Home › Utilities › Massachusetts › Eversource Energy (Massachusetts)
Investor-owned utilityEversource Energy (Massachusetts) interconnection application
Eversource Energy (Massachusetts) is an investor-owned utility serving 1,274,856 residential customers in Massachusetts (EIA-861, 2025). Applications: PowerClerk (Eversource MA PowerClerk (Simplified / Expedited-Standard)). Gridpol files Eversource Energy (Massachusetts) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Eversource Energy (Massachusetts)’s official sources (see below). Simplified threshold per M.D.P.U. 55G (Aug 2026) is 25 kW; Eversource web page text still mentions 15 kW in places.
Eversource Energy (Massachusetts) at a glance
NSTAR Electric Company (Eversource Energy)
TypeInvestor-owned utility
EIA utility ID54913
Residential customers1,274,856 (EIA-861, 2025)
Net-metered residential customers89,475 (EIA-861, 2025)
Service territory11 counties in Massachusetts
How to applyPowerClerk – Eversource MA PowerClerk (Simplified / Expedited-Standard) · official link
Who submitsInstaller/contractor on behalf of the Interconnecting Customer (application form has installer and electrical contractor sections); Interconnecting Customer must sign. eversource.com user ID required; CT PowerClerk contractor login works for MA. Exhibit H if billing customer is not system owner; Exhibit I landowner consent if applicable.
Export compensationNEM – Net Metering (M.D.P.U. No. 68 tariff) / SMART incentive
Schedule Z required for net metering; SMART program separate.
DPU-approved interconnection tariff (Simplified, radial): acknowledge 3 BD, completeness 10 BD, screens 15 BD (20 BD if Screen 5 fails), total max 25 BD (30 BD); witness test within 10 BD of Certificate of Completion; Authorization to Interconnect within 5 BD after requirements and meter installation.
Documents Eversource Energy (Massachusetts) asks for
- Interconnection application formExhibit A Simplified Process application, signed by Interconnecting Customer Gridpol prepares this.
- UL 1741 / IEEE 1547 certificationInverter manufacturer UL 1741 listing documentation; UL 1741 SB required since Oct 1, 2023
- Single-line diagram (one-line)Electrical sketch/one-line; for Simplified does not need PE stamp (Eversource seminar); Expedited/Standard needs MA Electrical PE stamp Gridpol prepares this.
- Site plan / site layout (when applicable)Required for Expedited/Standard (plan view, lot lines, pole numbers, meters, title block; no PE stamp) Gridpol prepares this.
- Battery spec sheet (when applicable)Energy Storage Questionnaire/BESS sheet required for completeness when storage included
- Net metering / net billing agreement (when applicable)Schedule Z - net metering application, if net metering sought
- Other utility-specific document (when applicable)Exhibit H Retail Customer Agreement / Exhibit I Landowner Consent if applicable
- Final inspection sign-offCertificate of Completion signed by local wiring inspector
How the Eversource Energy (Massachusetts) process runs
- (If new/upgraded service needed, request it first.) Installer submits Simplified Process application (Exhibit A) with supporting documents through the utility portal.
- Utility acknowledges receipt within 3 business days; completeness determination within 10 business days.
- Utility completes screens within 15 business days (20 if Screen 5 fails); total max 25 business days (30 with Screen 5 failure).
- Utility countersigns application approval line = Conditional Approval to Interconnect (minor system modifications billed if needed).
- Install facility; local electrical wiring inspector signs Certificate of Completion (installing electrical contractor also completes it).
- Return Certificate of Completion (and completion documentation); utility may perform Witness Test within 10 business days or it is deemed waived.
- Meter installation; utility issues Authorization to Interconnect within 5 business days after requirements met and meter installed. No parallel operation before Authorization to Interconnect.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Simplified, radial (non-network) <=25 kW | Tariff fee table |
| $100 / $300 | Simplified spot/area network (<=3 kW / >3 kW) | |
| $4.50/kW (min $300, max $7,500) | Expedited/Standard | |
| up to $4,500 | Supplemental review | 30 h at $150/h |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Simplified (radial) | 25 kW | UL-listed inverter, single-phase on single-phase service or three-phase on three-phase service; aggregate <15% of feeder peak |
| Simplified (network) | 25 kW | <1/15 of customer minimum load |
| Expedited/Standard | Above simplified; pre-application required >=250 kW |
Net metering classes: Class I <=60 kW, Class II 60-1,000 kW, Class III 1-2 MW.
Storage, EV and stamps
Battery storage
Storage must be disclosed; Energy Storage Questionnaire required for complete application (DPU 19-55 interim guidance); application asks whether ESS will participate in ISO-NE markets; export-limiting schemes can cap capacity used for group-study cost allocation.
PE stamp
Simplified: electrical sketch need not be PE stamped. Expedited/Standard: one-line stamped by a Massachusetts registered Electrical PE. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Single-phase inverters on a three-phase service do not qualify for Simplified
- Application must be signed by Interconnecting Customer, show AC and DC size, voltage, phases, generator type, fault current; correct fee received (Eversource application checklist)
- Missing Energy Storage Questionnaire when storage included -> application not complete
Gridpol’s pre-submission check covers these before we file.
Sources
- Eversource MA - Application to Interconnect: https://www.eversource.com/residential/about/doing-business-with-us/interconnections/massachusetts/massachusetts-application-to-interconnect (retrieved 2026-11-13)
- NSTAR Electric d/b/a Eversource - Standards for Interconnection of DG, M.D.P.U. No. 55G (eff. Aug 20, 2026): https://www.eversource.com/docs/default-source/rates-tariffs/mdpu-55a-interconnection-distributed-generation.pdf?sfvrsn=897b4555_4 (retrieved 2026-11-13)
- Eversource MA - Interconnection Resources: https://www.eversource.com/residential/about/doing-business-with-us/interconnections/massachusetts/massachusetts-application-to-interconnect/interconnection-resources (retrieved 2026-11-13)
- Eversource MA - DG Application Check List: https://www.eversource.com/docs/default-source/doing-business/dg-application-checklist.pdf?sfvrsn=41ac310f_2 (retrieved 2026-11-13)
- Eversource MA - Net Metering: https://www.eversource.com/residential/about/doing-business-with-us/interconnections/massachusetts/net-metering (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.