Home › Utilities › Connecticut
ConnecticutConnecticut interconnection applications
11 electric utilities serve Connecticut (EIA-861, 2025): 3 investor-owned utilitys, 7 municipal utilitys, 1 public power district. Together they serve 1,563,919 residential customers; 119,508 residential customers were on net metering at year-end 2025.
Largest utilities in Connecticut
Investor-owned utility · 1,193,581 residential customers · Connecticut
Applications: PowerClerk – Eversource PowerClerk (CT)
Interconnection process and documents →Investor-owned utility · 314,909 residential customers · Connecticut
Interconnection process and documents →Municipal utility · 21,426 residential customers · Connecticut
Interconnection process and documents →Municipal utility · 18,967 residential customers · Connecticut
Interconnection process and documents →Municipal utility · 12,596 residential customers · Connecticut
Interconnection process and documents →Municipal utility · 2,440 residential customers · Connecticut
Interconnection process and documents →Municipal utility · 7,439 customers · Connecticut
Interconnection process and documents →Municipal utility · 4,139 customers · Connecticut
Interconnection process and documents →Municipal utility · 2,701 customers · Connecticut
Interconnection process and documents →Public power district · 75 customers · Connecticut
Interconnection process and documents →Investor-owned utility · 0 customers · Connecticut
Interconnection process and documents →Export compensation among the researched Connecticut utilities: Net billing. Rules differ by utility – see each utility page.
Connecticut interconnection rule
Connecticut Public Utilities Regulatory Authority (PURA)
Interconnection rulePURA-approved EDC Guidelines: Docket 17-12-03 RE06 'Guidelines for Generator Interconnection - Fast Track and Study Processes' (Eversource/UI, 2023-12-20) and Docket 03-01-15 RE04 'Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities' (<=25/50 kW) – Guidelines for Generator Interconnection · source
Applies toThe two electric distribution companies: Eversource (CL&P) and United Illuminating; not municipal utilities (CMEEC members)
Application formJoint EDC interconnection request submitted through each EDC's online portal (Eversource PowerClerk); separate simplified residential inverter guideline application
TimelinesFast Track/Study guideline: receipt confirmation 3 business days, completeness notice 10 business days, applicant 15 business days to cure; generator signs agreement within 30 business days; EDC witness test within 10 business days of request.
Fees$200 inverter-based <=25 kW; $500 Fast Track; $1,000 Study + actual study costs (Table 1 of guideline; Eversource CT page).
InsuranceGeneral liability per guideline Table 2: <100 kW $300,000; >100 kW-1 MW $1,000,000; >1-5 MW $2,000,000; >5 MW $5,000,000; Eversource page lists N/A for inverter-based 0-25 kW but asks proof of insurance in residential application.
External disconnectEversource CT: isolation device (AC disconnect) must be visible and within 10 feet of main utility panel/meter; variance needs written approval.
Export compensationNet billing – CGS 16-244z (Residential and Non-Residential Renewable Energy Solutions programs); legacy net metering CGS 16-243h
Traditional net metering closed to new residential customers end of 2021; RRES offers netting or buy-all tariff at fixed rates for the program term; NRES for non-residential. Program-year details not verified here.
Municipal electric utilities (CMEEC members, e.g. Norwich, Groton, Wallingford) are not under the PURA EDC guidelines and set their own interconnection/net metering policies.
| Level | Up to | Criteria / review / fee |
|---|---|---|
| Residential certified inverter-based | 25 kW | Certified (UL 1741) inverter-based, residential single phase; Eversource page lists 0-25 kW (guideline title also references 50 kW or less) · 15 business days (Eversource table) · $200 |
| Fast Track | 2000 kW | 0-2 MW certified, or <=25 kW certified that failed the 25 kW screens · 15 business days screens; receipt 3 BD, completeness 10 BD · $500 + actual cost of studies |
| Study Process | >2 MW, or <=2 MW not certified, or failed Fast Track · 105-120 business days (Eversource table) · $1,000 + actual cost of studies |
- Guidelines for Generator Interconnection Fast Track and Study Processes, Docket 17-12-03 RE06: https://www.eversource.com/Content/docs/default-source/ct---pdfs/guidelines-generator-inter-fast-track.pdf (retrieved 2026-11-13)
- Eversource CT - Application to Connect: https://www.eversource.com/residential/about/doing-business-with-us/interconnections/connecticut/connecticut-application-to-connect (retrieved 2026-11-13)
- PURA Distributed Generation Policy Working Group: https://portal.ct.gov/PURA/Electric/Interconnection-Policy-Working-Group (retrieved 2026-11-13)
All 11 utilities in Connecticut
- Eversource Energy (Connecticut)1,193,581
- UI (United Illuminating)314,909
- Town of Wallingford21,426
- City of Norwich18,967
- Groton Dept of Utilities12,596
- Bozrah Light & Power Company2,440
- City of South Norwalk0
- Norwalk Third Taxing District0
- City of Jewett City0
- Mohegan Tribal Utility Authority0
- Farmington River Power Company0
Residential customers in Connecticut per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.