FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) interconnection application

FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) is an investor-owned utility serving 1,812,335 residential customers in New York, Pennsylvania (EIA-861, 2025). Applications: Own online portal (FirstEnergy Interconnection Portal). Gridpol files FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power)’s official sources (see below). NY customers of this entity (EIA lists NY) - NY process not checked.

FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) at a glance

Utility

FirstEnergy Pennsylvania Electric Co (FirstEnergy)

Type

Investor-owned utility

EIA utility ID

66101

Residential customers

1,812,335 (EIA-861, 2025)

Net-metered residential customers

26,501 (EIA-861, 2025)

Service territory

2 counties in New York, 55 counties in Pennsylvania

How to apply

Own online portal – FirstEnergy Interconnection Portal · official link

Who submits

Customer or installer via online portal; paper applications also listed; contacts per rate district (ME_/PN_/PP_/WP_interconnection@firstenergycorp.com).

Export compensation

NEM – Pennsylvania net metering (52 Pa. Code §75.11 et seq.)
bi-directional meter installed after Approval to Operate

Review time (official)

Per 52 Pa. Code Ch. 75 schedules (not restated on FE page).

Documents FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) asks for

  • Interconnection application formPA Level 1 (<=10 kW UL 1741) or Level 2-4 application; PA Interconnection Application Addendum Gridpol prepares this.
  • Site plan / site layoutno overhead internet photos; property layout, north arrow, nearest cross streets, route/length of connection, DER AC disconnect location (visible-break for CT metering), generation/inverter/storage locations, service transformer Gridpol prepares this.
  • Single-line diagram (one-line)energy source with DC/AC ratings, inverter AC rating, disconnect make/model and lockable visible break, connection point, utility meter, inverter and battery equipment Gridpol prepares this.
  • Net metering / net billing agreement (when applicable)PA Net Metering Rider Application
  • Interconnection agreementLevel 1 Application/Agreement or Level 2-4 Agreement after install
  • Final inspection sign-offCertificate of Completion plus evidence of electrical inspection by authorized agency (inspector may sign COC)

How the FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power) process runs

  1. Determine size/type and application level (online portal determines level from data entered)
  2. Submit application with site plan and one-line diagram in the FirstEnergy Interconnection Portal; pay fee online
  3. Engineering review; customer notified by email/phone: approved, upgrade+fee required, or information missing/incorrect
  4. Install per approved application and FirstEnergy interconnection requirements
  5. Submit signed Interconnection Agreement with Certificate of Completion and evidence of electrical inspection
  6. Company final review, possible witness test, Approval to Operate (do not energize before)
  7. Company replaces meter with bi-directional net meter (may take several weeks; excess not credited until installed)

Fees

FeeApplies toNote
$100Level 1 (<=10 kW)
$250 + $1/kWLevel 2
$350 + $2/kWLevel 3Level 4 per separate fee list

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 110 kWcertified inverter
Level 2 & 32000 kWcertified inverter
Level 4per 52 Pa. Code

Separate process for >=500 kW net metering applications since June 2025

Storage, EV and stamps

Battery storage

Site plan and one-line must show storage equipment.

Common issues the utility lists

  • Application not completed correctly
  • Drawings/documentation missing
  • Fees not determined/paid
  • Overhead internet photos submitted instead of a site plan
  • Design inconsistent with company policy/state requirements

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.