Home › Utilities › Illinois › ComEd
Investor-owned utilityComEd interconnection application
ComEd is an investor-owned utility serving 3,753,924 residential customers in Illinois (EIA-861, 2025). Applications: Own online portal (ComEd interconnection portal). Gridpol files ComEd interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from ComEd’s official sources (see below). Level 1 review day counts (Part 466) not extracted from ComEd Appendix 1; confirm on first project.
ComEd at a glance
Commonwealth Edison Co (Exelon)
TypeInvestor-owned utility
EIA utility ID4110
Residential customers3,753,924 (EIA-861, 2025)
Net-metered residential customers73,159 (EIA-861, 2025)
Service territory24 counties in Illinois
How to applyOwn online portal – ComEd interconnection portal · official link
Who submitsInterconnection Customer (customer) or installer; ComEd states installers normally file but customers may apply themselves. Combined interconnection + net metering application possible (select level, then 'net metering' as intent of generation). Mail alternative: ComEd Interconnection Services, 2 Lincoln Center 9th Floor, Oakbrook Terrace IL 60181 (check/money order).
Export compensationNet billing – Rider NM - Net Metering (CEJA)
Systems with PTO on/after 1 Jan 2025 net only the Supply portion (kWh or monetary credit, non-expiring); legacy pre-2025 systems keep full retail. DG rebate $250-300/kW for smart-inverter systems (separate).
Per Part 466 and ComEd Appendix 1 timeline (not extracted); pre-application report within 20 business days. Initial completeness screen then technical review.
Documents ComEd asks for
- Interconnection application formIllinois Standard DG Interconnection Level 1 (or 2-4) application, online preferred Gridpol prepares this.
- Single-line diagram (one-line)One-line diagram; PE stamp NOT required for Level 1/Level 2 < 1 MW Gridpol prepares this.
- Site plan / site layoutSite plan with POI and array layout Gridpol prepares this.
- PV module spec sheetEquipment data sheets
- Inverter spec sheetEquipment data sheets; lab-certified (UL 1741) for Level 1
- Other utility-specific document (when applicable)Manufacturer derate letter + supplemental nameplate label if inverter configured below nameplate (Part 466.75(c)(5)); proposed export-control settings for limited/non-export systems
- Other utility-specific document (when applicable)Proof of site control (deed, lease, tax bill) if applicant is not current ComEd customer at site
- Photos (meter, main panel, equipment)Photos of inverter nameplates after installation (for Certificate of Completion)
- Final inspection sign-offProof of electrical inspection from AHJ
- Other utility-specific document (when applicable)As-built drawings if changed
- Net metering / net billing agreement (when applicable)Net metering application (online or NetMeteringApplication.pdf)
How the ComEd process runs
- Optional pre-application report ($300)
- Submit interconnection (+ net metering) application with fee at interconnect.comed.com
- Completeness screen, then technical review (Level 1 screens)
- Approval / interconnection agreement (Level 1 standard terms); pay any upgrade costs
- Install; contractor tests; AHJ electrical inspection
- Upload inverter nameplate photos, AHJ inspection proof, as-built drawings; witness test if required
- Customer and ComEd sign 'Approval for Operation of Generating Facility in Parallel' (Certificate of Completion) = PTO; net metering begins. Energizing before PTO leads to disconnection.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $50 | Level 1 (export ≤25 kW, nameplate ≤50 kW, lab-certified inverter) | Review does not start until fee paid |
| $100 + $1/kVA | Level 2 (up to 5 MW dep. on line voltage) | |
| $500 + $2/kVA | Level 3 (non-export) | |
| $1,000 + $2/kVA | Level 4 (≤10 MVA) | |
| $300 | Optional pre-application report | non-binding |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 25 kW | export capacity ≤25 kW and nameplate ≤50 kW, lab-certified inverter |
| Level 2 | 5000 kW | dependent on line voltage, Part 466.80(b) |
| Level 3 | non-exporting | |
| Level 4 | 10000 kW | ≤10 MVA |
Illinois rules 83 Ill. Adm. Code Part 466 (≤10 MVA)
Storage, EV and stamps
Battery storage
ESS is an eligible DER and goes through the same levels. Level 1 is based on export capacity (≤25 kW) with nameplate ≤50 kW, so storage that is limited-export/non-export can stay in Level 1. Export controls per Part 466.75(c); limited-export inverter systems must use advanced inverter modes/settings specified by ComEd; proposed control settings required before evaluation; may be field-verified/witness-tested. DG rebate also available for storage (smart inverter required).
PE stamp
Not required for Level 1 or Level 2 < 1.0 MW unless required by Illinois Professional Engineering Act; larger (Community Supply/C&I) applications need Illinois PE-stamped one-line, three-line, relay schematics and settings. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Application received without fee is not reviewed
- Incomplete or inconsistent application package (data must match across documents)
- Missing proposed control/protection settings for systems operated below nameplate
- Missing manufacturer derate letter for derated inverters
Gridpol’s pre-submission check covers these before we file.
Sources
- ComEd DER Interconnection Requirements for Interconnection Customers, Rev. 3, 9/10/2026: https://www.comed.com/cdn/assets/v3/assets/blt3ebb3fed6084be2a/blt2bdb5921266bf5c4/6ab15b81a6ea1d80e833b7ff/DER_Interconnection_Requirements_2026_Rev09102026.pdf?branch=prod_alias (retrieved 2026-11-13)
- ComEd Net Metering: https://www.comed.com/MyAccount/MyService/Pages/NetMetering.aspx (retrieved 2026-11-13)
- ComEd Net Metering FAQ 2026: https://www.comed.com/cdn/assets/v3/assets/blt3ebb3fed6084be2a/bltceb8d9495434223b/6a3eb57c41c29aeee5636a03/20099-1_Net_Metering_FAQ_2026_0616A.pdf (retrieved 2026-11-13)
Other utilities in Illinois
- Ameren Illinois1,062,810
- MidAmerican Energy73,481
- City of Springfield59,366
- City of Naperville57,225
- Corn Belt Energy Corporation34,952
- Southwestern Electric Cooperative Inc.24,414
- Southeastern IL Electric Cooperative, Inc.22,607
- Norris Electric Cooperative18,163
- Jo-Carroll Energy, Inc.17,278
- Tri-County Electric Cooperative, Inc. (IL)16,203
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.