Citizens' Electric Company interconnection application

Citizens' Electric Company is an investor-owned utility serving 6,005 residential customers in Pennsylvania (EIA-861, 2025). Applications: PDF + mail (Mail to Citizens' Electric Engineering Dept., 1775 Industrial Blvd, Lewisburg PA 17837 (electronic copies to operations@citizenselectric.com)). Gridpol files Citizens' Electric Company interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Citizens' Electric Company’s official sources (see below).

Citizens' Electric Company at a glance

Utility

Citizens Electric Co (C&T Enterprises)

Type

Investor-owned utility

EIA utility ID

3597

Residential customers

6,005 (EIA-861, 2025)

Net-metered residential customers

83 (EIA-861, 2025)

Service territory

2 counties in Pennsylvania

How to apply

PDF + mail – Mail to Citizens' Electric Engineering Dept., 1775 Industrial Blvd, Lewisburg PA 17837 (electronic copies to operations@citizenselectric.com) · official link

Who submits

Customer or contractor; most customers use a professional installer.

Export compensation

NEM – Pennsylvania net metering (Net Metering Rider)

Review time (official)

Complete, legible applications typically approved in 10 business days or less.

Documents Citizens' Electric Company asks for

  • Interconnection application formLevel 1 Part 1 or Level 2-4 with Attachment A Gridpol prepares this.
  • Other utility-specific documentLetter of Intent & Acknowledgement of Costs
  • Net metering / net billing agreementNet Metering Rider Application
  • Other utility-specific documentIRS Form W-9 (mail with fee check, do not email)
  • Single-line diagram (one-line)plans meeting Part II Sec. 6-12 of Requirements for Customer-Owned Small Generation (single-line example provided) Gridpol prepares this.
  • Final inspection sign-offinspection by qualified licensed codes inspector; Level 1 Part 2 / Attachment B Certificate of Completion after construction
  • Other utility-specific document (when applicable)Virtual Aggregation Form

How the Citizens' Electric Company process runs

  1. Plan system per Requirements for Customer-Owned Small Generation
  2. Determine level and fee
  3. Mail/email application, Letter of Intent, NEM Rider application, W-9, plans; mail fee check
  4. Engineering review: conditional approval, rejection or info request; notice of upgrade costs
  5. Install (municipal permits may apply); inspection by licensed codes inspector; temporary energize for testing on request
  6. Submit Certificate of Completion; final acceptance before operation

Fees

FeeApplies toNote
$100Level 1check marked 'Net Metering Interconnection Fee'
$250 + $1/kWLevel 2
$350 + $1/kWLevel 3as listed on Citizens' page
contact utilityLevel 4

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote

levels per 52 Pa. Code §75.34, by total AC nameplate

Common issues the utility lists

  • Applications not approved until all documentation and fee check received

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited