Investor-owned utilityPG&E interconnection application
PG&E is an investor-owned utility serving 5,055,556 residential customers in California (EIA-861, 2025). Applications: Own online portal (PG&E Interconnection Portal (YourProjects)). Gridpol files PG&E interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from PG&E’s official sources (see below). Rejection reasons derived from PG&E requirements, not an official deficiency list.
PG&E at a glance
Pacific Gas & Electric Co. (PG&E Corporation)
TypeInvestor-owned utility
EIA utility ID14328
Residential customers5,055,556 (EIA-861, 2025)
Net-metered residential customers924,854 (EIA-861, 2025)
Service territory50 counties in California
How to applyOwn online portal – PG&E Interconnection Portal (YourProjects) · official link
Who submitsUsually the contractor. Customer of record signs the Agreement and Customer Authorization (A&A, Form 79-1151A) authorizing the contractor to submit the Standard NEM/NBT application (Form 79-1151B) and receive the executed Interconnection Agreement and PTO letter; A&A must be signed (DocuSign or upload, all pages) before Step 2 of the online application.
Export compensationNet billing – Solar Billing Plan (Net Billing Tariff, NBT)
NEM2 applications without final electrical clearance by 11:59 pm 14 Apr 2026 were moved to Solar Billing Plan; customer must take an eligible rate.
Standard NEM: typically 5-10 business days after complete documentation; maximum 30 business days to PTO (per PG&E NEM page).
Documents PG&E asks for
- Letter of authorization / designated agent formAgreement and Customer Authorization, Form 79-1151A (signed by customer of record)
- Interconnection application formStandard NEM/NBT Interconnection Application Form 79-1151B (systems ≤30 kW) completed online Gridpol prepares this.
- Recent electric billMost recent PG&E Energy Statement: Electric Service Agreement ID, meter ID, service address matching final building permit
- Single-line diagram (one-line) (when applicable)Portal generates SLD; upload custom SLD only if tool diagram is inaccurate Gridpol prepares this.
- PV module spec sheet (when applicable)Only if PV module/inverter not on Go Solar California (CEC) list
- Inverter spec sheet (when applicable)Only if not on CEC list
- UL 1741 / IEEE 1547 certification (when applicable)NRTL UL1741 documentation for inverters not on CEC list
- Customer signatureCA consumer protection docs for residential: CPUC Solar Consumer Protection Guide signed by customer, CSLB Solar Disclosure, installation contract, CSLB license no.
- Final inspection sign-offScanned final building permit/inspection certificate showing generating facility address, scope of work, final approval date and signature
- Other utility-specific document (when applicable)Variance request if Distribution Interconnection Handbook/Greenbook requirements cannot be met (POI vs main breaker, AC disconnect distance)
- Interconnection agreementSigned in portal before PTO
How the PG&E process runs
- Customer signs A&A (Form 79-1151A) in YourProjects portal
- Contractor completes Standard NEM/NBT application (79-1151B) and uploads consumer protection docs and supplements
- Automated network capacity check; engineering review if needed
- Install and pass local building inspection; upload final permit/inspection
- Customer signs Interconnection Agreement
- PG&E issues Permission to Operate letter - never energize before PTO
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Standard NEM/NBT ≤30 kW | Typically no fee; upgrades may cost extra |
| $145 | NEM2 aggregation / programs ≤1 MW | Per PG&E NEM page |
| ~$1,047 | Optional Green Meter Adapter (GMA) | Special Facilities Agreement estimate, may change |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Standard NEM/NBT | 30 kW | Solar/wind ≤30 kW; storage ≤10 kW |
| Complex NEM (Rule 21 / EGI rep) | 1000 kW | Solar >30 kW or storage >10 kW; handled via Rule21Gen@pge.com and assigned EGI representative |
| Net metering cap | 1000 kW |
Systems must be sized to load; no incentive for oversizing. Certain SF/Oakland secondary network ZIPs need Rule21Gen review.
Storage, EV and stamps
Battery storage
Storage ≤10 kW can use the Standard (simplified) application with PV ≤30 kW; storage >10 kW routes to Complex NEM/Rule 21 review.
EV chargers
Checklist asks for number of EVs charging on site and anticipated future annual usage increase.
Common issues the utility lists
- A&A not signed before Step 2
- Missing contractor/customer email addresses
- Equipment not on CEC list without spec sheet/UL1741 documentation
- Portal SLD not matching actual system without custom SLD
- Service address on bill not matching final building permit
- Variance needed but not requested
Gridpol’s pre-submission check covers these before we file.
Sources
- PG&E Net Energy Metering program: https://www.pge.com/en/about/doing-business-with-pge/interconnections/net-energy-metering-program.html (retrieved 2026-11-13)
- PG&E Interconnection Checklist - Standard NEM Application for YourProjects Portal: https://www.pge.com/assets/pge/docs/about/doing-business-with-pge/interconnection-checklist.pdf (retrieved 2026-11-13)
- PG&E Form 79-1151B-03: https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_FORMS_79-1151B-03.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.