RG&E is an investor-owned utility serving 353,617 residential customers in New York (EIA-861, 2025). Applications: Own online portal (RG&E Distributed Generation online portal (NY SIR Interconnection Online Application Portal, IOAP)). Gridpol files RG&E interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from RG&E’s official sources (see below). Portal, documents (SIR Appendix F + Appendix K/H) and steps confirmed from RG&E online-portal page (archive capture 2026-04-11) and SIR Oct 2026. Minor gaps: live rge.com unreachable from server; RG&E-specific technical requirements document and NEM vs. Value Stack eligibility per project not checked; Appendix F/K PDFs linked by RG&E not opened (SIR versions read instead).
RG&E at a glance
Rochester Gas & Electric Corp (Avangrid (Iberdrola))
TypeInvestor-owned utility
EIA utility ID16183
Residential customers353,617 (EIA-861, 2025)
Net-metered residential customers3,405 (EIA-861, 2025)
Service territory7 counties in New York
How to applyOwn online portal – RG&E Distributed Generation online portal (NY SIR Interconnection Online Application Portal, IOAP) · official link
Who submitsApplication package is submitted in the name of the customer (SIR Step 3); contractor may act as the customer's agent with a customer-signed letter of authorization (SIR Appendix F). For CDG the project sponsor applies.
Export compensationNEM – NY net metering (Phase One NEM for mass-market) / Value Stack
compensation per utility tariff under PSC Case 15-E-0751; verify per-project eligibility
SIR <=50 kW: utility has 10 business days to determine completeness/approval; 10 business days after deficiency info received; applicant has 30 business days to cure or is removed from queue; NEM metering changes within 10 business days of completion notice; witnessed verification test within 10 business days of notice; applicant certifies test within 5 business days; final acceptance letter within 5 business days; project may be removed after 12 months of inactivity.
Documents RG&E asks for
- Interconnection application formSIR standardized application (Appendix B inverter-based / C non-inverter) Gridpol prepares this.
- Interconnection agreementsigned NYS Standardized Interconnection Contract (Appendix A) for residential <=50 kW
- Letter of authorization / designated agent form (when applicable)customer-signed letter of authorization if contractor acts as agent
- Other utility-specific document (when applicable)NYS Standardized Acknowledgement of Property Owner Consent Form (SIR Appendix H) - systems >50 kW up to 5 MW only; linked on RG&E portal page
- Site plan / site layout (when applicable)for new service: site plan with interconnection point on satellite image (Google Earth/Bing); existing service: account and meter numbers Gridpol prepares this.
- Other utility-specific documentproject narrative, DG type/fuel, AC kW size, net metered/remote/community designation
- UL 1741 / IEEE 1547 certificationUL 1741 certificate (incl. SB); power-limited equipment needs manufacturer letter
- Inverter spec sheetmanufacturer data sheet for interface equipment
- Other utility-specific documentmanufacturer's verification test procedures (systems <=50 kW)
- Single-line diagram (one-line)single-line for PV and BESS (three-line for other types); must show inverter protection settings, disconnects, components Gridpol prepares this.
- Battery spec sheet (when applicable)Hybrid or stand-alone ESS: complete SIR Appendix K and upload with the application (RG&E portal page); covers configuration option, nameplate, export/import capacity
How the RG&E process runs
- Initial communication / inquiry; utility assigns a single point of contact (SIR Steps 1-2)
- If new or upgraded service is needed, submit RG&E Application for Service separately (RG&E portal page)
- Submit complete application package (SIR Appendix F; Appendix K for hybrid/ESS) in the customer's name via the RG&E DG online portal (IOAP) - no fee <=50 kW, $750 >50 kW
- RG&E reviews within 10 business days; acceptance includes executed NYS Standardized Interconnection Contract and whether RG&E will witness testing
- Install per accepted design (submit revised diagram for substantive changes); RG&E completes net-metering meter changes within 10 business days of completion notice
- Verification testing per Appendix F (witnessed within 10 business days of notice, or applicant certifies within 5 business days)
- Final acceptance letter within 5 business days; parallel operation
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | <=50 kW | SIR Step 3: no application fee |
| $750 | Pre-applications and applications >50 kW | non-refundable (RG&E portal page); plus CESIR/upgrade costs per SIR |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Expedited (<=50 kW) | 50 kW | inverter-based 50-300 kW certified UL 1741 SB may use expedited path (Exception 1) |
| Standard (>50 kW-5 MW) | 5000 kW | screens + CESIR if needed |
SIR covers DG and ESS up to 5 MW AC
Storage, EV and stamps
Battery storage
SIR covers energy storage systems up to 5 MW AC inverter/converter nameplate; export capped at 5 MW. Appendix K: stand-alone vs hybrid (Option A charged only by DG, B ESS no export, C/D grid charging netted), market participation, nameplate per configuration, total export/import capacity; factory-limited ratings need manufacturer letter.
PE stamp
SIR Appendix F: drawings for systems interconnected at 1,000 V or greater must be sealed by a NYS licensed Professional Engineer. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Incomplete package per SIR Appendix F checklist (utility must list deficiencies)
- Substantive design variation from accepted diagram without revised diagram
- Failure to cure deficiencies within 30 business days
- Non-certified equipment (fails UL 1741/UL 1741 SB screen)
- Underground secondary network locations may need extra review or be denied
Gridpol’s pre-submission check covers these before we file.
Sources
- RG&E Online Portal (archive.org capture 2026-04-11; live site timed out): https://web.archive.org/web/20260411090701/https://www.rge.com/w/online-portal (retrieved 2026-11-13)
- NYS Standardized Interconnection Requirements (SIR), effective Oct 1, 2026 (PDF; Sections I.B/I.C, Appendix F checklist): https://dps.ny.gov/nys-standardized-interconnection-requirements-effective-october-1-2026 (retrieved 2026-11-13)
- RG&E Distributed Generation (not reachable on 2026-11-13; content per search listing): https://www.rge.com/w/distributed-generation (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.