Pike County Light & Power is an investor-owned utility serving 4,365 residential customers in Pennsylvania (EIA-861, 2025). Gridpol files Pike County Light & Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Partly researched from official sources. verify on first project: no official interconnection page found (pclp.com redirects to a domain-sale page); fees are PA PUC standard fees, not confirmed from the utility.
Pike County Light & Power at a glance
Pike County Light & Power Co
TypeInvestor-owned utility
EIA utility ID15045
Residential customers4,365 (EIA-861, 2025)
Net-metered residential customers38 (EIA-861, 2025)
Service territory1 county in Pennsylvania
Export compensationNEM – Pennsylvania net metering (52 Pa. Code §75.11 et seq.)
Documents Pike County Light & Power asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Pike County Light & Power. We confirm Pike County Light & Power’s exact list on the first project.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Level 1 (certified inverter <=10 kW) | |
| $250 + $1/kW | Level 2 | |
| $350 + $2/kW | Level 3 / Level 4 |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 10 kW | certified inverter-based |
| Level 2 | 2000 kW | certified inverter-based |
| Level 3 | non-certified / larger | |
| Level 4 | non-export | |
| Net metering cap | 50 kW |
PA NEM: residential <=50 kW; systems >=500 kW need PUC review (per utilities)
Sources
- 52 Pa. Code Chapter 75 (Alternative Energy Portfolio Standards: net metering & interconnection): https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/chap75toc.html (retrieved 2026-11-13)
Pennsylvania interconnection rule
Pennsylvania Public Utility Commission
Interconnection rule52 Pa. Code 75.21-75.51 (Chapter 75 Subchapter C, Interconnection Standards); fee policy 52 Pa. Code 69.2104 – Alternative Energy Portfolio Standards - Interconnection Standards · source
Applies toElectric distribution companies (EDCs) regulated by the PUC, for customer-generators' small generator facilities <=5 MW not subject to RTO interconnection rules (75.31); not electric cooperatives or municipal utilities
Application formEDC standard interconnection request forms and standard small generator interconnection agreement (examples posted on EDC websites, 75.33); Certificate of Completion
TimelinesLevel 1: completeness 10 business days; screen verification 15 BD after; witness test within 10 BD of certificate of completion or deemed waived; approval conditional on local code approval, certificate of completion and signed standard agreement (75.37).
FeesPolicy statement 52 Pa. Code 69.2104: Level 1 $100; Level 2 $250 + $1/kW; Level 3 $350 + $2/kW plus studies; engineering not over $100/hour.
InsuranceNot addressed in the Chapter 75 sections reviewed.
External disconnectRequired: lockable, visible-break isolation device accessible by EDC, owned/maintained by facility owner; padlockable draw-out breaker acceptable; lockbox option for locked areas (75.36(9)-(10)).
Export compensationNEM – 52 Pa. Code 75.11-75.17; 73 P.S. 1648.1 et seq. (AEPS Act)
Residential <=50 kW; nonresidential <=3 MW (<=5 MW under 75.16); >=500 kW needs PUC approval. Full retail kWh credit (generation, transmission, distribution), excess carried forward through the year; year-end excess compensated per 75.13 (price-to-compare).
Electric cooperatives and municipal utilities are not EDCs under the AEPS rules and set their own net metering/interconnection policies.
- 52 Pa. Code 75.31 Applicability: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/s75.31.html&d= (retrieved 2026-11-13)
- 52 Pa. Code 75.34 Review procedures: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/s75.34.html&d= (retrieved 2026-11-13)
- 52 Pa. Code 75.36 Additional general requirements: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/s75.36.html&d= (retrieved 2026-11-13)
- 52 Pa. Code 75.37 Level 1 review: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/s75.37.html&d= (retrieved 2026-11-13)
- 52 Pa. Code 69.2104 Interconnection application fees: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter69/s69.2104.html&d= (retrieved 2026-11-13)
- 52 Pa. Code 75.13 Net metering general provisions: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter75/s75.13.html&d= (retrieved 2026-11-13)
Other utilities in Pennsylvania
- FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power)1,808,941
- PECO1,538,993
- PPL Electric Utilities1,311,251
- Duquesne Light553,124
- UGI Electric55,181
- Adams Electric Cooperative Inc.32,580
- Central Electric Cooperative, Inc.23,675
- REA Energy Cooperative Inc.20,951
- Tri-County Rural Electric Cooperative Inc. (PA)18,214
- Northwestern Rural E C A, Inc.18,200
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.