Home › Utilities › Minnesota › Minnesota Power

Investor-owned utility

Minnesota Power interconnection application

Minnesota Power is an investor-owned utility serving 126,520 residential customers in Minnesota (EIA-861, 2025). Applications: Own online portal (Minnesota Power Simplified Interconnection Application (Formstack)). Gridpol files Minnesota Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Minnesota Power’s official sources (see below). Post-install steps (witness test, meter) taken from MN DIP generic; confirm MP-specific PTO notice.

Minnesota Power at a glance

Utility

ALLETE, Inc. (ALLETE)

Type

Investor-owned utility

EIA utility ID

12647

Residential customers

126,520 (EIA-861, 2025)

Net-metered residential customers

1,210 (EIA-861, 2025)

Service territory

17 counties in Minnesota

How to apply

Own online portal – Minnesota Power Simplified Interconnection Application (Formstack) · official link

Who submits

Installer or customer; applicant chooses whether customer or installer pays the fee. Installers need a MyAccount to view and pay invoices.

Export compensation

NEM – Minnesota net metering (Uniform Statewide Contract)

Review time (official)

Preliminary review of complete applications within 15 business days (MP DG application process doc).

Documents Minnesota Power asks for

  • Interconnection application formOnline Simplified form (≤20 kW); MN DIP Attachment 3 PDF for Fast Track/Study Gridpol prepares this.
  • Proof of insuranceProof of insurance ≥$300,000 personal liability shown as a line item
  • Single-line diagram (one-line)All components in installation order Gridpol prepares this.
  • Site plan / site layoutBird's-eye view matching one-line Gridpol prepares this.
  • PV module spec sheetManufacturer data sheets
  • Inverter spec sheetManufacturer data sheets; certified inverter
  • Battery spec sheet (when applicable)Energy Storage Addendum for BESS (paired or standalone)
  • Interconnection agreementMN DIA / Uniform Statewide Contract
  • Other utility-specific documentCertificate of Completion (MN DIP Exhibit C)

How the Minnesota Power process runs

  1. Submit Simplified online form with documents
  2. Pay $100 + $30 surcharge
  3. Review/approval; all forms reviewed before installation
  4. Sign MN DIA / Uniform Statewide Contract
  5. Install; electrical inspection
  6. Submit Certificate of Completion (Exhibit C)
  7. Meter/witness test; permission to operate

Fees

FeeApplies toNote
$100Simplified (≤20 kW)plus $30 state surcharge (MN PUC ombudsperson)
$100 + $1/kWacFast Track+ $30
$1,000 + $2/kWacStudy+ $30

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Simplified20 kW
Fast Track250 kWbehind the meter <250 kWac (MP page)
Study10000 kW
Net metering cap40 kW

Uniform statewide net metering contract for systems <1,000 kWac; ≤40 kW retail-rate net metering (MN law)

Storage, EV and stamps

Battery storage

Energy Storage Addendum required when BESS is part of system or standalone.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited