Home › Utilities › Massachusetts

Massachusetts

Massachusetts interconnection applications

46 electric utilities serve Massachusetts (EIA-861, 2025): 4 investor-owned utilitys, 40 municipal utilitys, 1 public power district, 1 state power authority. Together they serve 2,804,396 residential customers; 209,993 residential customers were on net metering at year-end 2025.

Largest utilities in Massachusetts

Eversource Energy (Massachusetts)Process verified

Investor-owned utility · 1,274,856 residential customers · Massachusetts

Applications: PowerClerk – Eversource MA PowerClerk (Simplified / Expedited-Standard)

Interconnection process and documents →
National Grid (Massachusetts)Process verified

Investor-owned utility · 1,231,865 residential customers · Massachusetts

Applications: Own online portal – National Grid Customer Application Portal (Salesforce)

Interconnection process and documents →
City of TauntonState guidance

Municipal utility · 34,952 residential customers · Massachusetts

Interconnection process and documents →
Town of ReadingState guidance

Municipal utility · 26,573 residential customers · Massachusetts

Interconnection process and documents →
Unitil (Fitchburg Gas and Electric Light)Partly researched

Investor-owned utility · 26,409 residential customers · Massachusetts

Applications: PowerClerk – Unitil Interconnection Program Portal (PowerClerk by Clean Power Research, announced Feb 2025); separate Interconnection Documentation Upload Portal

Interconnection process and documents →
City of ChicopeeState guidance

Municipal utility · 23,231 residential customers · Massachusetts

Interconnection process and documents →
City of PeabodyState guidance

Municipal utility · 22,697 residential customers · Massachusetts

Interconnection process and documents →
City of WestfieldState guidance

Municipal utility · 16,386 residential customers · Massachusetts

Interconnection process and documents →
Town of ShrewsburyState guidance

Municipal utility · 15,206 residential customers · Massachusetts

Interconnection process and documents →
City of HolyokeState guidance

Municipal utility · 15,155 residential customers · Massachusetts

Interconnection process and documents →
Town of MiddleboroughState guidance

Municipal utility · 14,978 residential customers · Massachusetts

Interconnection process and documents →
Town of BraintreeState guidance

Municipal utility · 14,090 residential customers · Massachusetts

Interconnection process and documents →

Export compensation among the researched Massachusetts utilities: NEM. Rules differ by utility – see each utility page.

Massachusetts interconnection rule

Commission

Massachusetts Department of Public Utilities (DPU)

Interconnection rule

DPU-approved uniform 'Standards for Interconnection of Distributed Generation' tariff of each distribution company (National Grid M.D.P.U. No. 1468; Eversource/NSTAR M.D.P.U. No. 55D; Unitil/FG&E M.D.P.U. No. 484); dockets incl. D.P.U. 19-55, D.P.U. 23-140 – Standards for Interconnection of Distributed Generation · source

Applies to

The investor-owned electric distribution companies (Eversource/NSTAR Electric, National Grid/Massachusetts Electric & Nantucket Electric, Unitil/Fitchburg Gas & Electric). Municipal light plants are not subject.

Application form

Uniform tariff exhibits: Exhibit A Simplified Process Interconnection Application (with Certificate of Completion attachment), Exhibit B Pre-Application Report form, Exhibit C Expedited/Standard application; Interconnection Service Agreement.

Timelines

All time frames in Company Business Days. Simplified (radial): acknowledgement 3 BD, completeness 10 BD, screen review (20 BD if failing screen 5), conditional approval by signed application, witness test within 10 BD of Certificate of Completion or deemed waived, Authorization to Interconnect within 5 BD. Pre-Application Report required >= 250 kW, issued within 10 BD (fee $100 <250 kW, $250 250-500 kW, $750 >500 kW).

Fees

Simplified $28; Expedited/Standard $4.50/kW (min $300, max $7,500) plus supplemental review/studies at cost; witness test actual cost up to $300 plus driving time (Table 6).

Insurance

No insurance required for facilities eligible for Class I net metering (<= 60 kW) per 220 CMR 18.03(2) (company recommends adequate insurance). Otherwise general liability: $500,000 for >10-100 kW; $1M for >100 kW-1 MW; $2M/$5M aggregate for >1-5 MW; $5M for >5 MW (tariff Sec. 11.1).

External disconnect

For Listed inverters the Company MAY require an external disconnect switch (or comparable device by mutual agreement) at the PCC, accessible at all times, gang-operated, visible break, lockable open (tariff 4.2.3.1(b)).

Export compensation

NEM – M.G.L. c. 164 §§ 138-140; 220 CMR 18.00 (Net Metering)
220 CMR 18.02: Class I <= 60 kW (any eligible generation); Class II > 60 kW to <= 1 MW and Class III > 1 MW to <= 2 MW (agricultural, anaerobic digestion, solar or wind). Subject to aggregate net metering caps (not re-read). Applies to distribution companies only.

Not bound by the rule

Municipal light plants (about 40, e.g., WGELD) are not subject to the DPU interconnection tariff or 220 CMR 18.00 and set their own interconnection and net metering policies (some use a similar simplified application).

LevelUp toCriteria / review / fee
Simplified Process – radial (3.1)25 kWListed inverter-based; <= 15 kW single-phase on single-phase service, or <= 25 kW three-phase on three-phase service; aggregate < 15% of feeder/line-segment annual peak load. Network: listed inverter < 1/15 of customer minimum load and <= 15 kW · Acknowledge 3 business days; completeness 10 business days; 20 business days review if screen 5 failed; witness test within 10 business days of Certificate of Completion (else waived); Authorization to Interconnect within 5 business days · $28 per application (spot/area network listed inverter: <=3 kW $100, >3 kW $300)
Expedited Process (3.3)Listed facilities on radial EPS passing pre-specified screens; supplemental review if screens failed · Acknowledge 3 BD; completeness 10 BD; supplemental review 20 BD · $4.50/kW, min $300, max $7,500; supplemental review up to 30 engineering hours
Standard Process (3.4)All facilities not qualifying for Simplified/Expedited, and all facilities on area networks; impact/facility studies, group studies · Per tariff Tables 3-4 · $4.50/kW, min $300, max $7,500 plus actual study costs
Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited