tampering charge)
  • System sized above usage-based limit

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited