Home › Utilities › Kansas › Sedgwick County El Cooperative Association Inc.

Electric cooperative

Sedgwick County El Cooperative Association Inc. interconnection application

Sedgwick County El Cooperative Association Inc. is an electric cooperative serving 8,530 customers in Kansas (EIA-861, 2025). Gridpol files Sedgwick County El Cooperative Association Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Kansas’s interconnection rule (K.S.A. 66-1,184 (parallel generation, as amended L. 2025 ch. 66 §4) and K.S.A. 66-1263 et seq. (Net Metering and Easy Connection Act, amended 2024 HB 2527); KCC-approved utility interconnection tariffs (standard interconnection process)) applies to Sedgwick County El Cooperative Association Inc.. Levels, timelines and documents below come from that rule; Sedgwick County El Cooperative Association Inc.’s own form and portal are confirmed on the first project.

Sedgwick County El Cooperative Association Inc. at a glance

Utility

Sedgwick County El Coop Assn Inc

Type

Electric cooperative

EIA utility ID

16920

Customers

8,530 (EIA-861, 2025, short form: all customer classes)

Net-metered residential customers

none reported

Service territory

5 counties in Kansas

Documents Sedgwick County El Cooperative Association Inc. asks for

  • Interconnection application formRequired by the state rule Gridpol prepares this.
  • Final inspection sign-offRequired by the state rule
  • Interconnection agreementRequired by the state rule
  • Other utility-specific documentRequired by the state rule

Documents required by the Kansas rule. Sedgwick County El Cooperative Association Inc. may ask for more on its own form; we confirm on the first project.

Kansas interconnection rule

Commission

Kansas Corporation Commission (KCC)

Interconnection rule

K.S.A. 66-1,184 (parallel generation, as amended L. 2025 ch. 66 §4) and K.S.A. 66-1263 et seq. (Net Metering and Easy Connection Act, amended 2024 HB 2527); KCC-approved utility interconnection tariffs (standard interconnection process) – Parallel generation service / Net Metering and Easy Connection Act · source

Applies to

K.S.A. 66-1,184 binds every utility providing retail electric service in Kansas: IOUs, electric cooperatives (incl. coop-owned utilities) and municipal utilities. NMECA (net metering) binds investor-owned utilities only (Evergy, Empire/Liberty). KCC-regulated utilities follow their KCC-approved rules with a standard interconnection process or FERC procedures; non-KCC-regulated utilities follow FERC procedures (66-1,184(k)).

Application form

Utility-specific application under KCC-approved tariff (no statewide form found); utility may require application and verification of standards/codes (66-1,184(c)).

Timelines

Acknowledge receipt in writing within 30 days; approve or deny within 90 calendar days (not applicable if studies needed - estimate given); denial must state reasons and corrective actions (66-1,184(c)).

Fees

Utility may charge a nonrefundable application fee, study costs (incl. SPP studies) and upgrade/equipment costs; no other fees unless authorized; no charge for exported power (66-1,184(c),(l)). NMECA: for pre-2014 net-metering customers no added interconnection fee (66-1265(d)).

External disconnect

Utility may install a disconnecting device near the meter or require a utility-accessible switch or breaker (66-1,184(f)(5)). NMECA requires a UL-listed anti-islanding mechanism (66-1264(b)(5)).

Export compensation

NEM – K.S.A. 66-1263 to 66-1271 (Net Metering and Easy Connection Act) as amended by 2024 HB 2527
IOUs only. Post-2014-07-01 systems: residential 15 kW, commercial/ag/government 100 kW, schools 150 kW AC export; monthly net excess credited at >=100% of monthly system average cost of energy; aggregate 2% (2024) rising to 5% of peak (2027); from 2026-01-01 generating capacity may exceed export capacity by max 50%. Pre-2014 systems: 25/200 kW with kWh carry-forward until 2030. Customers of IOUs may alternatively choose 66-1,184 parallel generation (avoided cost).

Not bound by the rule

Coops and munis are bound by K.S.A. 66-1,184 parallel generation (export compensation >=100% avoided cost or LMP/system average cost option, 30/90-day timelines, sizing factor 0.288); non-KCC-regulated utilities follow FERC interconnection procedures. Not required to offer NMECA net metering.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.