Home › Utilities › New York › Orange & Rockland (O&R)

Investor-owned utility

Orange & Rockland (O&R) interconnection application

Orange & Rockland (O&R) is an investor-owned utility serving 213,057 residential customers in New York (EIA-861, 2025). Applications: PowerClerk (PowerClerk - O&R 50 kW or less). Gridpol files Orange & Rockland (O&R) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Orange & Rockland (O&R)’s official sources (see below). >50 kW: https://oru-greaterthan50kw.powerclerk.com ($750); CDG: oru-communitydg.powerclerk.com. O&R also lists an Electric Vehicle Charging Registration link (not reviewed).

Orange & Rockland (O&R) at a glance

Utility

Orange & Rockland Utils Inc (Consolidated Edison Inc)

Type

Investor-owned utility

EIA utility ID

14154

Residential customers

213,057 (EIA-861, 2025)

Net-metered residential customers

14,015 (EIA-861, 2025)

Service territory

3 counties in New York

How to apply

PowerClerk – PowerClerk - O&R 50 kW or less · official link

Who submits

In most cases the certified installer handles the paperwork with a customer authorization letter.

Export compensation

NEM – NY net metering (Phase One NEM for mass-market) / Value Stack
compensation per utility tariff under PSC Case 15-E-0751; verify per-project eligibility

Review time (official)

SIR <=50 kW: utility has 10 business days to determine completeness/approval; 10 business days after deficiency info received; applicant has 30 business days to cure or is removed from queue; NEM metering changes within 10 business days of completion notice; witnessed verification test within 10 business days of notice; applicant certifies test within 5 business days; final acceptance letter within 5 business days; project may be removed after 12 months of inactivity.

Documents Orange & Rockland (O&R) asks for

  • Interconnection agreementexecuted interconnection agreement
  • Letter of authorization / designated agent formcustomer authorization letter
  • Site plan / site layoutproposed point of interconnection on satellite image Gridpol prepares this.
  • UL 1741 / IEEE 1547 certificationListing proof of the inverter (often covered by the spec sheet or the CEC/utility equipment list).
  • Inverter spec sheetinterface manufacturer data sheet
  • Other utility-specific documentmanufacturer verification test procedures
  • Single-line diagram (one-line)one-line (single phase) or three-line (three phase) incl. PCC wiring and existing service Gridpol prepares this.
  • Other utility-specific document (when applicable)>50 kW: Appendix B and check for $750 fee

How the Orange & Rockland (O&R) process runs

  1. Initial communication / inquiry (single point of contact assigned)
  2. Submit complete application package (Appendix F) in the customer's name via the utility's Interconnection Online Application Portal (IOAP) - no fee <=50 kW
  3. Utility reviews within 10 business days; acceptance includes executed Standardized Interconnection Contract and whether utility will witness testing
  4. Install per accepted design (revised diagram if substantive changes); NEM meter changes by utility
  5. Verification testing per Appendix F (witnessed or applicant-certified within 5 business days)
  6. Final acceptance letter (PTO) within 5 business days

Fees

FeeApplies toNote
$0<=50 kWSIR Step 3
$750>50 kW up to 5 MW (and pre-application)plus CESIR/construction costs; 25% payment if costs >$10,000

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Expedited (<=50 kW)50 kWinverter-based 50-300 kW certified UL 1741 SB may use expedited path (Exception 1)
Standard (>50 kW-5 MW)5000 kWscreens + CESIR if needed

SIR covers DG and ESS up to 5 MW AC

Storage, EV and stamps

Battery storage

SIR covers energy storage systems up to 5 MW AC inverter/converter nameplate; export capped at 5 MW. Appendix K: stand-alone vs hybrid (Option A charged only by DG, B ESS no export, C/D grid charging netted), market participation, nameplate per configuration, total export/import capacity; factory-limited ratings need manufacturer letter.

PE stamp

SIR Appendix F: drawings for systems interconnected at 1,000 V or greater must be sealed by a NYS licensed Professional Engineer. – PE-stamped drawings are not included in Gridpol.

Common issues the utility lists

  • Incomplete package per SIR Appendix F checklist (utility must list deficiencies)
  • Substantive design variation from accepted diagram without revised diagram
  • Failure to cure deficiencies within 30 business days
  • Non-certified equipment (fails UL 1741/UL 1741 SB screen)
  • Underground secondary network locations may need extra review or be denied

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited