South Carolina

South Carolina interconnection applications

46 electric utilities serve South Carolina (EIA-861, 2025): 4 investor-owned utilitys, 1 state power authority, 20 electric cooperatives, 21 municipal utilitys. Together they serve 2,554,014 residential customers; 41,365 residential customers were on net metering at year-end 2025.

Largest utilities in South Carolina

Dominion Energy South Carolina (DESC)Process verified

Investor-owned utility · 712,679 residential customers · South Carolina

Applications: PowerClerk – DESC PowerClerk (SC small generator)

Interconnection process and documents →
Duke Energy Carolinas (DEC)Partly researched

Investor-owned utility · 2,543,170 residential customers · South Carolina

Interconnection process and documents →
Santee CooperProcess verified

State power authority · 188,962 residential customers · South Carolina

Applications: Own online portal – DocuSign interconnection process (initiated after $100 fee); Interconnection Request Application PDF (SC0924i Attachment 7)

Interconnection process and documents →
Duke Energy Progress (DEP)Partly researched

Investor-owned utility · 1,527,825 residential customers · South Carolina

Interconnection process and documents →
Berkeley Electric Cooperative (BEC)Process verified

Electric cooperative · 119,545 residential customers · South Carolina

Applications: Own online portal – BEC online interconnection form (FormAssembly via SmartHub, linked from BEC Solar Energy page)

Interconnection process and documents →
Horry Electric Cooperative Inc.State guidance

Electric cooperative · 91,545 residential customers · South Carolina

Interconnection process and documents →
Palmetto Electric Cooperative Inc.State guidance

Electric cooperative · 69,848 residential customers · South Carolina

Interconnection process and documents →
Blue Ridge Electric Cooperative Inc.State guidance

Electric cooperative · 68,647 residential customers · South Carolina

Interconnection process and documents →
York Electric Cooperative Inc.State guidance

Electric cooperative · 66,385 residential customers · South Carolina

Interconnection process and documents →
Laurens Electric Cooperative, Inc.State guidance

Electric cooperative · 59,786 residential customers · South Carolina

Interconnection process and documents →
Mid-Carolina Electric Cooperative Inc.State guidance

Electric cooperative · 57,067 residential customers · South Carolina

Interconnection process and documents →
Aiken Electric Cooperative Inc.State guidance

Electric cooperative · 50,850 residential customers · South Carolina

Interconnection process and documents →

Export compensation among the researched South Carolina utilities: Net billing. Rules differ by utility – see each utility page.

South Carolina interconnection rule

Details from 2016 SCGIP; revised SCGIP from Docket 2019-326-E (Dominion redline 2022) may have changed fees/insurance/timelines - verify current version on utility site. ORS site geo-blocks server, archive copy used.

Commission

Public Service Commission of South Carolina

Interconnection rule

South Carolina Generator Interconnection Procedures, Forms and Agreements (SCGIP), adopted by Order No. 2016-191, Docket No. 2015-362-E, under S.C. Code Ann. 58-27-460; revised in Docket No. 2019-326-E – South Carolina Generator Interconnection Procedures (SCGIP) · source

Applies to

Commission-jurisdictional electrical utilities: Duke Energy Carolinas, Duke Energy Progress and Dominion Energy South Carolina (formerly SCE&G). Santee Cooper (state authority) and electric cooperatives are not bound; Santee Cooper publishes its own Generator Interconnection Procedures.

Application form

Statewide standard Interconnection Request Application Form (Attachment 3; Attachment 7 combined request/Certificate of Completion/terms for certified inverters <=20 kW) and standard Interconnection Agreement (Attachment 10)

Timelines

Receipt confirmation within 3 business days; completeness determination within 10 business days (customer has 10 business days to cure); 20 kW process: screens and approval within 15 business days; utility gets >=10 business days notice of commissioning tests; pre-application report 20 business days ($500).

Fees

20 kW Inverter Process: $100 processing fee. Study Process: deposit $10,000 + $1/kW AC. Pre-application report $500.

Insurance

Residential <=250 kW: homeowner's policy with liability >=$100,000 per occurrence; non-residential <=250 kW: CGL >=$300,000; non-residential >250 kW: CGL >=$1,000,000; self-insurance possible for creditworthy customers.

External disconnect

Required: manual load-break disconnect or safety switch with visible position indication, padlockable open, accessible to utility personnel, installed immediately adjacent to the utility meter unless otherwise approved (SCGIP 1.6 and 20 kW terms).

Export compensation

Net billing – S.C. Code Ann. 58-40-10 and 58-40-20 (Act 62 of 2019, Solar Choice Metering)
Residential customer-generators <=20 kW AC; non-residential <= lesser of 1,000 kW AC or 100% of contract demand (up to 5,000 kW AC on TOU after 2025-06-01). Solar choice tariffs for applications after 2021-05-31 at Commission-determined value; pre-June 2021 customers keep Order 2015-194 net metering until 2029-05-31. Applies to electrical utilities with >=100,000 customer accounts.

Not bound by the rule

Electric cooperatives and municipal utilities are not covered by the SCGIP or Solar Choice statute; distribution co-ops adopt their own net metering policies (2014 Act 236 s.7, uncodified); Santee Cooper has its own Generator Interconnection Procedures.

LevelUp toCriteria / review / fee
Optional 20 kW Inverter Process (Section 2)20 kWcertified (UL 1741-listed) inverter-based generating facility <=20 kW · receipt confirmed 3 business days; completeness 10 business days; screens 15 business days · $100 non-refundable processing fee ($50 for ownership transfer)
Fast Track Process (Section 3)certified generating facility up to capacity in Section 3.1 (voltage/location-dependent) · per application form
Study Process (Section 4)larger or failing Fast Track; system impact and facilities studies · customer returns study agreement within 15 business days · deposit $10,000 + $1/kW AC

All 46 utilities in South Carolina

Residential customers in South Carolina per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.