Home › Utilities › Alabama › Alabama Power
Investor-owned utilityAlabama Power interconnection application
Alabama Power is an investor-owned utility serving 1,342,827 residential customers in Alabama (EIA-861, 2025). Applications: PowerClerk (Alabama Power DER PowerClerk). Gridpol files Alabama Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Alabama Power’s official sources (see below). Process PDF (July 2025) says packet provided by email while solar page says all applications now via PowerClerk - use PowerClerk.
Alabama Power at a glance
Alabama Power Co (Southern Company)
TypeInvestor-owned utility
EIA utility ID195
Residential customers1,342,827 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory59 counties in Alabama
How to applyPowerClerk – Alabama Power DER PowerClerk · official link
Who submitsCustomer or installer may submit (process document addresses 'the customer or installer' throughout; PTO letter goes to both).
Export compensationAvoided cost – Rate RGB + Rate PAE (<100 kW) / Rate CPE (≥100 kW)
No net metering. Rate RGB (supplementary/backup/maintenance) applies to customers with interconnected generation; excess sold under Rate PAE (purchase of alternate energy) for <100 kW.
Study durations: Tier I 1-2 weeks, Tier II 2-4 weeks, Tier III 4-12 weeks screening (additional studies up to 26 weeks). Design approval valid 365 days.
Documents Alabama Power asks for
- Interconnection application formInterconnection Application (submitted in PowerClerk) Gridpol prepares this.
- Single-line diagram (one-line)Guidebook 5.3.1: inverter qty/nameplate, battery kWh and charge/discharge rate, existing vs new equipment, manufacturer/model, AC disconnect details (lockable, visible blades, location relative to meter) Gridpol prepares this.
- Site plan / site layoutGuidebook 5.3.2 Gridpol prepares this.
- PV module spec sheetManufacturer equipment specification sheets (Guidebook 5.3.3)
- Inverter spec sheetManufacturer spec sheets (Guidebook 5.3.3)
- Battery spec sheet (when applicable)If storage included; SLD must show kWh and max charge/discharge
- Other utility-specific documentLabeling per Guidebook 5.3.4
- Photos (meter, main panel, equipment)Photographs of existing equipment (5.3.5); post-construction photos for Tier I/II after install (8.1.1)
- Final inspection sign-off (when applicable)AHJ electrical inspection notification, or Parallel Generator Installation Certification signed by a licensed electrician where required
How the Alabama Power process runs
- Submit Interconnection Application with SLD, site plan, spec sheets, labeling, photos (PowerClerk).
- Pay study fee if applicable (Tier II/III).
- APC Interconnection Engineer reviews; revisions/upgrades emailed if needed (upgrade estimate valid 90 days).
- Design approved -> install (approval valid 365 days). Do not buy equipment before approval.
- Brief parallel operation only for testing (Tier I/II); Tier III needs written permission for test dates.
- Notify APC of completion; submit post-construction photos (Tier I/II) or as-builts (Tier III); AHJ inspection or Parallel Generator Installation Certification signed by licensed electrician.
- Optional on-site inspection (Tier I/II) / witness test (Tier III); meter reprogrammed or replaced.
- Written permission to operate sent to customer and installer.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Tier I ≤25 kW | No study fee; study 1-2 weeks |
| $500 | Tier II >25-100 kW | Study fee; 2-4 weeks |
| $1,000 | Tier III >100 kW | Screening fee; further studies $10,000-$50,000 if required |
| $300 | Tier III optional pre-application |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Tier I | 25 kW | |
| Tier II | 100 kW | |
| Tier III | >100 kW |
Tiers by total aggregate nameplate of DER energy conversion devices (Guidebook 5.2).
Storage, EV and stamps
Battery storage
Batteries go through the same DER process; SLD must state battery qty, total kWh, max charge/discharge rate. Guidebook defines Full-Export, Limited-Export and Non-Export generation; load is not an acceptable method to limit export; power control systems (software export limits) addressed in Guidebook. V2H/V2G applications use normal process (Appendix 1): V2H needs external AC disconnect and MID; V2G must meet SoCo policy.
PE stamp
System designs >100 kW must be stamped by a licensed professional engineer (APC DER TIR Guidebook). – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Any modification incl. inverter replacement with a different model requires a new application and PTO before parallel operation.
- Proceeding before design approval with non-compliant design: 30 days to correct or power disconnected.
- Deficiencies found at on-site inspection require correction and re-inspection request.
Gridpol’s pre-submission check covers these before we file.
Sources
- Alabama Power - Solar Energy: https://www.alabamapower.com/company/clean-energy/solar-energy.html (retrieved 2026-11-13)
- APC DER Interconnection Process (July 2025): https://www.alabamapower.com/content/dam/alabama-power/pdfs-docs/Clean-Energy/APC-DER-interconnection-process.pdf (retrieved 2026-11-13)
- APC DER Technical Interconnection Requirements Guidebook V3.2 (Feb 2026): https://www.alabamapower.com/content/dam/alabama-power/pdfs-docs/Clean-Energy/APC%20DER%20TIR%20Guidebook.pdf (retrieved 2026-11-13)
Other utilities in Alabama
- Huntsville Utilities201,803
- Baldwin County El Member Corporation85,081
- Foley Board of Utilities53,818
- City of Athens52,200
- Central Alabama Electric Cooperative45,580
- City of Florence41,690
- Cullman Electric Cooperative, Inc.40,027
- Joe Wheeler Electric Member Corporation37,109
- Tallapoosa River Electric Cooperative Inc.30,157
- Sand Mountain Electric Cooperative27,485
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.