Home › Utilities › Iowa › Amana Society Service Company
Investor-owned utilityAmana Society Service Company interconnection application
Amana Society Service Company is an investor-owned utility serving 709 residential customers in Iowa (EIA-861, 2025). Gridpol files Amana Society Service Company interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Partly researched from official sources. verify on first project: no Amana Society Service Co interconnection page found online; confirm forms, fee, net metering tariff with utility.
Amana Society Service Company at a glance
Amana Society Service Co
TypeInvestor-owned utility
EIA utility ID471
Residential customers709 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory1 county in Iowa
Who submitsIowa rules: applicants use Iowa Utilities Commission-approved standard interconnection request forms and agreements; utility-specific channel not found online.
Review time (official)Per 199 IAC 45.
Documents Amana Society Service Company asks for
- Interconnection application formIUC standard Level 1 (≤20 kVA) or Level 2-4 interconnection request Gridpol prepares this.
- Single-line diagram (one-line)One-line diagram (Iowa standard form) Gridpol prepares this.
- Site plan / site layoutPlot plan Gridpol prepares this.
- Inverter spec sheetManufacturer specs + NRTL label info
- Proof of insuranceProof of homeowner's/general liability insurance
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
How the Amana Society Service Company process runs
- Obtain IUC standard form
- Submit to utility with fee and attachments
- Review per 199 IAC 45
- Interconnection agreement
- Install, inspection, witness test
- Certificate of Completion / operate
Fees
| Fee | Applies to | Note |
|---|---|---|
| $125 | Level 1 (Iowa standard form) | witness test up to $125 (199 IAC 45.5(10)); confirm utility applies it |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | kVA, 199 IAC 45 |
| Level 2-4 | 10000 kW |
Sources
- Iowa Utilities Commission – On-site distributed generation: https://iuc.iowa.gov/regulated-industries/electric/site-distributed-generation (retrieved 2026-11-13)
- Iowa standard Level 1 Interconnection Request (IUC form, as hosted by MidAmerican): https://www.midamericanenergy.com/media/pdf/iowa-level1-interconnectionrequest.pdf (retrieved 2026-11-13)
Iowa interconnection rule
Iowa Utilities Commission (IUC, formerly Iowa Utilities Board)
Interconnection rule199 IAC Chapter 45 (199-45.1 to 45.13) – Electric Interconnection of Distributed Generation Facilities · source
Applies toElectric utilities subject to IUC rate regulation (MidAmerican Energy, Interstate Power & Light/Alliant) for DG not subject to FERC/MISO/SPP/affected-system interconnection requirements (199-45.1 'Utility', 45.2). >10 MVA starts at Level 4.
Application formCommission-approved statewide interconnection request forms and agreements posted on iuc.iowa.gov (Level 1 Interconnection Request Application form and Distributed Generation Interconnection Agreement incl. Conditional Agreement; Level 2/3/4 forms; Certificate of Completion) (199-45.4(1)); electronic submission if agreed.
TimelinesLevel 1: completeness 7 BD, screens 15 BD; approval conditioned on local electrical code approval, Certificate of Completion, witness test (completed or waived), signed Conditional Agreement within 30 BD (+15 BD extension). Level 2: completeness 10 BD, screens 20 BD. Witness test needs 15 BD notice. Preapplication report $300.
FeesCaps (199-45.4(3)): L1 $125 (+$125 witness test); L2 $250 + $1/kVA (+$125); L3 $500 + $2/kVA; L4 $1,000 + $2/kVA. Preapplication report $300.
InsuranceChapter 45 text contains no insurance requirement (terms may be in commission-approved forms; not checked).
External disconnectRequired for DG placed in service after 2015-07-01: customer-owned disconnection device easily visible and adjacent to meter (within 10 ft home/business, 30 ft multi-building; 30-72 in height), labeled; permanent placard within 10 ft of meter (199-45.3(2)).
Export compensationNet billing – Iowa Code §476.49; utility tariffs
Rate-regulated utilities file either net billing (monthly kWh credit, annual cash-out at avoided cost split with LIHEAP) or inflow-outflow billing (hourly/subhourly, credited at retail volumetric rate for 20 years until value-of-solar). Facility <=1 MW AC and <=110% of annual usage. Value-of-solar proceeding after 2027-07-01 petition or 5% statewide DG penetration.
Municipal utilities and non-rate-regulated electric cooperatives are outside 199 IAC 45 and §476.49 definitions (rate-regulated utilities only); they adopt their own interconnection and net metering/buyback policies.
- 199 IAC ch. 45: https://www.legis.iowa.gov/docs/iac/chapter/199.45.pdf (retrieved 2026-11-13)
- Iowa Code §476.49: https://www.legis.iowa.gov/docs/code/476.49.pdf (retrieved 2026-11-13)
Other utilities in Iowa
- MidAmerican Energy639,558
- Alliant Energy (Iowa)419,451
- Corridor Energy Cooperative30,992
- City of Ames25,123
- Eastern Iowa Light & Power Cooperative20,472
- Cedar Falls Utilities17,746
- Midland Power Cooperative12,083
- Maquoketa Valley Rrl Electric Cooperative11,161
- Board of Water Electric & Communications10,105
- Iowa Lakes Electric Cooperative9,757
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO