Home › Utilities › Nebraska › Village of Lyman
Municipal utilityVillage of Lyman interconnection application
Village of Lyman is a municipal utility serving 238 customers in Nebraska (EIA-861, 2025). Gridpol files Village of Lyman interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Nebraska’s interconnection rule (Neb. Rev. Stat. 70-2001 to 70-2005 (LB 436, 2009)) applies to Village of Lyman. Levels, timelines and documents below come from that rule; Village of Lyman’s own form and portal are confirmed on the first project.
Village of Lyman at a glance
Village of Lyman
TypeMunicipal utility
EIA utility ID11346
Customers238 (EIA-861, 2025, short form: all customer classes)
Net-metered residential customersnone reported
Service territory1 county in Nebraska
Wholesale supplier / associationMunicipal Energy Agency of Nebraska (MEAN) / NMPP Energy
Documents Village of Lyman asks for
- Interconnection agreementRequired by the state rule
- Final inspection sign-offRequired by the state rule
Documents required by the Nebraska rule. Village of Lyman may ask for more on its own form; we confirm on the first project.
Nebraska interconnection rule
Nebraska Power Review Board (no PUC jurisdiction over electric rates; all retail electric service is public power)
Interconnection ruleNeb. Rev. Stat. 70-2001 to 70-2005 (LB 436, 2009) – Net metering and interconnection of qualified facilities · source
Applies toAll local distribution utilities (owner/operator of the local distribution system) - in Nebraska these are public power districts, municipal utilities and cooperatives; there is no commission-administered interconnection rule. Each utility uses its own interconnection agreement meeting the statute.
Application formUtility-specific interconnection agreement (statute requires an interconnection agreement establishing financial, interconnection, safety, performance and reliability requirements)
TimelinesCustomer must notify the utility of intent to install at least 60 days before installation and provide State Electrical Division inspection documentation before interconnection (70-2004). No utility review deadlines in statute.
FeesNo additional standby, capacity, demand, interconnection or other fee for qualified facilities; customer pays utility costs for equipment/services required only because of the interconnection; bidirectional meter at no additional cost.
InsuranceUtility may not require additional liability insurance if all safety and interconnection requirements are met (70-2003(6)(c)).
External disconnectStatute requires automatic isolation on outage and bars additional safety equipment/charges beyond statutory standards; no explicit external disconnect rule.
Export compensationNEM – Neb. Rev. Stat. 70-2002(6), 70-2003(4)-(5)
Retail-rate offset up to monthly usage; net excess generation credited at the utility's avoided cost, carried forward as monetary credits and paid out at end of annualized period. Utility may stop at 1% of average aggregate monthly peak demand forecast. Utilities may voluntarily offer net metering above 25 kW.
The statute itself binds all public power districts, municipal utilities and cooperatives; utility-specific policies apply above 25 kW.
- Neb. Rev. Stat. 70-2002 (archive.org copy): https://web.archive.org/web/20260711135129/https://nebraskalegislature.gov/laws/statutes.php?statute=70-2002 (retrieved 2026-11-13)
- Neb. Rev. Stat. 70-2003 (archive.org copy): https://web.archive.org/web/20250316073730/https://nebraskalegislature.gov/laws/statutes.php?statute=70-2003 (retrieved 2026-11-13)
- Neb. Rev. Stat. 70-2004 (archive.org copy): https://web.archive.org/web/20250311141444/https://nebraskalegislature.gov/laws/statutes.php?statute=70-2004 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.