Home › Utilities › Massachusetts › Eversource Energy (Massachusetts)

Investor-owned utility

Eversource Energy (Massachusetts) interconnection application

Eversource Energy (Massachusetts) is an investor-owned utility serving 1,274,856 residential customers in Massachusetts (EIA-861, 2025). Applications: PowerClerk (Eversource MA PowerClerk (Simplified / Expedited-Standard)). Gridpol files Eversource Energy (Massachusetts) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Eversource Energy (Massachusetts)’s official sources (see below). Simplified threshold per M.D.P.U. 55G (Aug 2026) is 25 kW; Eversource web page text still mentions 15 kW in places.

Eversource Energy (Massachusetts) at a glance

Utility

NSTAR Electric Company (Eversource Energy)

Type

Investor-owned utility

EIA utility ID

54913

Residential customers

1,274,856 (EIA-861, 2025)

Net-metered residential customers

89,475 (EIA-861, 2025)

Service territory

11 counties in Massachusetts

How to apply

PowerClerk – Eversource MA PowerClerk (Simplified / Expedited-Standard) · official link

Who submits

Installer/contractor on behalf of the Interconnecting Customer (application form has installer and electrical contractor sections); Interconnecting Customer must sign. eversource.com user ID required; CT PowerClerk contractor login works for MA. Exhibit H if billing customer is not system owner; Exhibit I landowner consent if applicable.

Export compensation

NEM – Net Metering (M.D.P.U. No. 68 tariff) / SMART incentive
Schedule Z required for net metering; SMART program separate.

Review time (official)

DPU-approved interconnection tariff (Simplified, radial): acknowledge 3 BD, completeness 10 BD, screens 15 BD (20 BD if Screen 5 fails), total max 25 BD (30 BD); witness test within 10 BD of Certificate of Completion; Authorization to Interconnect within 5 BD after requirements and meter installation.

Documents Eversource Energy (Massachusetts) asks for

  • Interconnection application formExhibit A Simplified Process application, signed by Interconnecting Customer Gridpol prepares this.
  • UL 1741 / IEEE 1547 certificationInverter manufacturer UL 1741 listing documentation; UL 1741 SB required since Oct 1, 2023
  • Single-line diagram (one-line)Electrical sketch/one-line; for Simplified does not need PE stamp (Eversource seminar); Expedited/Standard needs MA Electrical PE stamp Gridpol prepares this.
  • Site plan / site layout (when applicable)Required for Expedited/Standard (plan view, lot lines, pole numbers, meters, title block; no PE stamp) Gridpol prepares this.
  • Battery spec sheet (when applicable)Energy Storage Questionnaire/BESS sheet required for completeness when storage included
  • Net metering / net billing agreement (when applicable)Schedule Z - net metering application, if net metering sought
  • Other utility-specific document (when applicable)Exhibit H Retail Customer Agreement / Exhibit I Landowner Consent if applicable
  • Final inspection sign-offCertificate of Completion signed by local wiring inspector

How the Eversource Energy (Massachusetts) process runs

  1. (If new/upgraded service needed, request it first.) Installer submits Simplified Process application (Exhibit A) with supporting documents through the utility portal.
  2. Utility acknowledges receipt within 3 business days; completeness determination within 10 business days.
  3. Utility completes screens within 15 business days (20 if Screen 5 fails); total max 25 business days (30 with Screen 5 failure).
  4. Utility countersigns application approval line = Conditional Approval to Interconnect (minor system modifications billed if needed).
  5. Install facility; local electrical wiring inspector signs Certificate of Completion (installing electrical contractor also completes it).
  6. Return Certificate of Completion (and completion documentation); utility may perform Witness Test within 10 business days or it is deemed waived.
  7. Meter installation; utility issues Authorization to Interconnect within 5 business days after requirements met and meter installed. No parallel operation before Authorization to Interconnect.

Fees

FeeApplies toNote
$0Simplified, radial (non-network) <=25 kWTariff fee table
$100 / $300Simplified spot/area network (<=3 kW / >3 kW)
$4.50/kW (min $300, max $7,500)Expedited/Standard
up to $4,500Supplemental review30 h at $150/h

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Simplified (radial)25 kWUL-listed inverter, single-phase on single-phase service or three-phase on three-phase service; aggregate <15% of feeder peak
Simplified (network)25 kW<1/15 of customer minimum load
Expedited/StandardAbove simplified; pre-application required >=250 kW

Net metering classes: Class I <=60 kW, Class II 60-1,000 kW, Class III 1-2 MW.

Storage, EV and stamps

Battery storage

Storage must be disclosed; Energy Storage Questionnaire required for complete application (DPU 19-55 interim guidance); application asks whether ESS will participate in ISO-NE markets; export-limiting schemes can cap capacity used for group-study cost allocation.

PE stamp

Simplified: electrical sketch need not be PE stamped. Expedited/Standard: one-line stamped by a Massachusetts registered Electrical PE. – PE-stamped drawings are not included in Gridpol.

Common issues the utility lists

  • Single-phase inverters on a three-phase service do not qualify for Simplified
  • Application must be signed by Interconnecting Customer, show AC and DC size, voltage, phases, generator type, fault current; correct fee received (Eversource application checklist)
  • Missing Energy Storage Questionnaire when storage included -> application not complete

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks