Entergy Mississippi interconnection application

Entergy Mississippi is an investor-owned utility serving 384,493 residential customers in Mississippi (EIA-861, 2025). Applications: Own online portal (Entergy Interconnection Portal). Gridpol files Entergy Mississippi interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Entergy Mississippi’s official sources (see below). Verified 2026-11-13 from entergymississippi.com/net-metering and the Level 1 Standard Interconnection Agreement PDF (May 2024). Portal-specific upload list: see Entergy Interconnection Portal Manual.

Entergy Mississippi at a glance

Utility

Entergy Mississippi LLC (Entergy Corporation)

Type

Investor-owned utility

EIA utility ID

12685

Residential customers

384,493 (EIA-861, 2025)

Net-metered residential customers

793 (EIA-861, 2025)

Service territory

46 counties in Mississippi

How to apply

Own online portal – Entergy Interconnection Portal · official link

Who submits

Customer signs Standard Interconnection Agreement; installer signs the certification section (form notes the equipment vendor may help fill it out). Submitted via Entergy Interconnection Portal or by mail.

Export compensation

Net billing – Net Energy Metering Rate Schedule (MPSC Net Metering and Interconnection Rule, Docket 2011-AD-2)
Excess energy earns kWh account credits carried to next cycle; refund only on disconnection of facility.

Review time (official)

Residential: submit agreement ≥30 business days before intended interconnection (commercial ≥45); Entergy uses best efforts to return plan review within 14 days for residential; modifications reviewed within 30 days.

Documents Entergy Mississippi asks for

  • Interconnection application formStandard Interconnection Agreement for DER (residential ≤20 kWdc = Level 1 form; Level 2/3 forms for larger non-residential) Gridpol prepares this.
  • Single-line diagram (one-line)One-line diagram showing accessible 'visible open' disconnect within 3 ft of meter, or plaque specifying location Gridpol prepares this.
  • Inverter spec sheetManufacturer literature for the specific system(s); inverter must be UL 1741 SA and IEEE 1547-2018 certified (a 'No' means denial)
  • UL 1741 / IEEE 1547 certificationUL 1741 SA certification incl. anti-islanding
  • Customer signatureCustomer signs agreement; installer signs certification
  • Battery spec sheet (when applicable)Battery backup: description attached
  • Other utility-specific document (when applicable)Proof of site control for new customers; rental-property / low-to-moderate income addendum or affidavit if claiming LMI adder; description of any existing generator

How the Entergy Mississippi process runs

  1. Submit Standard Interconnection Agreement with one-line diagram and manufacturer literature via Entergy Interconnection Portal (or mail) at least 30 business days (residential) before intended interconnection.
  2. Entergy reviews plans (residential best efforts 14 days) and lists any required modifications.
  3. Install per NEC/IEEE 1547 with lockable, accessible manual disconnect; customer provides meter socket.
  4. Entergy inspects and gives approval to operate; installs bi-directional meter. No parallel operation before approval and meter installation.
  5. Account added to Net Energy Metering rate schedule; one-time $95/$135 fee billed.

Fees

FeeApplies toNote
$95Net Metering Admin Fee - AMI meter already installedOne-time, non-refundable, billed after operational
$135Net Metering Admin Fee - no AMI meterCovers meter, installation, administration

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 120 kW
Level 2500 kWNon-residential
Level 32000 kWNon-residential
Net metering cap20 kW

Level 1 may not offset >110% of prior-year annual kWh; Levels 2/3 ≤110% of prior-year peak kW. Panels must be on the facility, behind the meter (no remote/ground-mounted per page). Entergy may refuse applications above 3% of system peak. Single-phase interconnections limited to below 150 kVA.

Storage, EV and stamps

Battery storage

Form asks 'Battery Backup: Yes, description attached'. If unit can run when utility power is unavailable, a transfer switch is required for approval.

Common issues the utility lists

  • Inverter not UL 1741 SA or IEEE 1547-2018 certified (form: 'No' results in denial)
  • Service from Entergy Downtown Jackson network (all DER interconnections prohibited)
  • System sized above 110% of annual usage

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.