Investor-owned utilityNational Grid (Massachusetts) interconnection application
National Grid (Massachusetts) is an investor-owned utility serving 1,231,865 residential customers in Massachusetts (EIA-861, 2025). Applications: Own online portal (National Grid Customer Application Portal (Salesforce)). Gridpol files National Grid (Massachusetts) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from National Grid (Massachusetts)’s official sources (see below). Simplified fee ($28) and PE-stamp rule for PV+storage taken from NG portal documents; confirm in M.D.P.U. 1646 on first project.
National Grid (Massachusetts) at a glance
Massachusetts Electric Co (National Grid plc)
TypeInvestor-owned utility
EIA utility ID11804
Residential customers1,231,865 (EIA-861, 2025)
Net-metered residential customers114,502 (EIA-861, 2025)
Service territory12 counties in Massachusetts
How to applyOwn online portal – National Grid Customer Application Portal (Salesforce) · official link
Who submitsInstaller/developer submits in portal on behalf of Interconnecting Customer (system owner); Exhibit H required if billing account holder is not system owner; registered users communicate via case chatter.
Export compensationNEM – Net Metering Provision M.D.P.U. 1625 (03/01/2026) / SMART
Schedule Z required
DPU-approved interconnection tariff (Simplified, radial): acknowledge 3 BD, completeness 10 BD, screens 15 BD (20 BD if Screen 5 fails), total max 25 BD (30 BD); witness test within 10 BD of Certificate of Completion; Authorization to Interconnect within 5 BD after requirements and meter installation.
Documents National Grid (Massachusetts) asks for
- Interconnection application formExhibit A Simplified Interconnection Application (M.D.P.U. 1646, 11/1/2026), webform with e-signature, signature & date required Gridpol prepares this.
- Site plan / site layoutTo scale with scale bar, north arrow, property lines, streets, all meters, isolation device, PCC, nearest pole number, existing systems (ESB 756 C 5.1.4) Gridpol prepares this.
- Single-line diagram (one-line)Line diagram; equipment must match application and Equipment Selector; required notes on grouped/lockable metering and disconnects; ESS charge/discharge and derating notes Gridpol prepares this.
- PV module spec sheetTechnical specification sheets for all equipment
- Inverter spec sheetPlus UL 1741 SB certificate
- Battery spec sheet (when applicable)ESS Questionnaire (webform) + cut sheets; total ESS kWh and AC/DC coupling must match
- Net metering / net billing agreement (when applicable)Schedule Z (M.D.P.U. 1646) for net metering
- Other utility-specific document (when applicable)Exhibit H Retail Customer Agreement if billing account holder is not system owner; Exhibit I Landowner Consent; curtailment/derating letter on manufacturer letterhead if system larger than export
- Final inspection sign-offExhibit A2 Certificate of Completion + Simplified Process Completion Documentation Checklist + commissioning memo
- Photos (meter, main panel, equipment) (when applicable)PV plaques must be visible in pictures accompanying completion documentation
How the National Grid (Massachusetts) process runs
- (If new/upgraded service needed, request it first.) Installer submits Simplified Process application (Exhibit A) with supporting documents through the utility portal.
- Utility acknowledges receipt within 3 business days; completeness determination within 10 business days.
- Utility completes screens within 15 business days (20 if Screen 5 fails); total max 25 business days (30 with Screen 5 failure).
- Utility countersigns application approval line = Conditional Approval to Interconnect (minor system modifications billed if needed).
- Install facility; local electrical wiring inspector signs Certificate of Completion (installing electrical contractor also completes it).
- Return Certificate of Completion (and completion documentation); utility may perform Witness Test within 10 business days or it is deemed waived.
- Meter installation; utility issues Authorization to Interconnect within 5 business days after requirements met and meter installed. No parallel operation before Authorization to Interconnect.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $28 | Simplified application fee | As listed on NG MA documents page (DPU 15-155) |
| $4.50/kW (min $300, max $7,500) | Expedited/Standard | per tariff |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Simplified | 50 kW | <=50 kW AC system size with <=25 kW AC total export (NG checklist 08/2026, MDPU 1632/1646) |
| Expedited | Not Simplified; Standard recommended for non-inverter and >=500 kW |
Storage, EV and stamps
Battery storage
Batteries (ESS) must be entered in portal, ESS Questionnaire required (DPU 19-55 interim guidance); AC/DC coupling, kWh and charge/discharge intentions must be shown on one-line and match all documents; curtailment letter if export limited.
EV chargers
Service work for EV: 'New EV - Electric Service Form' and 'Electric Service Upgrade Form' (PDF, 8/15/2024) on NG MA documents page; requires pending/active billing account.
PE stamp
NG checklist: Electrical PE stamp required for any non-PV-only project (e.g., PV+storage) in Simplified, and for all Expedited; site plans stamped by Electrical PE in project state per ESB 756 C 5.1.4(A). – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Equipment on line diagram not matching application/Equipment Selector/completion documentation
- Missing ESS Questionnaire or ESS data mismatch (kWh, AC/DC coupling, aggregate size)
- Address mismatch between portal, site plan and application
- Missing required one-line notes (grouped, outside, 24/7 lockable metering and disconnects)
- PV plaques not visible in completion photos
Gridpol’s pre-submission check covers these before we file.
Sources
- National Grid Customer Application Portal - MA Interconnection Documents (Oct 29, 2026): https://gridforce.my.site.com/s/article/MA-Interconnection-Documents (retrieved 2026-11-13)
- National Grid - Application Checklist for Simple and Expedited (08/19/2026): https://gridforce.my.site.com/servlet/servlet.FileDownload?file=015Vw00000Udltp (retrieved 2026-11-13)
- MA DPU standard interconnection tariff (Eversource M.D.P.U. 55G) - uniform Simplified Process timelines: https://www.eversource.com/docs/default-source/rates-tariffs/mdpu-55a-interconnection-distributed-generation.pdf?sfvrsn=897b4555_4 (retrieved 2026-11-13)
Other utilities in Massachusetts
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.