State power authoritySantee Cooper interconnection application
Santee Cooper is a state power authority serving 188,962 residential customers in South Carolina (EIA-861, 2025). Applications: Own online portal (DocuSign interconnection process (initiated after $100 fee); Interconnection Request Application PDF (SC0924i Attachment 7)). Gridpol files Santee Cooper interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Santee Cooper’s official sources (see below). Process confirmed from Santee Cooper 2026 program manual. Not verified: commercial interconnection fees/levels (see SCPSA Generator Interconnection Procedures), DG-25 rider text read only via manual.
Santee Cooper at a glance
South Carolina Public Service Authority
TypeState power authority
EIA utility ID17543
Residential customers188,962 (EIA-861, 2025)
Net-metered residential customers1,954 (EIA-861, 2025)
Service territory3 counties in South Carolina
How to applyOwn online portal – DocuSign interconnection process (initiated after $100 fee); Interconnection Request Application PDF (SC0924i Attachment 7) · official link
Who submitsCustomer pays fee; installing contractor (SE Trade Ally / NABCEP PV installation professional) is contacted to submit supporting documentation via DocuSign. Approved IRAs emailed to customer or installer.
Export compensationNet billing – Distributed Generation Rider DG-25
Self-consumed energy offsets retail; exported energy credited at $0.0415/kWh; $10.00/month DG customer charge (per 2026 manual). Santee Cooper is a state-owned utility not under SC PSC net metering rules.
IRA package reviewed and approved/denied within 10 business days of submission (2026 Program Manual).
Documents Santee Cooper asks for
- Interconnection application formInterconnection Request Application (IRA), Santee Cooper form SC0924i Attachment 7 Gridpol prepares this.
- Proof of insuranceProof of home liability coverage meeting minimum requirements of Santee Cooper Interconnection Standard
- Single-line diagram (one-line)Electrical diagram Gridpol prepares this.
- PV module spec sheetPV module specification data sheet
- Inverter spec sheetInverter specification data sheet; must pass UL 1741 anti-islanding; IEEE 929/1547/1547.1
- Customer signatureDocuSign
- Final inspection sign-offFinal passed local inspection report submitted to Santee Cooper, then contact Santee Cooper for final acceptance testing
- Other utility-specific document (when applicable)Rebate only: Rebate Reservation Worksheet (max monthly kW demand), NABCEP installer letter, rebate application within 90 days of installation
How the Santee Cooper process runs
- (Rebate) Submit Rebate Reservation Worksheet to determine max monthly kW demand.
- Select SE Trade Ally / NABCEP installer; proposal and Santee Cooper savings estimate.
- Pay $100 non-refundable IRA fee - starts DocuSign interconnection process.
- Installer submits IRA, insurance proof, electrical diagram, module and inverter spec sheets via DocuSign.
- Approval/denial within 10 business days via DocuSign (approved IRA typically needed for building permit).
- Install within 90 days of approval (rebate); obtain local permit and passed final inspection.
- Submit final inspection report (and NABCEP letter) and contact Santee Cooper for final acceptance testing; meter set and interconnection.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Residential Interconnection Request Application | Non-refundable; check/cashier's check/money order by mail or cash in local office; payment starts DocuSign process |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Residential | 20 kW | Lesser of 20 kW or estimated maximum monthly kW demand; min 1 kW AC for rebate |
| Net metering cap | 20 kW |
Residence must be separately metered on Santee Cooper residential service (RG/REV) before interconnection.
Storage, EV and stamps
Battery storage
Battery backup systems allowed; rebates apply only to the solar portion (kW AC), not batteries (2026 Program Manual FAQ). No separate storage interconnection rules found.
Common issues the utility lists
- Discrepancies between application and installed system found at inspection may delay or void rebate
Gridpol’s pre-submission check covers these before we file.
Sources
- Santee Cooper 2026 Solar Home & Solar Share Home Program Manual (v12012025): https://www.santeecooper.com/Programs-Incentives/EmpowerSolar/Solar-Home/_pdfs/2026-Solar-Residential-Program-Manual-v1-12012025.pdf (retrieved 2026-11-13)
- Santee Cooper Generator Interconnection Standards: https://www.santeecooper.com/policies-reference-materials/generator-interconnection-standard/ (retrieved 2026-11-13)
- Santee Cooper Interconnection Request Application (Attachment 7): https://www.santeecooper.com/_Assets/pdfs/Forms/SC0924i_Attachment-7.pdf (retrieved 2026-11-13)
Other utilities in South Carolina
- Dominion Energy South Carolina (DESC)712,679
- Duke Energy Carolinas (DEC)582,062
- Duke Energy Progress (DEP)143,884
- Berkeley Electric Cooperative (BEC)119,545
- Horry Electric Cooperative Inc.91,545
- Palmetto Electric Cooperative Inc.69,848
- Blue Ridge Electric Cooperative Inc.68,647
- York Electric Cooperative Inc.66,369
- Laurens Electric Cooperative, Inc.59,786
- Mid-Carolina Electric Cooperative Inc.57,067
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.