Beauregard Electric Cooperative, Inc. is an electric cooperative serving 40,452 residential customers in Louisiana (EIA-861, 2025). Gridpol files Beauregard Electric Cooperative, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Louisiana’s interconnection rule (LPSC General Order dated 09-19-2019 (Docket R-33929), Distributed Generation Rule, incl. Standard Interconnection Agreement) applies to Beauregard Electric Cooperative, Inc.. Levels, timelines and documents below come from that rule; Beauregard Electric Cooperative, Inc.’s own form and portal are confirmed on the first project.

Beauregard Electric Cooperative, Inc. at a glance

Utility

Beauregard Electric Coop, Inc

Type

Electric cooperative

EIA utility ID

1458

Residential customers

40,452 (EIA-861, 2025)

Net-metered residential customers

486 (EIA-861, 2025)

Service territory

7 counties in Louisiana

Documents Beauregard Electric Cooperative, Inc. asks for

  • Interconnection agreementRequired by the state rule
  • Interconnection application formRequired by the state rule Gridpol prepares this.
  • Single-line diagram (one-line)Required by the state rule Gridpol prepares this.
  • Inverter spec sheetRequired by the state rule

Documents required by the Louisiana rule. Beauregard Electric Cooperative, Inc. may ask for more on its own form; we confirm on the first project.

Louisiana interconnection rule

Commission

Louisiana Public Service Commission

Interconnection rule

LPSC General Order dated 09-19-2019 (Docket R-33929), Distributed Generation Rule, incl. Standard Interconnection Agreement – Distributed Generation Rules · source

Applies to

LPSC-jurisdictional electric utilities: investor-owned utilities and electric cooperatives (definition of Electric Utility, La. R.S. 45:1161); not municipal utilities; Entergy New Orleans is regulated by the New Orleans City Council

Application form

Statewide Standard Interconnection Agreement (Part I standard information sections 1-4 + terms) filed by each utility

Timelines

Residential: submit Standard Interconnection Agreement at least 30 business days before interconnection, 30-day review (best efforts 14 days). Commercial/community: submit at least 45 business days before, 45-day review. Customer must document date of notification (Sec. 5.2).

Fees

Utility may assess greater fees or customer charges to DG customers only if authorized by the Commission after notice in a rate case or formula rate plan proceeding (Sec. 6.3). Interconnection costs for inadequate facilities per utility extension policies.

Insurance

Not addressed in the rule text reviewed.

External disconnect

Visibly open, lockable, manual, clearly labeled disconnect switch accessible to utility required, unless waived by utility under Section 4 of the Standard Interconnection Agreement: waiver if inverter cannot be manually overridden and shuts down on loss of utility, manufacturer warrants it, and inverter is properly installed and inspected/tested by utility (utility discretion).

Export compensation

Net billing – LPSC General Order 09-19-2019 (R-33929)
For interconnection requests/installations after 2019-12-31: customer pays full retail rate for all energy purchased, zero rate for self-consumed energy, and exports credited at the utility's avoided cost (published annually by LPSC). Earlier customers grandfathered (15 years).

Not bound by the rule

Electric cooperatives are bound. Municipal utilities (e.g. Lafayette Utilities System) are not LPSC-jurisdictional and set their own policies; New Orleans follows City Council rules.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.