Municipal utilityCity of Sharon interconnection application
City of Sharon is a municipal utility serving 83 customers in North Dakota (EIA-861, 2025). Gridpol files City of Sharon interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
North Dakota’s commission rule (N.D. Admin. Code ch. 69-09-07 (Small Power Production and Cogeneration, PURPA implementation), esp. 69-09-07-11 Interconnection costs) does not bind municipal utilitys; City of Sharon sets its own interconnection policy. We confirm its form on the first project. Rural electric cooperatives and municipal utilities are not covered by the PSC net billing rule or any state interconnection standard; they follow their own policies and federal PURPA obligations.
City of Sharon at a glance
City of Sharon
TypeMunicipal utility
EIA utility ID17045
Customers83 (EIA-861, 2025, short form: all customer classes)
Net-metered residential customersnone reported
Service territory1 county in North Dakota
Documents City of Sharon asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for City of Sharon. We confirm City of Sharon’s exact list on the first project.
North Dakota interconnection rule
North Dakota Public Service Commission (PSC)
Interconnection ruleN.D. Admin. Code ch. 69-09-07 (Small Power Production and Cogeneration, PURPA implementation), esp. 69-09-07-11 Interconnection costs – Small Power Production and Cogeneration · source
Applies toSales/purchases between PURPA qualifying facilities and 'electric public utilities' under PSC jurisdiction (NDCC 49-03-01.5) - investor-owned utilities (Xcel/NSP, MDU, Otter Tail). Rural electric cooperatives and munis are not PSC rate-regulated.
Application formNo statewide interconnection application/standard in the Administrative Code; utility-specific tariffs and forms.
FeesQF pays interconnection costs the commission may assess on a nondiscriminatory basis; reimbursement may be spread over time (69-09-07-11). No fee caps.
Export compensationNEM – N.D. Admin. Code 69-09-07-09(3)(a)
QFs <=100 kW design capacity entitled to net energy billing (meter reverses); utility may recover production-monitoring metering costs. Applies to PSC-regulated IOUs only; Legislative Council committee objection filed 1991 (rule remains). Netting period (monthly/annual) set in utility tariffs.
Rural electric cooperatives and municipal utilities are not covered by the PSC net billing rule or any state interconnection standard; they follow their own policies and federal PURPA obligations.
- N.D. Admin. Code ch. 69-09-07: https://ndlegis.gov/information/acdata/pdf/69-09-07.pdf (retrieved 2026-11-13)
- N.D. Admin. Code Art. 69-09 index: https://ndlegis.gov/information/acdata/html/69-09.html (retrieved 2026-11-13)
Other utilities in North Dakota
- Xcel Energy (Minnesota)83,434
- Montana-Dakota Utilities79,711
- Cass County Electric Cooperative Inc.52,785
- Otter Tail Power45,437
- Nodak Electric Cooperative Inc.20,715
- Capital Electric Cooperative, Inc.19,650
- Verendrye Electric Cooperative Inc.14,357
- Mountrail-Williams Electric Cooperative11,485
- Roughrider Electric Cooperativ11,246
- Northern Plains Electric Cooperative10,472
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.