Electric cooperativeVermont Electric Cooperative (VEC) interconnection application
Vermont Electric Cooperative (VEC) is an electric cooperative serving 36,019 residential customers in Vermont (EIA-861, 2025). Applications: Third-party portal (Vermont PUC ePUC (Net-Metering Registration / Application)). Gridpol files Vermont Electric Cooperative (VEC) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Vermont Electric Cooperative (VEC)’s official sources (see below).
Vermont Electric Cooperative (VEC) at a glance
Vermont Electric Cooperative, Inc
TypeElectric cooperative
EIA utility ID19791
Residential customers36,019 (EIA-861, 2025)
Net-metered residential customers2,665 (EIA-861, 2025)
Service territory8 counties in Vermont
How to applyThird-party portal – Vermont PUC ePUC (Net-Metering Registration / Application) · official link
Who submitsInstaller typically files registration/application for the member; Rule 5.500 application emailed to VEC for >15 kW.
Export compensationNEM – VEC Net Metering Tariff (rev. 08/01/26), Rule 5.100
Blended residential rate $0.2071/kWh; siting charge $0.05/kWh (<=150 kW, applications from 8/1/26); $0.04/kWh if member keeps RECs
<=15 kW: issues flagged within 15 days; >15 kW: approval letter within 31 days of complete application unless further analysis.
Documents Vermont Electric Cooperative (VEC) asks for
- Interconnection application formePUC registration (<=15 kW) or Rule 5.500 application (>15 kW) Gridpol prepares this.
- Other utility-specific document (when applicable)VEC interconnection approval letter attached to CPG filing (>15 kW)
How the Vermont Electric Cooperative (VEC) process runs
- <=15 kW: installer/applicant files Net-Metering Registration in ePUC (acts as interconnection application); utility flags interconnection issues within 15 days.
- 1b. >15 kW: submit Rule 5.500 interconnection application to utility first; utility approval letter by day 15 (<=25 kW) or day 31; then file Registration/Application in ePUC with letter attached.
- CPG deemed issued (conditioned on utility interconnection requirements).
- Install system; request utility production/net meter.
- Utility installs meter; system commissioned; credits begin.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $300 | Optional pre-application report | |
| $600 | Rule 5.500 application >150-500 kW | |
| $33/$66/$132 | Account setup | by number of accounts |
| $160.80 + $80 | Production meter + installation |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Registration as interconnection application | 15 kW | |
| Rule 5.500 <=150 kW | 150 kW | |
| Rule 5.500 >150 kW | 500 kW | |
| Net metering cap | 500 kW |
Registration (ePUC): roof-mounted PV <=500 kW, ground-mounted <=15 kW (guidance: ground portion up to 25 kW in mixed projects under Rule 5.105), hydro <=500 kW; Application: ground-mounted >15 kW to 500 kW.
Storage, EV and stamps
Battery storage
Not detailed on VEC page (Home Battery Enrollment form linked; Rule 5.500 covers storage devices).
Sources
- VEC - Solar and Net Metering: https://vermontelectric.coop/solar-and-net-metering (retrieved 2026-11-13)
- VT PUC - Net-Metering Registration Guidance: https://puc.vermont.gov/sites/psbnew/files/documents/nm-registration-guidance-070125.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.