Home › Utilities › Hawaii › Hawaiian Electric (Oahu)

Investor-owned utility

Hawaiian Electric (Oahu) interconnection application

Hawaiian Electric (Oahu) is an investor-owned utility serving 276,853 residential customers in Hawaii (EIA-861, 2025). Applications: Own online portal (Customer Interconnection Tool (CIT, GridUnity)). Gridpol files Hawaiian Electric (Oahu) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Hawaiian Electric (Oahu)’s official sources (see below). Fees and official review timelines not found; export credit values in program flyers/tariff Rule 14H not retrieved.

Hawaiian Electric (Oahu) at a glance

Utility

Hawaiian Electric Co Inc (Hawaiian Electric Industries)

Type

Investor-owned utility

EIA utility ID

19547

Residential customers

276,853 (EIA-861, 2025)

Net-metered residential customers

68,048 (EIA-861, 2025)

Service territory

1 county in Hawaii

How to apply

Own online portal – Customer Interconnection Tool (CIT, GridUnity) · official link

Who submits

Contractor (registered CIT account) applies online; customer signs Customer Authorization & Acknowledgement form; agreement e-signed by property owner and system owner via DocuSign.

Export compensation

Net billing – Smart Renewable Energy (SRE) Export / Non-Export; NEM Plus for existing NEM customers
Export rates locked 7 years for new interconnection; advanced meter required. CGS Plus/Smart Export/CSS closed 29 Mar 2024.

Documents Hawaiian Electric (Oahu) asks for

  • Interconnection application formCIT application with project system components (each battery inverter + storage listed) Gridpol prepares this.
  • Letter of authorization / designated agent formCustomer Authorization & Acknowledgement form (latest version, all pages)
  • Single-line diagram (one-line)Must show AC disconnect(s) covering entire facility incl. storage; service address, customer name/contact, revenue meter no., contractor info Gridpol prepares this.
  • Site plan / site layoutSame identifying info as SLD Gridpol prepares this.
  • Other utility-specific document (when applicable)Program application form (SRE Export/Non-Export ± BYOD Plus); DER Amendment form for equipment changes; property deed/trust documents/BREG authority if ownership records out of date
  • Load calculation (when applicable)Max/min site loads without generation for systems ≥30 kW
  • Photos (meter, main panel, equipment)Validation packet photos after installation
  • Interconnection agreementGenerated by CIT, DocuSign after inspection

How the Hawaiian Electric (Oahu) process runs

  1. Contractor creates and submits application in CIT
  2. Completeness review and technical/utility reviews -> conditional approval
  3. Install; submit revision if anything differs from application
  4. Submit Project Validation packet (post-installation info, photos)
  5. Validation review; utility inspection
  6. Agreement execution via DocuSign
  7. Meter change; PTO email from CIT

Size levels and limits

LevelUp toNote
≥30 kWAdditional site load data required

SRE Export and Non-Export: no project size limit per program page.

Storage, EV and stamps

Battery storage

Battery projects: list each battery inverter with its storage; AC disconnect on energy storage required (Rule 14H). BYOD Plus pays for scheduled battery dispatch (apply as BYOD Level 1 in CIT until updated).

Common issues the utility lists

  • Components (make/model/qty) inconsistent with SLD
  • Obsolete Customer Authorization form version / mixed pages
  • SLD missing AC disconnect covering storage
  • Wrong TMK format (Oahu: 1 + 12-digit TMK)
  • SLD/site plan missing address, customer, meter no., contractor info
  • Ownership records (trust/company/out-of-date) without supporting documents
  • Design not matching selected program type
  • Unaddressed flagged comments at Completeness Review

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited