Home › Utilities › Montana › NorthWestern Energy (Montana)

Investor-owned utility

NorthWestern Energy (Montana) interconnection application

NorthWestern Energy (Montana) is an investor-owned utility serving 334,012 residential customers in Montana, Wyoming (EIA-861, 2025). Applications: PDF + email (Level 1 Small Generator Facility Interconnection Request to Interconnection Department (hand delivery, mail or e-mail)). Gridpol files NorthWestern Energy (Montana) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from NorthWestern Energy (Montana)’s official sources (see below). Wyoming service territory not researched separately (WY has its own tariff); verify for WY projects.

NorthWestern Energy (Montana) at a glance

Utility

NorthWestern Energy LLC (NorthWestern Energy Group)

Type

Investor-owned utility

EIA utility ID

12825

Residential customers

334,012 (EIA-861, 2025)

Net-metered residential customers

11,386 (EIA-861, 2025)

Service territory

36 counties in Montana, 2 counties in Wyoming

How to apply

PDF + email – Level 1 Small Generator Facility Interconnection Request to Interconnection Department (hand delivery, mail or e-mail) · official link

Who submits

Applicant must be the NorthWestern customer (or premises owner if customer is tenant) in good standing; installer contact listed on form. Applicant signs the request and Exhibit A.

Export compensation

NEM – Electric Tariff Rule No. 16 Electric Net Metering
Monthly kWh netting; excess balance carried to annual settle-up month chosen by customer, then resets to zero.

Review time (official)

Rule 17: Interconnection Agreement provided within 5 business days after Level 1 approval determination; applicant must return signed agreement within 30 business days or request is withdrawn. Level 2 evaluation within 20 business days after complete request.

Documents NorthWestern Energy (Montana) asks for

  • Interconnection application formLevel 1 Small Generator Facility Interconnection Request (Rev 1/23); Levels 2-4 separate form Gridpol prepares this.
  • Single-line diagram (one-line)Site electrical one-line diagram incl. storage device if any Gridpol prepares this.
  • Site plan / site layoutDetailed site diagram: array, inverter, storage and disconnect locations Gridpol prepares this.
  • PV module spec sheetManufacturer spec sheets for all certified equipment; component list with certifying entity/standard (IEEE 1547, NRTL)
  • Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
  • Battery spec sheet (when applicable)Storage nameplate kW plus explanation of charging/discharging/operating plan
  • Net metering / net billing agreement (when applicable)Exhibit A Net Meter Applicant Information (choose settle-up month Jan/Apr/Jul/Oct), signed
  • Customer signatureApplicant certification
  • Interconnection agreementProvided by NorthWestern after Level 1 approval; sign and return within 30 business days
  • Final inspection sign-offLocal/state electrical permit and inspection approval before connection

How the NorthWestern Energy (Montana) process runs

  1. Submit Level 1 request with $200 fee, line diagram, site map, spec sheets, Exhibit A
  2. Obtain local/state electrical permit in tandem
  3. Level 1 screens; approval
  4. Interconnection Agreement sent (5 BD), signed and returned (30 BD)
  5. Install; external visible lockable AC disconnect within 10 ft of meter
  6. Electrical inspector approval
  7. NorthWestern installs net meter and authorizes interconnected operation

Fees

FeeApplies toNote
$200Level 1 (<= 50 kW AC certified equipment)Non-refundable processing fee

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 150 kWAggregate generation + storage nameplate AC, certified equipment
Levels 2-4Separate request form (Rule 17)
Net metering cap50 kW

Net metered facilities only solar, wind and/or hydro (Rule 16).

Storage, EV and stamps

Battery storage

Level 1 storage must store/discharge only energy produced by the net metering system (no grid charging); customer must demonstrate compliance of charge/discharge functions with Rule 16 before connection.

Common issues the utility lists

  • AC disconnect more than 10 ft from meter without prior written variance
  • Customer not in good standing
  • Storage charging from grid on Level 1 net-metered system

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited