Farmington River Power Company is an investor-owned utility serving 0 customers in Connecticut (EIA-861, 2025). Gridpol files Farmington River Power Company interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Connecticut’s interconnection rule (PURA-approved EDC Guidelines: Docket 17-12-03 RE06 'Guidelines for Generator Interconnection - Fast Track and Study Processes' (Eversource/UI, 2023-12-20) and Docket 03-01-15 RE04 'Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities' (<=25/50 kW)) applies to Farmington River Power Company. Levels, timelines and documents below come from that rule; Farmington River Power Company’s own form and portal are confirmed on the first project.
Farmington River Power Company at a glance
Farmington River Power Company
TypeInvestor-owned utility
EIA utility ID6207
Customers0 (EIA-861, 2025, short form: all customer classes)
Net-metered residential customersnone reported
Service territory1 county in Connecticut
Documents Farmington River Power Company asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Single-line diagram (one-line)Required by the state rule Gridpol prepares this.
- Site plan / site layoutRequired by the state rule Gridpol prepares this.
- Inverter spec sheetRequired by the state rule
- PV module spec sheetRequired by the state rule
- UL 1741 / IEEE 1547 certificationRequired by the state rule
- Proof of insuranceRequired by the state rule
- Interconnection agreementRequired by the state rule
Documents required by the Connecticut rule. Farmington River Power Company may ask for more on its own form; we confirm on the first project.
Connecticut interconnection rule
Connecticut Public Utilities Regulatory Authority (PURA)
Interconnection rulePURA-approved EDC Guidelines: Docket 17-12-03 RE06 'Guidelines for Generator Interconnection - Fast Track and Study Processes' (Eversource/UI, 2023-12-20) and Docket 03-01-15 RE04 'Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities' (<=25/50 kW) – Guidelines for Generator Interconnection · source
Applies toThe two electric distribution companies: Eversource (CL&P) and United Illuminating; not municipal utilities (CMEEC members)
Application formJoint EDC interconnection request submitted through each EDC's online portal (Eversource PowerClerk); separate simplified residential inverter guideline application
TimelinesFast Track/Study guideline: receipt confirmation 3 business days, completeness notice 10 business days, applicant 15 business days to cure; generator signs agreement within 30 business days; EDC witness test within 10 business days of request.
Fees$200 inverter-based <=25 kW; $500 Fast Track; $1,000 Study + actual study costs (Table 1 of guideline; Eversource CT page).
InsuranceGeneral liability per guideline Table 2: <100 kW $300,000; >100 kW-1 MW $1,000,000; >1-5 MW $2,000,000; >5 MW $5,000,000; Eversource page lists N/A for inverter-based 0-25 kW but asks proof of insurance in residential application.
External disconnectEversource CT: isolation device (AC disconnect) must be visible and within 10 feet of main utility panel/meter; variance needs written approval.
Export compensationNet billing – CGS 16-244z (Residential and Non-Residential Renewable Energy Solutions programs); legacy net metering CGS 16-243h
Traditional net metering closed to new residential customers end of 2021; RRES offers netting or buy-all tariff at fixed rates for the program term; NRES for non-residential. Program-year details not verified here.
Municipal electric utilities (CMEEC members, e.g. Norwich, Groton, Wallingford) are not under the PURA EDC guidelines and set their own interconnection/net metering policies.
- Guidelines for Generator Interconnection Fast Track and Study Processes, Docket 17-12-03 RE06: https://www.eversource.com/Content/docs/default-source/ct---pdfs/guidelines-generator-inter-fast-track.pdf (retrieved 2026-11-13)
- Eversource CT - Application to Connect: https://www.eversource.com/residential/about/doing-business-with-us/interconnections/connecticut/connecticut-application-to-connect (retrieved 2026-11-13)
- PURA Distributed Generation Policy Working Group: https://portal.ct.gov/PURA/Electric/Interconnection-Policy-Working-Group (retrieved 2026-11-13)
Other utilities in Connecticut
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.