PSEG Long Island (LIPA) interconnection application

PSEG Long Island (LIPA) is a state power authority serving 1,032,490 residential customers in New York (EIA-861, 2025). Applications: Own online portal (PSEG Long Island Interconnection Online Application Portal (IOAP)). Gridpol files PSEG Long Island (LIPA) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Partly researched from official sources. verify on first project: psegliny.com blocked automated access; portal URL not confirmed. LIPA uses its own SGIP (mirrors SIR: no fee <=50 kW, 10 business-day review, executed LIPA Standardized Interconnection Contract) and LIPA net metering tariff (not the state NEM law).

PSEG Long Island (LIPA) at a glance

Utility

Long Island Power Authority (Long Island Power Authority (operated by PSEG Long Island))

Type

State power authority

EIA utility ID

11171

Residential customers

1,032,490 (EIA-861, 2025)

Net-metered residential customers

95,569 (EIA-861, 2025)

Service territory

3 counties in New York

How to apply

Own online portal – PSEG Long Island Interconnection Online Application Portal (IOAP)

Who submits

Applicant via IOAP; contact Power Asset Management PSEG-LI-PAMInterconnect@pseg.com.

Export compensation

NEM – LIPA net metering (Tariff for Electric Service)
not governed by state NEM law

Review time (official)

SGIP <=50 kW: 10 business days completeness/approval; 10 business days after deficiency info; 30 business days to cure; NEM metering changes within 10 business days of request; 12-month inactivity rule.

Documents PSEG Long Island (LIPA) asks for

  • Interconnection application formSIR standardized application (Appendix B inverter-based / C non-inverter) Gridpol prepares this.
  • Interconnection agreementsigned NYS Standardized Interconnection Contract (Appendix A) for residential <=50 kW
  • Letter of authorization / designated agent form (when applicable)customer-signed letter of authorization if contractor acts as agent
  • Site plan / site layout (when applicable)for new service: site plan with interconnection point on satellite image (Google Earth/Bing); existing service: account and meter numbers Gridpol prepares this.
  • Other utility-specific documentproject narrative, DG type/fuel, AC kW size, net metered/remote/community designation
  • UL 1741 / IEEE 1547 certificationUL 1741 certificate (incl. SB); power-limited equipment needs manufacturer letter
  • Inverter spec sheetmanufacturer data sheet for interface equipment
  • Other utility-specific documentmanufacturer's verification test procedures (systems <=50 kW)
  • Single-line diagram (one-line)single-line for PV and BESS (three-line for other types); must show inverter protection settings, disconnects, components Gridpol prepares this.
  • Battery spec sheet (when applicable)SIR Appendix K ESS requirements (stand-alone/hybrid option, nameplate, export/import capacity)

How the PSEG Long Island (LIPA) process runs

  1. Initial communication / inquiry (single point of contact assigned)
  2. Submit complete application package (Appendix F) in the customer's name via the utility's Interconnection Online Application Portal (IOAP) - no fee <=50 kW
  3. Utility reviews within 10 business days; acceptance includes executed Standardized Interconnection Contract and whether utility will witness testing
  4. Install per accepted design (revised diagram if substantive changes); NEM meter changes by utility
  5. Verification testing per Appendix F (witnessed or applicant-certified within 5 business days)
  6. Final acceptance letter (PTO) within 5 business days

Fees

FeeApplies toNote
$0<=50 kWSIR Step 3
$750>50 kW up to 5 MW (and pre-application)plus CESIR/construction costs; 25% payment if costs >$10,000

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Expedited (<=50 kW)50 kWinverter-based 50-300 kW certified UL 1741 SB may use expedited path (Exception 1)
Standard (>50 kW-5 MW)5000 kWscreens + CESIR if needed

SIR covers DG and ESS up to 5 MW AC

Storage, EV and stamps

Battery storage

SIR covers energy storage systems up to 5 MW AC inverter/converter nameplate; export capped at 5 MW. Appendix K: stand-alone vs hybrid (Option A charged only by DG, B ESS no export, C/D grid charging netted), market participation, nameplate per configuration, total export/import capacity; factory-limited ratings need manufacturer letter.

PE stamp

SIR Appendix F: drawings for systems interconnected at 1,000 V or greater must be sealed by a NYS licensed Professional Engineer. – PE-stamped drawings are not included in Gridpol.

Common issues the utility lists

  • Incomplete package per SIR Appendix F checklist (utility must list deficiencies)
  • Substantive design variation from accepted diagram without revised diagram
  • Failure to cure deficiencies within 30 business days
  • Non-certified equipment (fails UL 1741/UL 1741 SB screen)
  • Underground secondary network locations may need extra review or be denied

Gridpol’s pre-submission check covers these before we file.

Sources

New York interconnection rule

Commission

New York State Public Service Commission (Department of Public Service)

Interconnection rule

NYS Standardized Interconnection Requirements (SIR), Case 24-E-0621 and predecessors – New York State Standardized Interconnection Requirements and Application Process for New Distributed Generators and/or Energy Storage Systems 5 MW or Less Connected in Parallel with Utility Distribution Systems · source

Applies to

PSC-regulated electric utilities: Central Hudson, Con Edison, NYSEG, National Grid (Niagara Mohawk), Orange & Rockland, RG&E; DG/ESS up to 5 MW AC in parallel with distribution system

Application form

Statewide standard application package (Appendix F checklist) submitted electronically via utility Interconnection Online Application Portal (IOAP); NYS Standardized Interconnection Contract; property owner consent form (>50 kW); site control form

Timelines

<=50 kW: utility determines completeness/approval within 10 BD; applicant has 30 BD to supply missing info; acceptance includes executed contract; metering changes for net metered systems within 10 BD; verification test within 10 BD of notice (or applicant certifies within 5 BD if not witnessed); final acceptance letter within 5 BD. >50 kW: completeness 10 BD, CESIR 60 BD, etc.

Fees

No application fee <=50 kW; $750 pre-application report (credited); supplemental screening $2,500 nonrefundable up to $5,000 actual; CESIR and upgrades at cost.

Insurance

No general liability insurance may be required for facilities <=300 kW AC (PSC recommends adequate insurance); 300 kW-1 MW $1M; >1-5 MW $2M per occurrence/$5M aggregate; >5 MW $5M (Standardized Contract sec. 7).

External disconnect

External manual visible gang-operated load-break disconnect required for systems >25 kW and for non-inverter systems <=25 kW; inverter-based systems <=25 kW exempt. Lockable with 3/8" shank padlock, labeled 'Generator Disconnect Switch' (SIR Section II.D).

Export compensation

NEM – PSL 66-j (solar etc.) and 66-l (wind); PSC VDER orders (Case 15-E-0751)
Mass-market customers interconnected after 2022 receive net metering with a Customer Benefit Contribution charge; larger projects on Value Stack (VDER). Details per utility tariff; not verified here.

Not bound by the rule

Municipal utilities (NYPA customers) and electric cooperatives are not bound by the SIR; PSEG Long Island/LIPA follows its own (LIPA) SIR-based requirements.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited