Home › Utilities › Arkansas › Entergy Arkansas

Investor-owned utility

Entergy Arkansas interconnection application

Entergy Arkansas is an investor-owned utility serving 612,255 residential customers in Arkansas, Missouri, Tennessee (EIA-861, 2025). Applications: PDF + email (Preliminary Interconnection Site Review Request + Standard Interconnection Agreement for Net-Metering Facilities (PDF forms; email NetMetering-Arkansas@entergy.com or mail Customer Service Net-Metering, P.O. Box 551, Little Rock, AR 72203)). Gridpol files Entergy Arkansas interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Entergy Arkansas’s official sources (see below). Portal (PDF + email to NetMetering-Arkansas@entergy.com), documents, fees and steps confirmed from Entergy Arkansas page and tariff/forms. Minor gaps: no installer LOA form published (installer submission by email unconfirmed); MO/TN service-area rules not researched; no online portal found for Arkansas (Entergy portal exists for other Entergy states).

Entergy Arkansas at a glance

Utility

Entergy Arkansas LLC (Entergy Corporation)

Type

Investor-owned utility

EIA utility ID

814

Residential customers

612,255 (EIA-861, 2025)

Net-metered residential customers

7,950 (EIA-861, 2025)

Service territory

65 counties in Arkansas, 5 counties in Missouri, 1 county in Tennessee

How to apply

PDF + email – Preliminary Interconnection Site Review Request + Standard Interconnection Agreement for Net-Metering Facilities (PDF forms; email NetMetering-Arkansas@entergy.com or mail Customer Service Net-Metering, P.O. Box 551, Little Rock, AR 72203) · official link

Who submits

Net-metering customer (and facility owner if different, e.g. leased/service agreement) signs the request and agreement; the agreement lists the installer ('Installed by', qualifications) but no installer submission or LOA/designated-agent form is published.

Export compensation

Net billing – Non-Legacy Net-Metering Service (Rate Schedule No. 71, NLN-M); Legacy Net-Metering (LN-M) for grandfathered customers
Customers interconnecting after Sept 30, 2024 take NLN-M (Act 278 of 2023): exports credited in dollars at Avoided Cost (MISO LMP load-zone average), $0.0334/kWh for March 2026-Feb 2027 ($0.0247 Mar 2025-Feb 2026); redetermined each Feb 1. Legacy: monthly kWh netting with carry-forward.

Review time (official)

Preliminary interconnection site review: written results within 30 calendar days (Preliminary Interconnection Site Review Request terms, per APSC Net-Metering Rules). Signed Standard Interconnection Agreement due at least 30 days before interconnection.

Documents Entergy Arkansas asks for

  • Interconnection application formPreliminary Interconnection Site Review Request (eff. 12/31/2023): customer/owner info, prior 12-month kWh, DC generator + AC inverter rating, expected annual kWh (PVWatts etc.), customer-site load, single/three phase; Sections 1-5 must be complete Gridpol prepares this.
  • Single-line diagram (one-line)Detailed electrical (one-line) diagram incl. protection and control schemes; must show location of utility-approved, labeled manual disconnect Gridpol prepares this.
  • Customer signatureNet-metering customer signature, plus owner signature if different
  • Inverter spec sheetInverter manufacturer, model, location and power rating entered on Standard Interconnection Agreement
  • Interconnection agreementSigned Standard Interconnection Agreement for Net-Metering Facilities at least 30 days before interconnection, plus signed Disclaimer (future rule/rate changes)
  • Final inspection sign-offAgreement Section 5: inspector signature or copy of final (city/county) inspection certificate
  • Other utility-specific document (when applicable)Common Ownership and Meter Aggregation affidavit (if aggregating Additional Meters); Lease and Service Agreement affidavit (leased / third-party service agreement)

How the Entergy Arkansas process runs

  1. Submit Preliminary Interconnection Site Review Request with one-line diagram (email NetMetering-Arkansas@entergy.com or mail); Entergy replies in writing within 30 calendar days.
  2. Pay actual cost of site review and any required technical/engineering studies.
  3. Obtain permits; install system with utility-approved, labeled, lockable manual disconnect accessible to utility, meeting Entergy DER Standards, NEC/NESC/IEEE/UL.
  4. Local inspection; inspector signs agreement Section 5 or attach final inspection certificate.
  5. Submit signed Standard Interconnection Agreement + Disclaimer (+ affidavits) at least 30 days before interconnection; pay one-time administrative fee.
  6. Entergy approves interconnection and verifies metering (agreement Section 6), installs two-way meter; parallel operation begins.

Fees

FeeApplies toNote
$196.75Per Generation Meter < 300 kW (Non-Legacy NLN-M)One-time administrative/interconnection review fee, assessed when Standard Interconnection Agreement is submitted
$667.60Per Generation Meter >= 300 kW (Non-Legacy NLN-M)
$31.50Per Additional Meter (aggregation)
actual costPreliminary site review, site screening, interconnection studies and interconnection facilitiesTwo-way meter at no charge; customer pays non-standard meter cost

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Residential net metering25 kWLesser of 25 kW or highest residential usage in prior 12 months
Non-residential net metering5000 kWLesser of 5 MW or highest usage in prior 12 months
Net metering cap25 kW

Fee break at 300 kW per generation meter; DER Standards cover facilities up to 20 MVA. Facility may not be sized/modified to exceed customer requirements.

Storage, EV and stamps

Battery storage

Application and agreement list 'Energy Storage Device' as a system type (same net-metering process). Entergy DER Standards (2024): battery storage uses inverter technology with smart-inverter functions per UL 1741-SA and IEEE 1547 (latest); non-export function protection listed where applicable. Net-metering page itself does not address batteries.

Common issues the utility lists

  • Preliminary request incomplete (Part 1 Sections 1-5 must be completed for notification to be valid)
  • Items violating safety standards and/or power generation limits are explained with required modifications (per request terms)

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited