PECO interconnection application

PECO is an investor-owned utility serving 1,538,993 residential customers in Pennsylvania (EIA-861, 2025). Applications: Own online portal (Connect-The-Grid). Gridpol files PECO interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from PECO’s official sources (see below). Storage-specific form not found on PECO pages; EV charger process not documented.

PECO at a glance

Utility

PECO Energy Co (Exelon)

Type

Investor-owned utility

EIA utility ID

14940

Residential customers

1,538,993 (EIA-861, 2025)

Net-metered residential customers

24,549 (EIA-861, 2025)

Service territory

6 counties in Pennsylvania

How to apply

Own online portal – Connect-The-Grid · official link

Who submits

Typically contractor completes and submits on behalf of customer; customer may apply directly. Email applications no longer accepted.

Export compensation

NEM – Rate RS-2 Net Metering
Apply for net metering via the interconnection application; alternative suppliers not obligated to credit excess

Review time (official)

PECO brochure (business days): Level 1 ~25 days, Level 2 ~30 days, Level 3 varies, Level 4 <10 kW 30 days / <50 kW 35 days; 52 Pa. Code Ch. 75 governs.

Documents PECO asks for

  • Interconnection application forminterconnection application (Level 1 <=10 kW or Level 2-4) Gridpol prepares this.
  • Other utility-specific documentService and meter form
  • PV module spec sheetspecifications of system type and output
  • Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
  • Single-line diagram (one-line) (when applicable)PECO publishes typical single line diagrams Gridpol prepares this.
  • Final inspection sign-offthird-party electrical inspection certificate sent to PECO
  • Other utility-specific documentcertificate of work completion
  • Photos (meter, main panel, equipment)photo of the meter setup
  • Other utility-specific document (when applicable)municipal construction permit (installer must obtain before work); Virtual Meter Aggregation application

How the PECO process runs

  1. Customer hires installer; installer submits interconnection application with system specifications and pays fee in Connect-The-Grid
  2. PECO engineers analyze local equipment/voltage and offer options if issues
  3. If upgrades required, PECO provides construction agreement with cost estimate; installer signs and pays
  4. PECO issues Approval to Install notice
  5. Installer obtains municipal construction permit and installs
  6. Third-party inspection service issues electrical inspection certificate to PECO
  7. Installer provides certificate of work completion and photo of meter setup
  8. PECO schedules bi-directional meter installation
  9. PECO issues Permission to Operate letter; only then system may be activated

Fees

FeeApplies toNote
$100Level 1 (certified inverter <=10 kW)
$250 + $1/kWLevel 2 (certified inverter <=2,000 kW)extra engineering review up to $100/hr
$350 + $2/kWLevel 3 and Level 4study engineering up to $100/hr

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 110 kWcertified inverter-based
Level 22000 kWcertified inverter-based
Level 32000 kWnon-certified/non-inverter
Level 45000 kWnon-export (reverse power relay) or not meeting L1/L2; contact PECO near 2,000 kW+
Net metering cap50 kW

NEM: residential <=50 kW, non-residential <=3,000 kW; leased systems limited to 110% of annual usage. Yellow Book (<=50 kW) and Gray Book (>50 kW) technical requirements.

Common issues the utility lists

  • Applications without payment are not entered into the review process

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.