Home › Utilities › Massachusetts › National Grid (Massachusetts)

Investor-owned utility

National Grid (Massachusetts) interconnection application

National Grid (Massachusetts) is an investor-owned utility serving 1,231,865 residential customers in Massachusetts (EIA-861, 2025). Applications: Own online portal (National Grid Customer Application Portal (Salesforce)). Gridpol files National Grid (Massachusetts) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from National Grid (Massachusetts)’s official sources (see below). Simplified fee ($28) and PE-stamp rule for PV+storage taken from NG portal documents; confirm in M.D.P.U. 1646 on first project.

National Grid (Massachusetts) at a glance

Utility

Massachusetts Electric Co (National Grid plc)

Type

Investor-owned utility

EIA utility ID

11804

Residential customers

1,231,865 (EIA-861, 2025)

Net-metered residential customers

114,502 (EIA-861, 2025)

Service territory

12 counties in Massachusetts

How to apply

Own online portal – National Grid Customer Application Portal (Salesforce) · official link

Who submits

Installer/developer submits in portal on behalf of Interconnecting Customer (system owner); Exhibit H required if billing account holder is not system owner; registered users communicate via case chatter.

Export compensation

NEM – Net Metering Provision M.D.P.U. 1625 (03/01/2026) / SMART
Schedule Z required

Review time (official)

DPU-approved interconnection tariff (Simplified, radial): acknowledge 3 BD, completeness 10 BD, screens 15 BD (20 BD if Screen 5 fails), total max 25 BD (30 BD); witness test within 10 BD of Certificate of Completion; Authorization to Interconnect within 5 BD after requirements and meter installation.

Documents National Grid (Massachusetts) asks for

  • Interconnection application formExhibit A Simplified Interconnection Application (M.D.P.U. 1646, 11/1/2026), webform with e-signature, signature & date required Gridpol prepares this.
  • Site plan / site layoutTo scale with scale bar, north arrow, property lines, streets, all meters, isolation device, PCC, nearest pole number, existing systems (ESB 756 C 5.1.4) Gridpol prepares this.
  • Single-line diagram (one-line)Line diagram; equipment must match application and Equipment Selector; required notes on grouped/lockable metering and disconnects; ESS charge/discharge and derating notes Gridpol prepares this.
  • PV module spec sheetTechnical specification sheets for all equipment
  • Inverter spec sheetPlus UL 1741 SB certificate
  • Battery spec sheet (when applicable)ESS Questionnaire (webform) + cut sheets; total ESS kWh and AC/DC coupling must match
  • Net metering / net billing agreement (when applicable)Schedule Z (M.D.P.U. 1646) for net metering
  • Other utility-specific document (when applicable)Exhibit H Retail Customer Agreement if billing account holder is not system owner; Exhibit I Landowner Consent; curtailment/derating letter on manufacturer letterhead if system larger than export
  • Final inspection sign-offExhibit A2 Certificate of Completion + Simplified Process Completion Documentation Checklist + commissioning memo
  • Photos (meter, main panel, equipment) (when applicable)PV plaques must be visible in pictures accompanying completion documentation

How the National Grid (Massachusetts) process runs

  1. (If new/upgraded service needed, request it first.) Installer submits Simplified Process application (Exhibit A) with supporting documents through the utility portal.
  2. Utility acknowledges receipt within 3 business days; completeness determination within 10 business days.
  3. Utility completes screens within 15 business days (20 if Screen 5 fails); total max 25 business days (30 with Screen 5 failure).
  4. Utility countersigns application approval line = Conditional Approval to Interconnect (minor system modifications billed if needed).
  5. Install facility; local electrical wiring inspector signs Certificate of Completion (installing electrical contractor also completes it).
  6. Return Certificate of Completion (and completion documentation); utility may perform Witness Test within 10 business days or it is deemed waived.
  7. Meter installation; utility issues Authorization to Interconnect within 5 business days after requirements met and meter installed. No parallel operation before Authorization to Interconnect.

Fees

FeeApplies toNote
$28Simplified application feeAs listed on NG MA documents page (DPU 15-155)
$4.50/kW (min $300, max $7,500)Expedited/Standardper tariff

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Simplified50 kW<=50 kW AC system size with <=25 kW AC total export (NG checklist 08/2026, MDPU 1632/1646)
ExpeditedNot Simplified; Standard recommended for non-inverter and >=500 kW

Storage, EV and stamps

Battery storage

Batteries (ESS) must be entered in portal, ESS Questionnaire required (DPU 19-55 interim guidance); AC/DC coupling, kWh and charge/discharge intentions must be shown on one-line and match all documents; curtailment letter if export limited.

EV chargers

Service work for EV: 'New EV - Electric Service Form' and 'Electric Service Upgrade Form' (PDF, 8/15/2024) on NG MA documents page; requires pending/active billing account.

PE stamp

NG checklist: Electrical PE stamp required for any non-PV-only project (e.g., PV+storage) in Simplified, and for all Expedited; site plans stamped by Electrical PE in project state per ESB 756 C 5.1.4(A). – PE-stamped drawings are not included in Gridpol.

Common issues the utility lists

  • Equipment on line diagram not matching application/Equipment Selector/completion documentation
  • Missing ESS Questionnaire or ESS data mismatch (kWh, AC/DC coupling, aggregate size)
  • Address mismatch between portal, site plan and application
  • Missing required one-line notes (grouped, outside, 24/7 lockable metering and disconnects)
  • PV plaques not visible in completion photos

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.