PGE (Portland General Electric) interconnection application

PGE (Portland General Electric) is an investor-owned utility serving 840,457 residential customers in Oregon (EIA-861, 2025). Applications: PowerClerk (PGE PowerClerk). Gridpol files PGE (Portland General Electric) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from PGE (Portland General Electric)’s official sources (see below). Storage interconnection rules and OAR 860-039 tier timelines not retrieved; verify on first project.

PGE (Portland General Electric) at a glance

Utility

Portland General Electric Co (Portland General Electric)

Type

Investor-owned utility

EIA utility ID

15248

Residential customers

840,457 (EIA-861, 2025)

Net-metered residential customers

33,867 (EIA-861, 2025)

Service territory

7 counties in Oregon

How to apply

PowerClerk – PGE PowerClerk · official link

Who submits

Customer or contractor submits the completed net metering application through PowerClerk. PPA/TPO (third-party owned/leased) systems may apply for net metering.

Export compensation

NEM – Schedule 203 Net Metering Service
Billed on net; monthly excess credits carried forward; annual true-up with first bill due in March, unused credits transferred to low-income assistance fund.

Review time (official)

Receipt confirmation email within 3 business days of PowerClerk submission (PGE Net Metering FAQ). Other timelines per OAR 860-039 (not retrieved).

Documents PGE (Portland General Electric) asks for

  • Interconnection application formNet Metering application in PowerClerk; must meet OAR 860-039; processed only if all fields accurate, fees paid and documentation provided Gridpol prepares this.
  • Single-line diagram (one-line)One-line diagram Gridpol prepares this.
  • Site plan / site layoutProperty lines, equipment/switchgear location, distances, panel layout, proposed point of interconnection Gridpol prepares this.
  • Interconnection agreementSigned agreement after approval
  • Final inspection sign-offApproved municipal or county electrical permit
  • Other utility-specific document (when applicable)Small Generator Certificate of Completion form (Form 6); as-built specifications form (Form 7); drawing package for single-phase services >320 A or three-phase >200 A, confirmed by PGE Meter Engineering

How the PGE (Portland General Electric) process runs

  1. Contact PGE / check Net Metering map; submit application via PowerClerk (customer or contractor)
  2. Receipt confirmation within 3 business days
  3. Technical review; upgrades at customer expense if needed
  4. Approval (wait before building)
  5. Obtain approved municipal/county electrical permit and signed agreement
  6. PGE requests bidirectional meter on customer's behalf; meter install and interconnection

Fees

FeeApplies toNote
$0Residential net metering <= 25 kWIf study needed, Tier 4 application: $100 + $2/kW; studies billed $100/hour
$50 + $1/kWCommercial/industrial 25 kW - 2 MW

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Residential net metering (no fee)25 kW
Commercial net metering2000 kW
Net metering cap2000 kW

Oregon tiered review under OAR 860-039; limited feeders shown on PGE Net Metering map may require design changes.

Common issues the utility lists

  • Applications not processed unless all fields accurate, all fees paid and all supporting documentation provided

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.