Home › Utilities › New York › RG&E

Investor-owned utility

RG&E interconnection application

RG&E is an investor-owned utility serving 353,617 residential customers in New York (EIA-861, 2025). Applications: Own online portal (RG&E Distributed Generation online portal (NY SIR Interconnection Online Application Portal, IOAP)). Gridpol files RG&E interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from RG&E’s official sources (see below). Portal, documents (SIR Appendix F + Appendix K/H) and steps confirmed from RG&E online-portal page (archive capture 2026-04-11) and SIR Oct 2026. Minor gaps: live rge.com unreachable from server; RG&E-specific technical requirements document and NEM vs. Value Stack eligibility per project not checked; Appendix F/K PDFs linked by RG&E not opened (SIR versions read instead).

RG&E at a glance

Utility

Rochester Gas & Electric Corp (Avangrid (Iberdrola))

Type

Investor-owned utility

EIA utility ID

16183

Residential customers

353,617 (EIA-861, 2025)

Net-metered residential customers

3,405 (EIA-861, 2025)

Service territory

7 counties in New York

How to apply

Own online portal – RG&E Distributed Generation online portal (NY SIR Interconnection Online Application Portal, IOAP) · official link

Who submits

Application package is submitted in the name of the customer (SIR Step 3); contractor may act as the customer's agent with a customer-signed letter of authorization (SIR Appendix F). For CDG the project sponsor applies.

Export compensation

NEM – NY net metering (Phase One NEM for mass-market) / Value Stack
compensation per utility tariff under PSC Case 15-E-0751; verify per-project eligibility

Review time (official)

SIR <=50 kW: utility has 10 business days to determine completeness/approval; 10 business days after deficiency info received; applicant has 30 business days to cure or is removed from queue; NEM metering changes within 10 business days of completion notice; witnessed verification test within 10 business days of notice; applicant certifies test within 5 business days; final acceptance letter within 5 business days; project may be removed after 12 months of inactivity.

Documents RG&E asks for

  • Interconnection application formSIR standardized application (Appendix B inverter-based / C non-inverter) Gridpol prepares this.
  • Interconnection agreementsigned NYS Standardized Interconnection Contract (Appendix A) for residential <=50 kW
  • Letter of authorization / designated agent form (when applicable)customer-signed letter of authorization if contractor acts as agent
  • Other utility-specific document (when applicable)NYS Standardized Acknowledgement of Property Owner Consent Form (SIR Appendix H) - systems >50 kW up to 5 MW only; linked on RG&E portal page
  • Site plan / site layout (when applicable)for new service: site plan with interconnection point on satellite image (Google Earth/Bing); existing service: account and meter numbers Gridpol prepares this.
  • Other utility-specific documentproject narrative, DG type/fuel, AC kW size, net metered/remote/community designation
  • UL 1741 / IEEE 1547 certificationUL 1741 certificate (incl. SB); power-limited equipment needs manufacturer letter
  • Inverter spec sheetmanufacturer data sheet for interface equipment
  • Other utility-specific documentmanufacturer's verification test procedures (systems <=50 kW)
  • Single-line diagram (one-line)single-line for PV and BESS (three-line for other types); must show inverter protection settings, disconnects, components Gridpol prepares this.
  • Battery spec sheet (when applicable)Hybrid or stand-alone ESS: complete SIR Appendix K and upload with the application (RG&E portal page); covers configuration option, nameplate, export/import capacity

How the RG&E process runs

  1. Initial communication / inquiry; utility assigns a single point of contact (SIR Steps 1-2)
  2. If new or upgraded service is needed, submit RG&E Application for Service separately (RG&E portal page)
  3. Submit complete application package (SIR Appendix F; Appendix K for hybrid/ESS) in the customer's name via the RG&E DG online portal (IOAP) - no fee <=50 kW, $750 >50 kW
  4. RG&E reviews within 10 business days; acceptance includes executed NYS Standardized Interconnection Contract and whether RG&E will witness testing
  5. Install per accepted design (submit revised diagram for substantive changes); RG&E completes net-metering meter changes within 10 business days of completion notice
  6. Verification testing per Appendix F (witnessed within 10 business days of notice, or applicant certifies within 5 business days)
  7. Final acceptance letter within 5 business days; parallel operation

Fees

FeeApplies toNote
$0<=50 kWSIR Step 3: no application fee
$750Pre-applications and applications >50 kWnon-refundable (RG&E portal page); plus CESIR/upgrade costs per SIR

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Expedited (<=50 kW)50 kWinverter-based 50-300 kW certified UL 1741 SB may use expedited path (Exception 1)
Standard (>50 kW-5 MW)5000 kWscreens + CESIR if needed

SIR covers DG and ESS up to 5 MW AC

Storage, EV and stamps

Battery storage

SIR covers energy storage systems up to 5 MW AC inverter/converter nameplate; export capped at 5 MW. Appendix K: stand-alone vs hybrid (Option A charged only by DG, B ESS no export, C/D grid charging netted), market participation, nameplate per configuration, total export/import capacity; factory-limited ratings need manufacturer letter.

PE stamp

SIR Appendix F: drawings for systems interconnected at 1,000 V or greater must be sealed by a NYS licensed Professional Engineer. – PE-stamped drawings are not included in Gridpol.

Common issues the utility lists

  • Incomplete package per SIR Appendix F checklist (utility must list deficiencies)
  • Substantive design variation from accepted diagram without revised diagram
  • Failure to cure deficiencies within 30 business days
  • Non-certified equipment (fails UL 1741/UL 1741 SB screen)
  • Underground secondary network locations may need extra review or be denied

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited