Home › Utilities › New Hampshire › NHEC (New Hampshire Electric Co-op)
Electric cooperativeNHEC (New Hampshire Electric Co-op) interconnection application
NHEC (New Hampshire Electric Co-op) is an electric cooperative serving 74,619 residential customers in New Hampshire (EIA-861, 2025). Applications: Own online portal (NHEC Solar & Battery Interconnection Application (online form via NHEC SmartHub/FormAssembly)). Gridpol files NHEC (New Hampshire Electric Co-op) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from NHEC (New Hampshire Electric Co-op)’s official sources (see below). Portal, documents and steps confirmed from NHEC page, online form and T&C Section X. Gaps: current export credit rate values not taken from Schedule of Rates; NH En 1000 rules (2026) applicability to NHEC not checked.
NHEC (New Hampshire Electric Co-op) at a glance
New Hampshire Elec Coop Inc
TypeElectric cooperative
EIA utility ID13441
Residential customers74,619 (EIA-861, 2025)
Net-metered residential customers2,048 (EIA-861, 2025)
Service territory9 counties in New Hampshire
How to applyOwn online portal – NHEC Solar & Battery Interconnection Application (online form via NHEC SmartHub/FormAssembly) · official link
Who submitsMember or contractor may complete the online application (form asks who is completing it); member is the member-generator, acknowledges T&C Section X and authorizes NHEC to share account info with the installer. Account must be current (no balance 30+ days overdue).
Export compensationNet billing – NHEC Terms & Conditions Section X - Net Metering (individual and group)
Delivered energy billed under Schedule of Rates; exported energy credited at the export rate of the member's class (members with a competitive supplier do not get the Co-op Power portion). Annual review after March billing: dollar credit >=$50 can be carried or paid by check; payout also possible after June/September cycles. Optional net-metering time-of-day rates.
NHEC notifies completeness in writing within 20 business days of receipt (T&C X.2.e). Accepted applications hold a queue number for 12 months; installation must be completed within 12 months of acceptance or the queue number expires. Increasing AC inverter rating loses queue position.
Documents NHEC (New Hampshire Electric Co-op) asks for
- Interconnection application formOnline Interconnection Application (solar, solar+battery, battery only); equipment data incl. NHEC pole number; UL 1741 SA inverters per IEEE 1547-2018 Gridpol prepares this.
- Single-line diagram (one-line)One-line drawing required for all interconnection-facilities and battery/backup installations; show exterior production meter socket, utility-accessible disconnect, 'line to solar - load to utility' Gridpol prepares this.
- Battery spec sheet (when applicable)Battery section: manufacturer/model/qty, kW/kVA, kWh, UL 1741 SA/SB listing, grid charging, off-grid/backup operation, switching
- Interconnection agreementMutual Indemnity Agreement (T&C X / NH PUC 904.03) accepted in the form
- Other utility-specific documentRenewable Energy Certificate Member Agreement - choose option (e.g. keep RECs with monitoring fee, give to NHEC, sell to NHEC)
- Final inspection sign-offAfter install: local building inspector (or NH licensed electrician if none) signs the Interconnection Application for code compliance
- Other utility-specific documentWitness test: load-break test (generator shuts down within 2 s) performed by member/contractor and signed on the application
How the NHEC (New Hampshire Electric Co-op) process runs
- Optional pre-application review; finalize design with installer; read T&C Section X and Schedule of Rates/Fees
- Submit online Solar & Battery Interconnection Application with one-line drawing, REC agreement and indemnity; pay application fee
- NHEC completeness review within 20 business days; queue number assigned; system modifications estimated and prepaid if needed
- NHEC notifies application complete - install (exterior production meter socket at 66 in., utility-accessible disconnect, placards)
- Local building inspector (or NH licensed electrician) signs application; contractor performs load-break witness test and signs
- NHEC inspection; if passed NHEC installs meters and signs application authorizing operation (copy to member)
Fees
| Fee | Applies to | Note |
|---|---|---|
| $220 | Interconnection application up to 25 kW AC | Schedule of Fees eff. Jan 1, 2026 |
| $600 | >25 kW to 100 kW AC | |
| $1,000 | >100 kW AC | |
| $320 | Interconnection site visit | each subsequent trip if facility fails inspection |
| estimated cost | System modifications/upgrades | member pays in advance |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Fee tier <=25 kW AC | 25 kW | |
| Fee tier 25-100 kW AC | 100 kW | |
| Net metering max | 1000 kW | total AC inverter nameplate <=1 MW; separate form option for >1 MW |
| Net metering cap | 1000 kW |
NHEC T&C Section X
Storage, EV and stamps
Battery storage
Storage facilities are included in 'interconnection-facility' under T&C X. Application requires battery details (DC/AC coupling, shared inverter, export or no-export, whether chargeable from grid and how prevented, off-grid/backup operation, disconnect/reconnect switching) and a one-line for battery/backup installations; UL 1741 SA/SB listing asked.
Common issues the utility lists
- Application without one-line diagram will not be accepted
- Incomplete application (NHEC states missing items in writing)
- Production meter not 66 in. above grade or within 10 ft of LP gas regulators/tanks
- Missing/incorrect placards (red background, white lettering) on net and production meters
- No exterior utility-accessible disconnect at production meter
- Wrong wiring: solar must be on line side (top), grid/panel on load side (bottom)
- Load-break test fails (no shutdown within 2 s)
- Increase of AC inverter rating after application (loses queue position)
Gridpol’s pre-submission check covers these before we file.
Sources
- NHEC Solar & Net Metering: https://www.nhec.com/solar-net-metering/ (retrieved 2026-11-13)
- NHEC Solar & Battery Interconnection Application (online form): https://smarthub.tfaforms.net/1513 (retrieved 2026-11-13)
- NHEC Terms & Conditions, Section X Net Metering: https://www.nhec.com/terms-and-conditions/ (retrieved 2026-11-13)
- NHEC Schedule of Fees effective Jan 1, 2026: https://www.nhec.com/wp-content/uploads/2025/10/Schedule_of_Fees_20260101.pdf (retrieved 2026-11-13)
- NHEC Solar Interconnection - Avoid These Common Mistakes: https://www.nhec.com/wp-content/uploads/2025/03/Avoid-These-Common-Mistakes.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.