Municipal utilityLADWP interconnection application
LADWP is a municipal utility serving 1,415,602 residential customers in California (EIA-861, 2025). Applications: Own online portal (LADWP NEM Portal (online interconnection application; issues Work Request number WR#)). Gridpol files LADWP interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from LADWP’s official sources (see below). Portal, documents and steps confirmed from LADWP pages/PDFs (2024-2025). Open: fee amounts (Expenditure Recovery Charge) not published; AIA PDF and Type page disagree on Type 1/3/4 size bounds; NEM portal page itself not fetchable (redirects to login). No PE-stamp rule found.
LADWP at a glance
Los Angeles Department of Water & Power (City of Los Angeles)
TypeMunicipal utility
EIA utility ID11208
Residential customers1,415,602 (EIA-861, 2025)
Net-metered residential customers95,898 (EIA-861, 2025)
Service territory2 counties in California
How to applyOwn online portal – LADWP NEM Portal (online interconnection application; issues Work Request number WR#) · official link
Who submitsCustomer or contractor may complete the NEM portal application and upload documents (LADWP Electric Service Guide). LADWP customer of record signs the Interconnection Agreement; if a tenant is the customer, the property owner must also sign. Leased systems: lessor and lessee file the NEM Solar Lease Compliance Form (SLCF). Owens Valley projects and verifiable portal errors use the Assisted Interconnection Application (AIA) by email to SolarCoordinator@ladwp.com.
Export compensationNEM – LADWP Net Energy Metering (NEM Guidelines / NEM Service Rider)
Excess energy credited to bill balance; credit zeroed at service termination. Systems >1 MW on CG rates.
LADWP Electric Service Guide (3/2024) typical timelines: Fast Track 2-5 days (IA approval) + 1-2 weeks (meter/energize); <30 kW 1-3 weeks + 2-5 days + 1-2 weeks + 1-2 weeks; >=30 kW 6-8 weeks (engineering) then 1-2 week phases. AIA: WR# must be sent within 7 business days of approval email.
Documents LADWP asks for
- Interconnection application formOnline NEM portal application (www.ladwp.com/NEM) -> confirmation email with WR#; AIA cases: AIA Submission Information Form + shell application Gridpol prepares this.
- Photos (meter, main panel, equipment)Photos of service panel/existing electric service and installation area (Types 1-3)
- Interconnection agreement (when applicable)>10 to <=30 kW-AC: Short-Form/Small System IA (solar and/or ESS); >30 kW and all non-solar: Standard Offer Interconnection Agreement (SOIA)
- Single-line diagram (one-line) (when applicable)Type 2+ (>10 kW, panel upgrade, three-phase, multi-meter, battery): single-line diagram with system size and inverter specs Gridpol prepares this.
- Site plan / site layout (when applicable)Plot/site plan for Type 2+ Gridpol prepares this.
- Battery spec sheet (when applicable)BESS Technical Data Sheet if storage
- Load calculation (when applicable)Load Schedule if required (Types 1-2); required for Types 3-4 (>30 kW)
- Other utility-specific document (when applicable)Service Planning Information Form (Type 2+); Preliminary Review Approval (Type 4 if required); Solar Lease Compliance Form for leased systems; portal error screenshot for AIA
- Final inspection sign-offLADBS permit and final inspection approval; ESR verification for Type 2+
How the LADWP process runs
- Submit online application with documents and photos at www.ladwp.com/NEM; apply for LADBS permit (Owens Valley/portal error: email AIA package to SolarCoordinator@ladwp.com, wait for approval, submit shell application with proxy address, send WR# within 7 business days)
- Receive confirmation email with Interconnection/NEM Work Request number (WR#); pay Expenditure Recovery Charge(s)
- LADWP review: ESR preliminary review/site visit and location drawing, engineer review (Type 2+), Interconnection Agreement approval ('OK to build')
- Install system; LADBS final inspection; ESR final verification (Type 2+)
- LADWP construction/testing as needed; crew installs net (and performance) meter
- LADWP NEM Permission to Operate (PTO) notice by email; system must stay off/locked until then
Fees
| Fee | Applies to | Note |
|---|---|---|
| All types | Expenditure Recovery Charge(s) payable after WR# issued; amount not stated on official page |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Fast Track Solar Process | 10 kW | <10 kW CEC-AC, no panel upgrade, no battery backup, no additional generation |
| Type 1 | 30 kW | PV (NEM) and/or BESS up to 30 kW aggregate; no panel upgrade, no three-phase, no multi-meter (AIA instructions describe Type 1 as up to 10 kW single-phase) |
| Type 2 | 30 kW | Up to 30 kW single-phase or up to 10 kW three-phase; includes panel upgrades, small multi-meter |
| Type 3 | 1000 kW | >30 kW to <1 MW (AIA instructions: >30 to 100 kW); tract projects 5+ homes, three-phase >10 kW, large multi-meter |
| Type 4 | >1 MW (AIA instructions: >100 kW to 1 MW); size = total on-site generation incl. non-solar inverter nameplate | |
| Net metering cap | 1000 kW |
PV rated kW AC-CEC, BESS kW AC. Single-phase aggregate generation limited to 20 kW (inverter max output); larger must be balanced three-phase (feasibility study possible up to 40 kW at customer expense). NEM limited to <=1 MW.
Storage, EV and stamps
Battery storage
BESS covered by Types 1-4, sized by kW AC. Battery backup excludes Fast Track. Short-Form IA covers solar and/or ESS >10 to <=30 kW-AC. BESS Technical Data Sheet required. Grid-interconnected ESS reviewed/inspected by LADWP Distribution Engineer and Electric Service Representative (ESR).
EV chargers
Level II: notify LADWP (866) 484-0433 / pluginla@ladwp.com to schedule preliminary home inspection, LADBS express permit, LADBS + LADWP final inspection, TOU meter if needed; contact ESR at least two weeks before installing. Level III (480 V) handled as commercial service by Service Planning Engineer.
Common issues the utility lists
- AIA submittals not following all steps (one email per address, required subject line, error screenshot) are delayed or cancelled
- AIA request cancelled if WR# not provided within 7 business days of approval
- Non-compliance with LADWP Electric Service Requirements, local ordinances or electrical codes fails LADWP solar inspection
Gridpol’s pre-submission check covers these before we file.
Sources
- LADWP - Type 1, 2, and 3 Interconnection: https://www.ladwp.com/commercial-services/programs-and-rebates-commercial/commercial-solar-programs/type-1-2-and-3-interconnection (retrieved 2026-11-13)
- LADWP - How to Submit an Assisted Interconnection Application (AIA) Request (rev. 01/21/2025): https://www.ladwp.com/sites/default/files/2025-05/Assisted%20Interconnection%20Application%20(AIA)%20Customer%20Instructions%20for%20LADWP%20NEM%20Program.pdf (retrieved 2026-11-13)
- LADWP Consumer's Guide to Having Electric Service Installed or Revised (3/12/2024) - Solar Interconnection, EV Chargers: https://www.ladwp.com/sites/default/files/2024-03/Guide%20to%20Electric%20Service%203.12.24.pdf (retrieved 2026-11-13)
- LADWP Net Energy Metering Guidelines (mod. 4/28/2021): https://www.ladwp.com/sites/default/files/2023-09/NEM%20Guidelines%20%28with%20April%202021%20technical%20modification%29%20%281%29.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.