Investor-owned utilityEntergy Mississippi interconnection application
Entergy Mississippi is an investor-owned utility serving 384,493 residential customers in Mississippi (EIA-861, 2025). Applications: Own online portal (Entergy Interconnection Portal). Gridpol files Entergy Mississippi interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Entergy Mississippi’s official sources (see below). Verified 2026-11-13 from entergymississippi.com/net-metering and the Level 1 Standard Interconnection Agreement PDF (May 2024). Portal-specific upload list: see Entergy Interconnection Portal Manual.
Entergy Mississippi at a glance
Entergy Mississippi LLC (Entergy Corporation)
TypeInvestor-owned utility
EIA utility ID12685
Residential customers384,493 (EIA-861, 2025)
Net-metered residential customers793 (EIA-861, 2025)
Service territory46 counties in Mississippi
How to applyOwn online portal – Entergy Interconnection Portal · official link
Who submitsCustomer signs Standard Interconnection Agreement; installer signs the certification section (form notes the equipment vendor may help fill it out). Submitted via Entergy Interconnection Portal or by mail.
Export compensationNet billing – Net Energy Metering Rate Schedule (MPSC Net Metering and Interconnection Rule, Docket 2011-AD-2)
Excess energy earns kWh account credits carried to next cycle; refund only on disconnection of facility.
Residential: submit agreement ≥30 business days before intended interconnection (commercial ≥45); Entergy uses best efforts to return plan review within 14 days for residential; modifications reviewed within 30 days.
Documents Entergy Mississippi asks for
- Interconnection application formStandard Interconnection Agreement for DER (residential ≤20 kWdc = Level 1 form; Level 2/3 forms for larger non-residential) Gridpol prepares this.
- Single-line diagram (one-line)One-line diagram showing accessible 'visible open' disconnect within 3 ft of meter, or plaque specifying location Gridpol prepares this.
- Inverter spec sheetManufacturer literature for the specific system(s); inverter must be UL 1741 SA and IEEE 1547-2018 certified (a 'No' means denial)
- UL 1741 / IEEE 1547 certificationUL 1741 SA certification incl. anti-islanding
- Customer signatureCustomer signs agreement; installer signs certification
- Battery spec sheet (when applicable)Battery backup: description attached
- Other utility-specific document (when applicable)Proof of site control for new customers; rental-property / low-to-moderate income addendum or affidavit if claiming LMI adder; description of any existing generator
How the Entergy Mississippi process runs
- Submit Standard Interconnection Agreement with one-line diagram and manufacturer literature via Entergy Interconnection Portal (or mail) at least 30 business days (residential) before intended interconnection.
- Entergy reviews plans (residential best efforts 14 days) and lists any required modifications.
- Install per NEC/IEEE 1547 with lockable, accessible manual disconnect; customer provides meter socket.
- Entergy inspects and gives approval to operate; installs bi-directional meter. No parallel operation before approval and meter installation.
- Account added to Net Energy Metering rate schedule; one-time $95/$135 fee billed.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $95 | Net Metering Admin Fee - AMI meter already installed | One-time, non-refundable, billed after operational |
| $135 | Net Metering Admin Fee - no AMI meter | Covers meter, installation, administration |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | |
| Level 2 | 500 kW | Non-residential |
| Level 3 | 2000 kW | Non-residential |
| Net metering cap | 20 kW |
Level 1 may not offset >110% of prior-year annual kWh; Levels 2/3 ≤110% of prior-year peak kW. Panels must be on the facility, behind the meter (no remote/ground-mounted per page). Entergy may refuse applications above 3% of system peak. Single-phase interconnections limited to below 150 kVA.
Storage, EV and stamps
Battery storage
Form asks 'Battery Backup: Yes, description attached'. If unit can run when utility power is unavailable, a transfer switch is required for approval.
Common issues the utility lists
- Inverter not UL 1741 SA or IEEE 1547-2018 certified (form: 'No' results in denial)
- Service from Entergy Downtown Jackson network (all DER interconnections prohibited)
- System sized above 110% of annual usage
Gridpol’s pre-submission check covers these before we file.
Sources
- Entergy Mississippi - Net metering for renewable energy resources: https://www.entergymississippi.com/net-metering/ (retrieved 2026-11-13)
- Entergy Mississippi Standard Interconnection Agreement for DER (Residential ≤20 kWdc): https://www.entergymississippi.com/wp-content/uploads/Interconnection_App_and_Agreement_Level_1.pdf (retrieved 2026-11-13)
- Entergy Interconnection Portal Manual for External Users Rev 2.0: https://www.entergymississippi.com/wp-content/uploads/Entergy-Interconnection-Portal-Manual-for-External-Users-Rev2.0.pdf (retrieved 2026-11-13)
Other utilities in Mississippi
- Mississippi Power158,206
- Coast Electric Power Association84,194
- Singing River Electric Cooperative73,398
- Southern Pine Electric Cooperative65,580
- Pearl River Valley El Power Association52,557
- 4-County Electric Power Association41,491
- Dixie Electric Power Association37,963
- Tombigbee Electric Power Association37,347
- Magnolia Electric Power Association31,161
- Central Electric Power Association31,032
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.