Home › Utilities › Nevada › Mt Wheeler Power, Inc.
Electric cooperativeMt Wheeler Power, Inc. interconnection application
Mt Wheeler Power, Inc. is an electric cooperative serving 5,387 residential customers in Nevada, Utah (EIA-861, 2025). Gridpol files Mt Wheeler Power, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Nevada’s commission rule (NRS 704.766-704.776 (net metering) and NAC 704.8812-704.8825; technical interconnection per each utility's PUCN-approved tariff (NV Energy Rule 15)) does not bind electric cooperatives; Mt Wheeler Power, Inc. sets its own interconnection policy. We confirm its form on the first project. Not covered by NRS 704.766-776 (utility = public utility). Rural electric cooperatives and municipal/district systems set their own net metering and interconnection policies.
Mt Wheeler Power, Inc. at a glance
Mt Wheeler Power, Inc
TypeElectric cooperative
EIA utility ID13073
Residential customers5,387 (EIA-861, 2025)
Net-metered residential customers17 (EIA-861, 2025)
Service territory4 counties in Nevada, 3 counties in Utah
Documents Mt Wheeler Power, Inc. asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Mt Wheeler Power, Inc.. We confirm Mt Wheeler Power, Inc.’s exact list on the first project.
Nevada interconnection rule
No statewide small-generator interconnection rule with levels; technical process, fees and disconnect rule are in NV Energy Rule 15 tariff (not retrieved). Official leg.state.nv.us blocked (403); archive copies used.
Public Utilities Commission of Nevada
Interconnection ruleNRS 704.766-704.776 (net metering) and NAC 704.8812-704.8825; technical interconnection per each utility's PUCN-approved tariff (NV Energy Rule 15) – Net metering statute and regulations; utility interconnection tariff · source
Applies toUtilities = public utilities supplying electricity in Nevada (NRS 704.772): Nevada Power and Sierra Pacific Power (NV Energy). Municipal utilities and cooperatives are not public utilities under this definition.
Application formUtility net metering application plus standard net metering contract created by the utility (NAC 704.8821); interconnection must be consistent with the utility's tariff (NAC 704.882(3))
TimelinesUtility reviews complete, compliant application and sends standard net metering contract within 10 business days (or returns incomplete application with deficiencies within 10 business days); authorizes interconnection or lists deficiencies within 10 business days after completion notice and receipt of governmental final inspection/clearance (NAC 704.8823). Utility final inspection 'within a reasonable time' (NRS 704.7745).
FeesSystems <=25 kW: no fees different from the customer's rate class (except universal energy charge and statutory charges). >25 kW: customer may pay for meter capable of measuring generation and load, and required system upgrades; no standby charge.
InsuranceUtility may not require additional liability insurance (or additional standards, tests or controls) for systems meeting NEC/UL/IEEE standards and holding required permits (NRS 704.774(3)).
External disconnectStatute bars utilities from requiring 'additional controls' for compliant systems (NRS 704.774(3)(c)); any disconnect requirement comes from the utility interconnection tariff (not retrieved).
Export compensationNet billing – NRS 704.773, 704.7732, 704.775
Systems <=1 MW. Monthly netting; excess carried forward indefinitely, no payout. For <=25 kW systems applied on/after 2017-06-15, excess credited at a stepped % of the retail rate (95%, 88%, 81%, then 75% in 80 MW tranches). 20-year right to continue net metering (NRS 704.773).
Not covered by NRS 704.766-776 (utility = public utility). Rural electric cooperatives and municipal/district systems set their own net metering and interconnection policies.
- NRS Chapter 704 (archive.org copy, 2026-11-09): https://web.archive.org/web/20261109060818/https://www.leg.state.nv.us/nrs/nrs-704.html (retrieved 2026-11-13)
- NAC Chapter 704 (archive.org copy, 2026-08-04): https://web.archive.org/web/20260804110508/https://www.leg.state.nv.us/NAC/NAC-704.html (retrieved 2026-11-13)
Other utilities in Nevada
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.