Home › Utilities › Pennsylvania › PECO
Investor-owned utilityPECO interconnection application
PECO is an investor-owned utility serving 1,538,993 residential customers in Pennsylvania (EIA-861, 2025). Applications: Own online portal (Connect-The-Grid). Gridpol files PECO interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from PECO’s official sources (see below). Storage-specific form not found on PECO pages; EV charger process not documented.
PECO at a glance
PECO Energy Co (Exelon)
TypeInvestor-owned utility
EIA utility ID14940
Residential customers1,538,993 (EIA-861, 2025)
Net-metered residential customers24,549 (EIA-861, 2025)
Service territory6 counties in Pennsylvania
How to applyOwn online portal – Connect-The-Grid · official link
Who submitsTypically contractor completes and submits on behalf of customer; customer may apply directly. Email applications no longer accepted.
Export compensationNEM – Rate RS-2 Net Metering
Apply for net metering via the interconnection application; alternative suppliers not obligated to credit excess
PECO brochure (business days): Level 1 ~25 days, Level 2 ~30 days, Level 3 varies, Level 4 <10 kW 30 days / <50 kW 35 days; 52 Pa. Code Ch. 75 governs.
Documents PECO asks for
- Interconnection application forminterconnection application (Level 1 <=10 kW or Level 2-4) Gridpol prepares this.
- Other utility-specific documentService and meter form
- PV module spec sheetspecifications of system type and output
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Single-line diagram (one-line) (when applicable)PECO publishes typical single line diagrams Gridpol prepares this.
- Final inspection sign-offthird-party electrical inspection certificate sent to PECO
- Other utility-specific documentcertificate of work completion
- Photos (meter, main panel, equipment)photo of the meter setup
- Other utility-specific document (when applicable)municipal construction permit (installer must obtain before work); Virtual Meter Aggregation application
How the PECO process runs
- Customer hires installer; installer submits interconnection application with system specifications and pays fee in Connect-The-Grid
- PECO engineers analyze local equipment/voltage and offer options if issues
- If upgrades required, PECO provides construction agreement with cost estimate; installer signs and pays
- PECO issues Approval to Install notice
- Installer obtains municipal construction permit and installs
- Third-party inspection service issues electrical inspection certificate to PECO
- Installer provides certificate of work completion and photo of meter setup
- PECO schedules bi-directional meter installation
- PECO issues Permission to Operate letter; only then system may be activated
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Level 1 (certified inverter <=10 kW) | |
| $250 + $1/kW | Level 2 (certified inverter <=2,000 kW) | extra engineering review up to $100/hr |
| $350 + $2/kW | Level 3 and Level 4 | study engineering up to $100/hr |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 10 kW | certified inverter-based |
| Level 2 | 2000 kW | certified inverter-based |
| Level 3 | 2000 kW | non-certified/non-inverter |
| Level 4 | 5000 kW | non-export (reverse power relay) or not meeting L1/L2; contact PECO near 2,000 kW+ |
| Net metering cap | 50 kW |
NEM: residential <=50 kW, non-residential <=3,000 kW; leased systems limited to 110% of annual usage. Yellow Book (<=50 kW) and Gray Book (>50 kW) technical requirements.
Common issues the utility lists
- Applications without payment are not entered into the review process
Gridpol’s pre-submission check covers these before we file.
Sources
- PECO Smaller Generators: https://www.peco.com/smart-energy/my-green-power-connection/developers-contractors/smaller-generators (retrieved 2026-11-13)
- PECO Net Metering/Interconnection Application Fees: https://www.peco.com/cdn/assets/v3/assets/blt1b5616c79bacadb4/bltff7c5c1ad276014c/64ca5289241e88fd7dcb3507/summaryoffeesrev1.pdf (retrieved 2026-11-13)
- PECO Interconnection Brochure 2024: https://azure-na-assets.contentstack.com/v3/assets/blt1b5616c79bacadb4/blt73d21bcd354c49c6/67c0d46e86c64e0580368cd2/PECOInterconnectionBrochure2024.pdf (retrieved 2026-11-13)
- PECO Net Metering: https://www.peco.com/smart-energy/my-green-power-connection/developers-contractors/net-metering (retrieved 2026-11-13)
Other utilities in Pennsylvania
- FirstEnergy Pennsylvania (Met-Ed, Penelec, Penn Power, West Penn Power)1,808,941
- PPL Electric Utilities1,311,251
- Duquesne Light553,124
- UGI Electric55,181
- Adams Electric Cooperative Inc.32,580
- Central Electric Cooperative, Inc.23,675
- REA Energy Cooperative Inc.20,951
- Tri-County Rural Electric Cooperative Inc. (PA)18,214
- Northwestern Rural E C A, Inc.18,200
- Valley Rural Electric Cooperative Inc.18,057
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.