Home › Utilities › Connecticut

Connecticut

Connecticut interconnection applications

11 electric utilities serve Connecticut (EIA-861, 2025): 3 investor-owned utilitys, 7 municipal utilitys, 1 public power district. Together they serve 1,563,919 residential customers; 119,508 residential customers were on net metering at year-end 2025.

Largest utilities in Connecticut

Eversource Energy (Connecticut)Process verified

Investor-owned utility · 1,193,581 residential customers · Connecticut

Applications: PowerClerk – Eversource PowerClerk (CT)

Interconnection process and documents →
UI (United Illuminating)Partly researched

Investor-owned utility · 314,909 residential customers · Connecticut

Interconnection process and documents →
Town of WallingfordState guidance

Municipal utility · 21,426 residential customers · Connecticut

Interconnection process and documents →
City of NorwichState guidance

Municipal utility · 18,967 residential customers · Connecticut

Interconnection process and documents →
Groton Dept of UtilitiesState guidance

Municipal utility · 12,596 residential customers · Connecticut

Interconnection process and documents →
Bozrah Light & Power CompanyState guidance

Municipal utility · 2,440 residential customers · Connecticut

Interconnection process and documents →
City of South NorwalkState guidance

Municipal utility · 7,439 customers · Connecticut

Interconnection process and documents →
Norwalk Third Taxing DistrictState guidance

Municipal utility · 4,139 customers · Connecticut

Interconnection process and documents →
City of Jewett CityState guidance

Municipal utility · 2,701 customers · Connecticut

Interconnection process and documents →
Mohegan Tribal Utility AuthorityState guidance

Public power district · 75 customers · Connecticut

Interconnection process and documents →
Farmington River Power CompanyState rule applies

Investor-owned utility · 0 customers · Connecticut

Interconnection process and documents →

Export compensation among the researched Connecticut utilities: Net billing. Rules differ by utility – see each utility page.

Connecticut interconnection rule

Commission

Connecticut Public Utilities Regulatory Authority (PURA)

Interconnection rule

PURA-approved EDC Guidelines: Docket 17-12-03 RE06 'Guidelines for Generator Interconnection - Fast Track and Study Processes' (Eversource/UI, 2023-12-20) and Docket 03-01-15 RE04 'Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities' (<=25/50 kW) – Guidelines for Generator Interconnection · source

Applies to

The two electric distribution companies: Eversource (CL&P) and United Illuminating; not municipal utilities (CMEEC members)

Application form

Joint EDC interconnection request submitted through each EDC's online portal (Eversource PowerClerk); separate simplified residential inverter guideline application

Timelines

Fast Track/Study guideline: receipt confirmation 3 business days, completeness notice 10 business days, applicant 15 business days to cure; generator signs agreement within 30 business days; EDC witness test within 10 business days of request.

Fees

$200 inverter-based <=25 kW; $500 Fast Track; $1,000 Study + actual study costs (Table 1 of guideline; Eversource CT page).

Insurance

General liability per guideline Table 2: <100 kW $300,000; >100 kW-1 MW $1,000,000; >1-5 MW $2,000,000; >5 MW $5,000,000; Eversource page lists N/A for inverter-based 0-25 kW but asks proof of insurance in residential application.

External disconnect

Eversource CT: isolation device (AC disconnect) must be visible and within 10 feet of main utility panel/meter; variance needs written approval.

Export compensation

Net billing – CGS 16-244z (Residential and Non-Residential Renewable Energy Solutions programs); legacy net metering CGS 16-243h
Traditional net metering closed to new residential customers end of 2021; RRES offers netting or buy-all tariff at fixed rates for the program term; NRES for non-residential. Program-year details not verified here.

Not bound by the rule

Municipal electric utilities (CMEEC members, e.g. Norwich, Groton, Wallingford) are not under the PURA EDC guidelines and set their own interconnection/net metering policies.

LevelUp toCriteria / review / fee
Residential certified inverter-based25 kWCertified (UL 1741) inverter-based, residential single phase; Eversource page lists 0-25 kW (guideline title also references 50 kW or less) · 15 business days (Eversource table) · $200
Fast Track2000 kW0-2 MW certified, or <=25 kW certified that failed the 25 kW screens · 15 business days screens; receipt 3 BD, completeness 10 BD · $500 + actual cost of studies
Study Process>2 MW, or <=2 MW not certified, or failed Fast Track · 105-120 business days (Eversource table) · $1,000 + actual cost of studies

All 11 utilities in Connecticut

Residential customers in Connecticut per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited